Otonabee River Bridge<br />

Retaining Wall Repair


TSW<br />

Parks Canada<br />

Township<br />

of<br />

Selwyn<br />

MNR<br />

Site<br />

Multiple jurisdictions<br />

Transport<br />

Canada<br />

ORCA<br />

OPG


Property ownership


Ownership


Design


Design<br />

Barrier<br />

Wall


Construction<br />

- work is anticipated to be performed from top of embankment<br />

- remove scrub brush from embankment<br />

- excavate dry stone wall from embankment<br />

- coordination with TSW Water Control Manager & OPG<br />

- dewater at the toe of embankment<br />

- form and pore concrete footing and pad; match existing footing<br />

and match old bridge abutment<br />

- form and pore cast-in-place concrete wall<br />

- backfill and restore embankment<br />

Note: closure of one traffic lane will be fully dependant on the site<br />

conditions that could be encountered when construction begins. The<br />

stability of the embankment is to be confirmed by the contractor.


Questions/comments<br />

Peter Nielsen, C.E.T.<br />

Manager of Technical Services<br />

705-775-2737 ext. 322<br />

pnielsen@county.peterborough.on.ca