7. All the measurement shall be jointly taken by Contractor’s representative and Engineer-in-charge of the<br />

work at site and they shall be jointly signed. Any dispute arising out of this shall be referred to the<br />

Authorized Officer’s of the Corporation and his decision shall be binding on both the parties.<br />

8. Purchase vouchers of materials in original shall be produced for verification on demand by the Authorized<br />

Officer of the Corporation. Carriage or transport charges shall not be considered for the purpose of this<br />

payment.<br />

9. Any deviation between specifications, schedule of quantities and drawings found by the Contractor, the<br />

same shall be brought to the notice of the Authorized Officer of the Corporation immediately.<br />

10. Rates shall be quoted both in figures and in words in clear legible writing. No overwriting is allowed. All<br />

scoring and cancellation should be countersigned by the Tenderer. In case of illegibility, the interpretation,<br />

the decision of the Engineer-in-charge of work shall be final. All entries shall be in English Language. In<br />

case if on check there are differences between the rates given by the bidder in words and figures or in the<br />

amounts worked out by him, the following procedure should be followed.<br />

(iv)<br />

(v)<br />

(vi)<br />

When there is difference between the rates in figures and in words, the rates which correspond to the<br />

amount worked out by the bidder shall be taken as correct.<br />

When the amount of an item is not worked out by the bidder or it does not correspond with the rate<br />

retain either in figures or words, then rate quoted by the bidder in words shall be taken as correct.<br />

When the rate quoted by the bidder in figures and in words tallies but the amount is not worked out<br />

correctly, the rates quoted by the bidder shall be taken as correct and not the amount.<br />

11. In case of doubt regarding the meaning and scope of specifications of different items of works and in case<br />

of variation in the provisions of IS Specification, National Building Code and Orissa Details Standard<br />

Specification and I.R.C., MOS&T specification, the decision of the Managing Director, <strong>IDCO</strong> will be final and<br />

binding, and no extra claim over and above the accepted agreement, rules will be payable to the Contractor<br />

on this account.<br />

12. The Contractor shall carry out the electrical, sanitary and water supply through the agency as approved by<br />

the Corporation whose name shall be submitted to the authorized officer for approval. All works carried out<br />

shall comply with Rules, Bye-laws, regulations in force. All testing fees for materials as required shall be<br />

borne by the Contractor only.<br />

13. All formalities such as obtaining approvals for water supply, drainage and fire fighting installations, getting<br />

the works inspected or tested in the presence of concerned officials obtaining completion certificates for the<br />

installation and final connection of water supply and drainage for the building shall be the responsibility of<br />

the Contractor and no extra payment shall be payable to the Contractor on this account.<br />