are applied in a water conservation inclining block rate. County Ordinance 93-16 requires each new development to construct a reclaimed water distribution system as a condition of wastewater service when the development is within designated areas in the Reclaimed Water Master Plan and when providing the development with reclaimed water supply is determined in the best interest of the County. Pasco County participates in the National Flood Insurance Program, administered through FEMA. All finished floor elevations are required to be above the 100-year flood elevation. These elevations are reviewed prior to construction and certified after construction. Fill Ordinance, adopted 3/05, requires permit applications and review for placement of fill greater than 5 CY on properties. Funding Source Prior Funding FY2013 Budget FY2014 Budget Future Funding Total Funding Applicant Share 30,000 90,000 120,000 Hillsborough River 30,000 90,000 120,000 Total 60,000 180,000 240,000 Matching Fund Reduction Check here if requesting a reduction in matching funds requirement pursuant to s.288.06561, F.S. Timelines August 15, 2013 Milestone Projected Date Design Start 08/15/2013 July 1, 2014 Milestone Projected Date Construction Start 07/01/2014 July 1, 2015 Milestone Projected Date Project Closeout 07/01/2015 March 15, 2015 Milestone Projected Date Construction Complete 03/15/2015 46

Return to TOC SOUTHWEST FLORIDA WATER MANAGEMENT DISTRICT FY2014 COOPERATIVE FUNDING INITIATIVE APPLICATION FORM Project Name Design & Construction - Pasco County Groves Golf Course Reclaimed Water Transmission and Storage Pond Project Project Number N462 Cooperator Pasco County Department Utilities Contact Person Pamela Wright Address 7536 State Street City Sate Zip New Port Richey, FL 34654 Phone # 727-847-8145 ext7825 Email pwright@pascocountyfl.net Project Type: X Water Supply Water Quality Flood Protection Natural Systems Strategic Initiatives: Water Quality Maintenance and Improvement Water Quality Monitoring Alternative Water Supply Conservation X Reclaimed Water Regional Water Supply Planning Emergency Flood Response Floodplain Management Minimum Flows and Level Establishment and Monitoring Minimum Flows and Levels Recovery Natural Systems Conservation and Restoration Natural Systems Identification and Monitoring Indicate All Counties to Benefit From Project: Charlotte Citrus Desoto Hardee Hernando Highlands Hillsborough Lake Levy Manatee Marion X Pasco Pinellas Sarasota Sumter Polk Project Description: This proposed multi-year FY2013 and FY2014 project is for the design and construction of an 8-inch diameter reclaimed water line from the County's reclaimed water transmission main on US41 to a new isolated pond on The Groves Golf Course property in Land O'Lakes. The project will provide reclaimed water for irrigation at the golf course and some common areas within the community. The project will supply The Groves Golf Course and common areas with 0.25 million gallons per day (mgd) of reclaimed water to offset 0.18 mgd of existing irrigation (current source groundwater wells). The estimated cost/benefit amortized at 8 percent over 30 years is $0.26 per thousand gallons offset. The total cost of the project is estimated to be $200,000. A request for 50% ($100,00) of District funding was submitted in FY2013; however, the project schedule shows that only $25,000 of the share will be used in FY2013. Therefore, we are submitting a request for the remaining share ($75,000) in FY2014. Describe your organizations efforts in developing, implementing and enforcing water conservation and flood protection ordinances. Pasco County adopted Ordinance 01-08 requiring the following: one day/week irrigation restrictions for potable water; curtailed use of potable water for irrigation when rain has occurred within 24 hours; scheduled availability and restricted use of reclaimed water irrigation to distribute limited supply to as many customers as possible; washing of non-business, personal vehicles only using low volume methods and over non-impervious surfaces; prohibiting aesthetic uses of water unless such use also provides a necessary aeration or water quality benefit; and the use of reclaimed water for road construction activities when available. Enforcement of this ordinance is by designated County personnel and law enforcement officers. During Water Year 2012, 100% of Pasco County Utilities' wastewater was reused. The bulk rate charged for the use of reclaimed water is $0.47 per 1,000 gallons (normal rate), $0.21 per 1,000 gallons (surplus rate), and a flat rate of $10.26 per month residential irrigation. Pasco County's potable water rates are applied in a water conservation inclining block rate. County Ordinance 93-16 requires each new development to construct a reclaimed water distribution system as a condition of wastewater service when the development is within designated areas in the Reclaimed Water Master Plan and when providing the development with reclaimed water supply is determined in the best interest of the County. Pasco County participates in the National Flood Insurance Program, administered through FEMA. All finished floor 47

are applied in a water conservation inclining block rate. County Ordinance 93-16 requires each new development to construct a<br />

reclaimed water distribution system as a condition of wastewater service when the development is within designated areas in the<br />

Reclaimed <strong>Water</strong> Master Plan and when providing the development with reclaimed water supply is determined in the best interest<br />

of the County. Pasco County participates in the National Flood Insurance Program, administered through FEMA. All finished floor<br />

elevations are required to be above the 100-year flood elevation. These elevations are reviewed prior to construction and certified<br />

after construction. Fill Ordinance, adopted 3/05, requires permit applications and review for placement of fill greater than 5 CY on<br />

properties.<br />

Funding Source<br />

Prior Funding<br />

FY2013<br />

Budget<br />

FY2014<br />

Budget<br />

Future<br />

Funding<br />

Total Funding<br />

Applicant Share 30,000 90,000 120,000<br />

Hillsborough River 30,000 90,000 120,000<br />

Total 60,000 180,000 240,000<br />

Matching Fund Reduction<br />

Check here if requesting a reduction in matching funds requirement pursuant to s.288.06561, F.S.<br />

Timelines<br />

August 15, 2013<br />

Milestone<br />

Projected Date<br />

Design Start 08/15/2013<br />

July 1, 2014<br />

Milestone<br />

Projected Date<br />

Construction Start 07/01/2014<br />

July 1, 2015<br />

Milestone<br />

Projected Date<br />

Project Closeout 07/01/2015<br />

March 15, 2015<br />

Milestone<br />

Projected Date<br />

Construction Complete 03/15/2015<br />