SPECIAL CONDITIONS OF FORMING A PART OF THIS CONTRACT<br />

1. All works are to be executed and measured in conformity with the relevant upto date I.S. Specifications,<br />

National Building Code and Orissa Detailed Standard Specification, I.R.C. and MOS&T Code of practice and<br />

specification.<br />

In case of variation in the norms, specifications and methods of execution and measurement as prescribed in<br />

the different codes and in case of doubt regarding means and scope of specification of any items, the<br />

decision of Managing Director, <strong>IDCO</strong> will be final and binding in this regard. No extra monetary compensation<br />

over and above the accepted agreement rates for various item will be paid to the Contractor on this Account.<br />

2. In case of any technical specification not covered in the relevant I.S. Specifications, National Building Code<br />

and Orissa Detailed Standard Specification, I.R.C. and MOS&T Code etc., the specification given by the<br />

Consultant/ Purchaser/ <strong>IDCO</strong> is final and binding on the Contractor.<br />

3. Every tenderer must examine the detailed specification of Orissa Public Works Department, relevant IS<br />

specifications and provisions in National Building Code and IRC, MOS&T specification before submitting his<br />

tender. The right is reserved with the Corporation without impairing the contract to make such increase or<br />

decrease in the quantities or items of work mentioned in the schedule of quantities attached to the tender<br />

notice as may be considered necessary to complete the work fully and satisfactorily. Such increase/ decrease<br />

shall in no case invalidate the contract or rates. However, increase in quantity of any particular item upto 25%<br />

of the tendered quantity the rate quoted/accepted will remain in force. It shall be definitely understood that the<br />

Corporation does not accept any responsibility for the correctness or completeness of the quantities shown in<br />

the schedule. The schedule is liable to alternation by omission or addition or deduction and such omissions,<br />

additions and deductions shall in no case invalidate the contract and no extra monetary compensation will be<br />

entertained. At any point of time, the contract can be terminated if so desired by the Corporation without<br />

assigning any reason thereof after issue of notice in writing by the Corporation before 30 days of the<br />

proposed date of termination. In the event of such termination, the Contractor shall not be entitled to any<br />

monetary compensation whatsoever.<br />

4. It is the responsibility of the Contractor to ensure production of quality concrete of required strength and<br />

durability which shall be ascertained by regular field and Laboratory tests in accordance with IS:516 and<br />

other relevant Indian Standards. All cost involving such test shall be borne by the Contractor.<br />

5. The Contractor shall provide at site required proper plant and machinery including testing equipment’s,<br />

instruments etc., for concrete at his own cost. The Contractor shall not be paid any thing extra for carrying out<br />

any test as directed either at site or at Laboratory. In case of Laboratory test , the name of the Laboratory or<br />

Institutions shall be suggested by <strong>IDCO</strong>.<br />

6. INSURANCE AGAINST FIRE, ACCIDENT, DAMAGE AND THEFT:<br />

a) The Contractor shall ensure that he and his sub-contractors use one safe and reliable equipment’s.The<br />

Contractor shall be responsible for the safe custody and storage of all equipment’s, materials, construction<br />

tools, tackles and machinery at the site, which are covered by this contract. All Contractors’ equipment shall<br />

be at the sole risk of the Contractor. The Contractor shall take necessary insurance cover for all tools, tackles<br />

and other constructions equipment’s and machinery and materials, owned hired or used by the Contractor for<br />

performance of the works but which does not form a part of the permanent work. The Contractor shall take<br />