Section 8<br />
Independent Geologist’s Report<br />
and south of the Sand Prince mine workings, 13 RC holes over the Sand Queen East gold in soil anomaly, one<br />
diamond drill hole to evaluate the southern plunge of the Comet Vale lode, one RC hole and two diamond<br />
drill holes at Coonega.<br />
7. Exploration by Reed Resources Ltd ( 1998 – 2007)<br />
In September 1998, Mr David Reed acquired Destra Corporation’s 100% interest in the Comet Vale project.<br />
Since that time exploration has been directed at defining extensions to, or repetitions of, the Sand Queen-<br />
Gladsome gold mineralisation. This exploration program has met with a great deal of success, with the<br />
identification of new zones of gold mineralisation that have significantly added to Reed Resource’s resource<br />
inventory.<br />
7.1 Exploration 1998 – 2002 (after Collins, PLF)<br />
1999: Two deep diamond drill holes (CV11 and CV12) with RC pre-collars (DRC1, 2) were drilled in July-<br />
August 1999 to test for possible depth extensions of the Comet Vale lode to the north of the Gladsome<br />
mine. A third RC drill hole (DRC3) was drilled to test a gold in soil anomaly at the Sand Queen East<br />
prospect.<br />
2000: Exploration focused on prospective ground to the south of the Sand Queen-Gladsome mine, with<br />
5,983m of drilling in 66 RC percussion drill holes (DRC4-DRC69). This work resulted in the discovery<br />
of two, closely-spaced, sub-parallel, high-grade gold lodes, referred to as the ‘Sand George prospect, and<br />
centred about 300m south of the Sand Queen shaft. Preliminary tonnage and grade estimates indicated<br />
a resource of the order of 115,000 tonnes grading 12g/t Au.<br />
2001: Exploration included an evaluation of the results of the 1999-2000 drilling programs along the<br />
Gladsome-Sand Queen-Sand George-Sand Prince ‘line’ of lodes, 3-D geological modelling of the Sand<br />
George lode, and an estimation of a mineral resource. Resource modelling indicated 85,549 tonnes<br />
grading 14.2g/t Au in the main Sand George lode. Environmental and hydro-geological studies were<br />
completed in preparation for dewatering of the Sand Queen main shaft.<br />
2002: Surface exploration focused on the Sand George deposit and the potential for repetition of highgrade<br />
lodes elsewhere along the Comet Vale lode structure. In addition a comprehensive data base<br />
was established for all current and previous exploration. Work commenced on dewatering and<br />
rehabilitation of the Sand Queen main shaft to gain underground access to source any remnant ore, for<br />
geological mapping, and to assess use of the shaft as a means of underground access to the Sand George<br />
deposit.<br />
7.2 Exploration 2003 – 2007 (after Potter, D)<br />
2003: Dewatering and rehabilitation of the Sand Queen main shaft to below No. 4 Level was completed and<br />
geological mapping/sampling of the 4 Level south drive revealed a change in structural position of the<br />
lode below 4 Level. Infill RC drilling at the southern end of the Sand Queen identified an Indicated<br />
Mineral Resource of 6,500 tonnes at 19.7g/t Au (4,100 ounces of contained gold). Exploration of the<br />
Comet Vale lode structure at the Sand George prospect included diamond drilling to test the deeper<br />
lode positions, re-assessment of the geological model, and recalculation of the Mineral Resource<br />
(155,000 tonnes at 11.6g/t Au, 58,052 ounces gold). Drilling also identified a shallow, flat-lying<br />
structure referred to as the Sand Prince West lode with a resource (undefined) of 77,000 tonnes grading<br />
3.9g/t Au.<br />
2004: Exploration at the Comet Vale project during 2004 continued to target the area’s gold potential with<br />
most of the work being confined to M29/52 and M29/321. Most exploration has focussed on definition<br />
of a mineable resource at the Sand George deposit together with an evaluation of various mining<br />
options for feasibility studies for development of a mine. A new resource of 205,160 tonnes grading<br />
10.6g/t for 70,000 ounces was calculated using a 2g/t cut-off grade.<br />
2005: Development focussed on Sand Prince West where a total of 93 RC holes were drilled and a resource of<br />
34,881t grading 2.94g/t for 3,300 ounces was defined.<br />
2006: Exploration at the Comet Vale project during 2006 involved:<br />
Page 26