<strong>Chip</strong>BLASTER, Inc. 19<br />
8.0. MECHANICAL INSTALLATION:<br />
8.1. PLUMBING INSTALLATION:<br />
8.1.1. When you are ready to start the installation of the <strong>Chip</strong>BLASTER unit you first<br />
must locate the high-pressure hoses that <strong>Chip</strong>BLASTER Inc. has provided.<br />
Connect the female end to the <strong>Chip</strong>BLASTER outlet 1 and 2 hoses located on the<br />
filter side lower right, then connect the other ends to the machining center (spindle,<br />
turret or other designated tool/orifice).<br />
8.1.2. Next you will want to find the 1” clear hose, this will be for the return line.<br />
For units that do not have a <strong>Chip</strong>BLASTER supplied return/transfer pump, connect<br />
the 1” clear hose to the 1” inlet on the <strong>Chip</strong>BLASTER reservoir tank. The other<br />
end will connect either to the existing machining center coolant pump.<br />
For units that are supplied with a return/transfer pump, connect the 1” clear hose to<br />
the inlet of the return/transfer pump and connect the other end to the 1” hose barb<br />
of the standpipe assembly after installation on the machine tool sump.<br />
8.1.3. For best use, the inlet of the 1” clear hose in the machining center coolant sump<br />
should be approximately 1” from the bottom of the coolant Sump. If using the<br />
standpipe assembly position the suction pipe (pipe with 45 degree taper) 1” from<br />
bottom of machine tool sump, this should be connected to the inlet of the<br />
return/transfer pump.<br />
8.1.4. Connect the 1 1/2” hose to the overflow outlet barb on the side of the<br />
<strong>Chip</strong>BLASTER tank. The other end of this hose should go to the machining center<br />
coolant tank. If using the standpipe assembly connect the 1 1/2” to the hose barb.<br />
!<br />
THE RETURN PUMP MUST BE WITHING 12 FEET OF THE<br />
MACHINING CENTER COOLANT TANK.<br />
9.0. ELECTRICAL INSTALLATION:<br />
!<br />
INSTALLER MUST COMPLY WITH ALL LOCAL AND NATIONAL<br />
ELECTRICAL CODES AND SAFETY GUIDELINES WHEN MAKING<br />
ELECTRICAL CONNECTIONS TO THE <strong>Chip</strong>BLASTER.<br />
REFER TO THE ELECTRICAL DRAWING(S) (SECTION 20) DURING<br />
ELECTRICAL INSTALLATION. ALSO REFER TO THE FOOTPRINT<br />
DRAWING (SECTION 23) FOR RECOMMENDED WORK CLEARANCE.<br />
!<br />
BEFORE OPENING THE MACHINING CENTER CABINET<br />
DISCONNECT AND LOCKOUT / TAGOUT ALL<br />
ELECTRICAL ENERGY SOURCES.<br />
*NOTE-The <strong>Chip</strong>BLASTER is equipped to accept control interface voltages of 115vac or 24vdc. Please<br />
make sure the appropriate control voltage relays are installed in CR1 through CR4. Before applying<br />
control power to the unit. The unit is shipped from the factory with 115vac relays installed in CR1, CR2,<br />
CR3, CR4. We also include the 24vdc relays loose in the electrical cabinet for interfacing convenience<br />
to 24vdc machines.<br />
8.0 – 9.0