CIVIC CENTRE CAPITAL REQUIREMENTS<br />

SUMMARY OF PROJECT COSTS £000's<br />

2006/7 2007/8 2008/9 2009/10 2010/11 20011/12 2012/13 2013/14 Total<br />

Chiller Valve Replacement 12 ~ ~ ~ ~ ~ ~ ~ 12<br />

Water Tank Replacement 61 ~ ~ ~ ~ ~ ~ ~ 61<br />

Cooling Towers 285 ~ ~ ~ ~ ~ ~ ~ 285<br />

Electrical Infrastructure* 100 600 500 ~ ~ ~ ~ ~ 1,200<br />

Access / DDA ~ ~ 150 150 150 ~ ~ ~ 450<br />

Ro<strong>of</strong> / Drainage Gulleys 50 50 50 50 50 ~ ~ ~ 250<br />

WC Modernisation 18 ~ 100 100 100 32 ~ ~ 350<br />

AHU Replacement ~ ~ ~ 500 200 ~ ~ ~ 700<br />

Internal Building Fabric ~ ~ ~ 100 ~ ~ ~ ~ 100<br />

Multi Storey Car Park ~ ~ ~ ~ ~ 600 700 ~ 1,300<br />

Daylight Lighting ~ ~ 150 150 150 150 ~ ~ 600<br />

Lift Controls Gear ~ 400 ~ ~ ~ ~ ~ ~ 400<br />

Window Programme ~ ~ ~ ~ ~ ~ 50 50 100<br />

Asbestos Removal 1N ~ ~ 25 ~ ~ ~ ~ ~ 25<br />

Council Chamber refurbishment ~ ~ 200 ~ ~ ~ ~ ~ 200<br />

External Walk Way Repairs ~ 20 20 20 ~ ~ 20 20 100<br />

Replace Saltzer Pumps ~ 30 ~ ~ ~ ~ ~ ~ 30<br />

Exterior Lighting ~ ~ 30 ~ ~ ~ ~ ~ 30<br />

Balcony Repairs ~ ~ ~ ~ ~ 100 ~ ~ 100<br />

Fan Coil Replacement ~ ~ ~ ~ 500 750 750 1,000 3,000<br />

Total 526 1,100 1,225 1,070 1,150 1,632 1,520 1,070 9,293<br />

Notes:<br />

(vi) *Electrical Infrastructure - only £300K currently approved for 2007/8. Requires approval <strong>of</strong> £300K 2007/8 and £500K 2008/9<br />

(vii)<br />

(viii)<br />

(ix)<br />

(x)<br />

WC modernisation £18K 2006/7 - being funded from Leaders Initiative.<br />

Suggest Lift Controls be included in 2007/8 program as new supplier has been awarded the lift maintenance contract.<br />

Council Chamber modernisation provisionally programmed 2008/9 and to be reviewed in the context <strong>of</strong> Civic Centre redevelopment<br />

opportunities.<br />

Asbestos removal 1 North provisionally programmed for 2008/9. Should be reviewed in the context <strong>of</strong> the review <strong>of</strong> the Cashiers service.<br />

Removal <strong>of</strong> Asbestos could then be incorporated into future scheme for change <strong>of</strong> use <strong>of</strong> premises.<br />

75