API-RP-576
API ICP Self Study Notes API ICP Self Study Notes
5.8 Rough Handling Fion Zhang/ Charlie Chong
Rough handling can occur during; • shipment, • maintenance, or • installation. Fion Zhang/ Charlie Chong
- Page 131 and 132: Corrosion is a basic cause of many
- Page 133 and 134: http://www.valveworld.net/safetyequ
- Page 135 and 136: Because there is metal-to-metal con
- Page 137 and 138: Basic interferometry The interferen
- Page 139 and 140: As light travels through the Optica
- Page 141 and 142: Example: 1 a series of fringes indi
- Page 143 and 144: Fion Zhang/ Charlie Chong
- Page 145 and 146: Fion Zhang/ Charlie Chong
- Page 147 and 148: Causes of damaged valve seats; 1. C
- Page 149 and 150: Spring failures. 2 modes of failure
- Page 151 and 152: Fion Zhang/ Charlie Chong
- Page 153 and 154: Fion Zhang/ Charlie Chong The size
- Page 155 and 156: Incorrect calibration of pressure g
- Page 157 and 158: How to adjust a PSV The spring dete
- Page 159 and 160: http://www.cicpro.com/products/safe
- Page 161 and 162: The design of the shroud must be su
- Page 163 and 164: Adjustment pin affect the character
- Page 165 and 166: Fion Zhang/ Charlie Chong
- Page 167 and 168: 5.5 Plugging and Sticking Fion Zhan
- Page 169 and 170: 5.6 Misapplication of Materials Fio
- Page 171 and 172: Typical ball valve material selecti
- Page 173 and 174: Fion Zhang/ Charlie Chong
- Page 175 and 176: Fion Zhang/ Charlie Chong
- Page 177 and 178: 5.7 Improper Location, History, or
- Page 179 and 180: Fion Zhang/ Charlie Chong V-203
- Page 181: Fion Zhang/ Charlie Chong
- Page 185 and 186: The following table summarises the
- Page 187 and 188: Greater differentials between opera
- Page 189 and 190: 5.10 Improper Discharge Piping Test
- Page 191 and 192: Fion Zhang/ Charlie Chong When hydr
- Page 193 and 194: Fion Zhang/ Charlie Chong the bello
- Page 195 and 196: 5.11 Improper Handling, Installatio
- Page 197 and 198: Rupture disk problems are often ass
- Page 199 and 200: Fion Zhang/ Charlie Chong
- Page 201 and 202: Fion Zhang/ Charlie Chong
- Page 203 and 204: Fion Zhang/ Charlie Chong
- Page 205 and 206: Fion Zhang/ Charlie Chong
- Page 207 and 208: Fion Zhang/ Charlie Chong
- Page 209 and 210: 6.1 Reasons for Inspection and Test
- Page 211 and 212: 6.2.2 Safety 1. proper authority an
- Page 213 and 214: National Board approved ASME stamps
- Page 215 and 216: The Kdr or aW value can vary accord
- Page 217 and 218: 6.2.5 Removal of Device from System
- Page 219 and 220: Exercise; Dismantling of PSV Fion Z
- Page 221 and 222: Highly Reactive Materials Water-Rea
- Page 223 and 224: 6.2.7 Inspection of Adjacent Inlet
- Page 225 and 226: Fion Zhang/ Charlie Chong Rupture d
- Page 227 and 228: 6.2.10 Visual Inspection This inspe
- Page 229 and 230: 6.2.11 Dismantling of Valve. Disman
- Page 231 and 232: Fion Zhang/ Charlie Chong
Rough handling can occur during;<br />
• shipment,<br />
• maintenance, or<br />
• installation.<br />
Fion Zhang/ Charlie Chong