7 Presentation of the institutional framework<br />

Necessary steps that have to be taken are:<br />

• Identification of problems and prioritisation by LGU and communication with qark.<br />

• Application of LGU to ADF for project, that has to be approved by qark.<br />

• LGU has to secure 10 % of construction costs as local contribution as well as operation and<br />

maintenance. Coordination with utility for O&M, if area is covered by utility.<br />

• Organising public meetings with the inhabitants to secure participation of inhabitants. Regular<br />

information exchange and discussions between inhabitants and LGU and the village leader to<br />

decide on technology. Perhaps organising inhabitants in beneficiary group.<br />

• Agreement between donors and beneficiaries to guarantee the commitment of beneficiaries and<br />

clarify their responsibilities.<br />

• Involvement of an engineer for the design of the technical solution. Call for tenders for<br />

construction, design and supervision and their selection.<br />

• Application to qark for construction permission.<br />

• Preparation of O&M manual by ADF.<br />

• Tariff approval by WRA.<br />

• Ensure supervision after project implementation finished.<br />

These are the main steps that could be identified from the project examples given before. Every new project<br />

can vary from each other a little bit.<br />