5 Learning from already implemented CWs (in Albania and the Balkan region)<br />

An additional settling chamber was added during reconstruction works in 2010. The flow diagram for the<br />

wastewater treatment is given in Figure 5.5 (p. 59).<br />

Figure 5.5: Flow diagram of constructed wetland at SOS children’s village,<br />

Tirana (Gjinali et al. 2011)<br />

The raw wastewater is pre-treated in an Imhoff tank, which is located at the lowest point of the area, next<br />

to the pumping chamber and a second settling chamber that is used since first reconstruction. This<br />

construction is the result of using the old collection tank by reconstructing it to a Imhoff tank with second<br />

settling chamber and pumping chamber between Inhoff tank and settling chamber. Originally this re-use of<br />

already existing parts should help saving money.<br />

Figure 5.6: Imhoff tank and settling tank at the constructed<br />

wetland plant in November 2011 (Niebel 2011)<br />

59