(b) The length width and depths of all excavations shall be sufficient to provide for the necessary working<br />

space shuttering and any other temporary structures required during construction of all excavations shall be<br />

measured net and neither allowance shall made for the extra space for working etc. nor for the increase in bulk<br />

after excavation.<br />

(c) Any excavation including excavation in rock made in error below the level shown on the drawings or below<br />

the levels ordered by the engineer will not be paid for and shall be brought back to the specified levels with<br />

mass concrete at the contractor’s own expense.<br />

(d)<br />

(e)<br />

Where indicated the excavation shall be out to slopes the cost of which be included in the rates.<br />

No concrete or screed shall be placed in any excavation without the prior approval of the Engineer.<br />

(f) Mechanical excavation shall not be carried down to within less than 15 cm. above the required formation<br />

level the last 15cm will be removed by hand. If required by the engineer this 15 cm. shall not be removed until<br />

immediately before concreting takes place.<br />

1.02 REMOVAL OF UNSUITABLE MATERIALS<br />

Where unsuitable materials in encountered at the exposed formation level in excavations or immediately there<br />

under it shall be excavated to such levels as the engineer shall direct. The resultant excavations shall be back<br />

filled with selected materials deposited and compacted in layers of 15 cm as directed by the engineer. Such<br />

excavations shall be measured in accordance with the relevant item in the bill.<br />

1.03 TEMPORARY DRAINAGE AND TIMBERING<br />

(a) During the whole time that the excavations are open they shall be kept dry. The contractor shall construct<br />

temporary drains and bunds to prevent the entry of surface water excavate and maintain all drains bunds and<br />

provide and operated all pumps necessary to collect and remove all water, which enters into the excavations.<br />

(b) The contractors shall be solely responsible for the safety and stability of the excavations. He shall at his<br />

own cost slope the sides of the excavations or provide timber supports built and secured to the satisfaction of<br />

the engineer in order to prevent the occurrence of subsidence or slips.<br />

(c) The contractor shall at his own cost promptly provide and maintain any temporary drainage or other<br />

protective measures required by the engineer. Compliance with the engineer’s instructions in this respect shall<br />

not however relieve him of his sole responsibility for the stability of the excavations on site.<br />

1.03.1 DISPOSAL OF SOIL<br />

(a)<br />

Spoils from the site shall be disposed off within the areas as directed by the engineer.<br />

(b) Under no circumstances shall the spoils from the site be sold or given away to any unauthorized party for<br />

any consideration.<br />

1.04 EARTH FILLING IN PLINTH<br />

Fill material should be well-graded natural inorganic soil approved by the engineer and meeting the following<br />

requirements<br />

(a) It shall be free of organic or other weak or compressible materials and be of such nature and character<br />

that it can be compacted to the specified density on a reasonable length of time.<br />

(b) It shall be free of highly plastic clay or all materials subject to decay, decomposition or dissolution and<br />

corrosion etc.<br />

(c)<br />

It shall have a maximum dry density of not less than 1590 Kg. Per cubic meters<br />

(d) It should have liquid limit of 35 to 40% and P.I. value of 5 to 7<br />

(e)<br />

Earth available from trench cutting any also be utilized for filling plinth if it meets the above requirements.<br />

(f) The work under plinth or any places to make up level with sand having FM not less than 0.8<br />

(g) Earth shall be filled in plinth in 15cm. Layers and in each shall be compacted to the entire satisfaction of<br />

the engineer by vibration roller/power hammer at optimum moisture contents. The contractor shall be very<br />

careful regarding foundation walls/columns so that no harm is done during ramming.<br />