Tampa Bay Region - Southwest Florida Water Management District
Tampa Bay Region - Southwest Florida Water Management District
Tampa Bay Region - Southwest Florida Water Management District
Create successful ePaper yourself
Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.
eclaimed water distribution system as a condition of wastewater service when the development is within designated areas in the<br />
Reclaimed <strong>Water</strong> Master Plan and when providing the development with reclaimed water supply is determined in the best interest<br />
of the County. Pasco County participates in the National Flood Insurance Program, administered through FEMA. All finished floor<br />
elevations are required to be above the 100-year flood elevation. These elevations are reviewed prior to construction and certified<br />
after construction. Fill Ordinance, adopted 3/05, requires permit applications and review for placement of fill greater than 5 CY on<br />
properties.<br />
Funding Source<br />
Prior Funding<br />
FY2013<br />
Budget<br />
FY2014<br />
Budget<br />
Future<br />
Funding<br />
Total Funding<br />
Applicant Share 50,000 50,000 100,000<br />
Coastal Rivers 50,000 50,000 100,000<br />
Total 100,000 100,000 200,000<br />
Matching Fund Reduction<br />
Check here if requesting a reduction in matching funds requirement pursuant to s.288.06561, F.S.<br />
Timelines<br />
June 15, 2014<br />
Milestone<br />
Projected Date<br />
Construction Complete 06/15/2014<br />
November 1, 2012<br />
Milestone<br />
Projected Date<br />
Design Start 11/01/2012<br />
September 1, 2013<br />
Milestone<br />
Projected Date<br />
Construction Start 09/01/2013<br />
September 30, 2014<br />
Milestone<br />
Projected Date<br />
Project Closeout 09/30/2014<br />