ecome outmoded for effective reclaimed water supply. Recent re-evaluations confirm that the San Christopher Drive site, on which<br />
the smaller tank is situated, can accommodate two, new 1.0 mg, prestressed concrete, ground storage tanks. (Please refer to the<br />
two site drawings included with this grant request.) With increased storage capacity at this site, the City could both add new<br />
residential reclaimed water customers and further reduce the amount of reclaimed water discharged into St Joseph Sound. For<br />
example, in May 2012, although the City was able to stop discharges to the Sound for short periods of time, it did discharge some<br />
water into the Sound every day and the average rate of discharge was 0.257 mgd. With 2.0 mg storage on the San Christiopher<br />
Drive site, instead of 0.5 mg, the City could have avoided discharges to the Sound for 14 days and used that avoided discharge as<br />
a source of supply to 360 to 400 new customoers. Changing the type and capacity of the storage tanks does not require a change<br />
in the available pumping operations or in a need for additional operations or maintenance staff. The City requests SWFWMD grant<br />
assistance to make this important change for improved water resource management.<br />
Funding Source<br />
Prior Funding<br />
FY2013<br />
Budget<br />
FY2014<br />
Budget<br />
Future<br />
Funding<br />
Total Funding<br />
Applicant Share 880,000 880,000<br />
Pinellas Anclote 880,000 880,000<br />
Total 1,760,000 1,760,000<br />
Matching Fund Reduction<br />
Check here if requesting a reduction in matching funds requirement pursuant to s.288.06561, F.S.<br />
Timelines<br />
San Christopher Drive Reclaimed <strong>Water</strong> Storage Tank<br />
Milestone<br />
Projected Date<br />
Project Design 10/25/2013<br />
Begin Project Construction 01/06/2014<br />
Complete Project Construction 09/26/2014<br />
120