Table 3.<br />

Significant Results<br />

The successful completion of the Comet Vale Resource Extension drilling program has doubled the strike<br />

extent of the Sand George resource.<br />

The Resource Extension drilling has extended the potential reserves for a further 500m, down to a vertical<br />

depth of 250m with significant drill intersections being made at depths up to 400 metres below ground level.<br />

A new lode of 8m @ 3.60g/t Au was intercepted beneath the Sand Prince West orebody in the precollar of<br />

JVD006 which was planned to test depth continuity of the Sand George orebodies.<br />

Mineralised wide lode intersections which contain narrow high-grade intervals with assays in excess of 15g/t<br />

Au include:<br />

• 3m @ 6.32g/t Au (92-95m) including 1m @ 15.24g/t Au (JVC001)<br />

• 1m @ 17.30g/t Au (20-21m) (JVD001)<br />

Hole ID Collar Collar Interval Interval Intersection Grade<br />

Northing Easting From (m) To (m) Width (m) (g/t Au)<br />

JVC001 13100 7770 92 95 3 6.32<br />

including 93 94 1 15.24<br />

JVC002 13075 7810 53 54 1 4.2<br />

JVC004 13025 7800 75 75.3 0.3 4.55 @ BOH<br />

JVD 12950 7800 20 21 1 17.3<br />

JVC005 12850 7825 38 39 1 3.54<br />

JVD006 13000 7600 42 50 8 3.60<br />

8. Development Budget<br />

including 48 49 1 13.64<br />

The table below shows a summary of the budgeted, expenditure items for the next 2 years mine development<br />

at the Sand Queen Gold Mine.<br />

2 Year Summary of level Development<br />

4L<br />

5L<br />

Total Metres<br />

Total Millholes<br />

732 m<br />

522 m<br />

1,394 m<br />

23 units<br />

Infrastructure for 2 Years of Development<br />

Level and Rising Development $ 1,882,210<br />

Shaft Refurishment 3L to 5L $ 75,000<br />

Winder (Purchase, Install and Commission) $ 200,000<br />

Diamond Drilling (New Rig and Diamond Drill Cuddies) $ 95,395<br />

Truck/Bogging (Locomotive and Boggers) $ 41,000<br />

Power/Ventilation/Pumps $ 218,000<br />

Total Expenditure $ 2,511,605<br />

Page 29