General Services<br />

necessitated in excess of 3,000 cards being programmed. In 2008 it is planned to integrate the issue<br />

process into the Human Resources induction programme for new employees.<br />

Key areas of the campus continue to be risk appraised for conversion to access control and it is planned to<br />

roll-out the system to all staff car parks in 2008.<br />

The department is managed by Jim Mitchell and the staff compliment in 2007 was 16.<br />

Technical Services<br />

Technical Services is responsible for the management, design, installation and maintenance of engineering<br />

services within the hospital. It is also involved in the broader areas of energy management and sustainability<br />

planning. Four key areas of activity in 2007 were:<br />

New Developments<br />

Due to the amount, complexity and cost of building services in new developments, systematic inspections<br />

and routine maintenance were devised to ensure continuity of good service and economy of resources. New<br />

maintenance schedules were planned using the manufactures specifications with O&M manuals. As most<br />

of the equipment was on a first year schedule, isolation and hazards had to be identified to ensure continuous<br />

support to the hospital. All plant equipment was identified and ranked to ascertain the impact of a failure to<br />

the hospital. Planned preventative maintenance was introduced to avoid disruption to the activities of the<br />

various areas covered, i.e. chillers were maintained in off peak hours. The new Allied Health Department<br />

Refurbishment came on stream in 2007. The process of integrating new developments into the campus has<br />

been a demanding, challenging and interesting one and we look forward to implementing the lessons learned<br />

as future projects come on stream during 2008.<br />

Estates <strong>St</strong>rategy Technical Services Projects<br />

Technical Services was a key stakeholder in the development of the Estates <strong>St</strong>rategy Group. Its Projects<br />

Team completed a substantial number of new projects with the combination of in-house technical services<br />

staff and outside contractors.<br />