15.07.2014 Views

Vigilance Compedium - CCL

Vigilance Compedium - CCL

Vigilance Compedium - CCL

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

General Manager also entered an agreement with the Ex-Servicemen Transport Company<br />

even though the Area Authorities were not delegated powers to enter into an extended<br />

contract involving more than one crore rupees. Such an arbitrary action was taken by the<br />

Area authorities despite being aware of the fact that the per ton rate of transportation for<br />

the same distance slab finalized by the Headquarters in favour of civilian contractor under<br />

Comprehensive Tender was much less when compared to the per ton rate of<br />

transportation cost paid / being paid against arbitrarily extended period of contract in<br />

favour of Ex-Servicemen Transport Company in the subject case.The per ton<br />

transportation cost came down further when fresh tenders were finalized and work was<br />

awarded to eligible civilian party during the intervening period of extended contract in<br />

favour of ESM company for one more year. In this view of the matter, the Headquarters<br />

terminated the extended period of contract in half way to pave way for civilian<br />

contractor to take up the work on the basis of work award. Such arbitrarily extended<br />

period of contract at a higher rate of transportation resulted in financial loss to the<br />

Company. Further, the action of Headquarters management in termination of the contract<br />

dragged the Company to litigation by means of lodging a writ petition against the<br />

Company by the ESM Company for breach of contract.<br />

d. To further bring advantage to the ESM Company during the extended period of contract,<br />

the Project Officers of the Washery on their part, failed to restore the weigh bridge that<br />

was located very near to the unloading point even though the components required for its<br />

restoration were procured by Washery even four months before the extended period of<br />

contract. The said failure resulted in the coal laden ESM trucks to cover an extra distance<br />

of 2 Kms. more to reach to another weigh bridge at a far off distance for weighment and<br />

to return to the unloading site. Such inaction / failure of the Project caused financial loss<br />

to the Company.<br />

e. Even though the coal was transported through a shorter route from the adjacent Collieries,<br />

the Project officials accepted bills for payment at the rates applicable for longer route and<br />

thereby caused unauthorized payment.<br />

PUNITIVE ACTIONS<br />

a. Since some of the executives involved were of M-2 level Officers, the entire case was<br />

referred to the CVC seeking their advice. All the responsible officials were proceeded<br />

with major penalty proceedings as per CVC’s advice.<br />

b. The charges leveled against responsible officials were established beyond doubt at the<br />

enquiry and major penalty was awarded to the concerned executives who were in<br />

employment at that point of time.<br />

c. The HOD of transportation Department at the Headquarters, even though retired from<br />

service, was awarded a penalty of ‘deemed dismissal’ by the Chairman, CIL.

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!