12.07.2014 Views

BID DOCUMENT - IDCO

BID DOCUMENT - IDCO

BID DOCUMENT - IDCO

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

SPECIAL CONDITION<br />

1. Notwithstanding any other condition in DTCN, No water will normally be supplied by Corporation. The<br />

Contractor is to arrange water for the work at his own cost. The Contractor will lay the pipeline network required for<br />

the construction purpose at his own cost. No delay in construction is permissible on the ground of paucity of water.<br />

If the water is availed from the Corporation source by the Contractor, water charges will be levied as per prevailing<br />

rate and the amount will be recovered from the his bill. Service roads are to be constructed by Contractor at his<br />

own cost.<br />

2. No time extension will be granted on the ground of scarcity of water, communication, material and<br />

machinery etc.<br />

3. The responsibility to locate Govt. approved quarry and burrow area lies with the Contractor.<br />

4. Wherever levels are to be taken it will be the responsibility of Contractor to get the same done through<br />

concerned Junior Engineer and checked by the Assistant Engineer.<br />

5. The Contractor will submit a detailed programme of completion of work with methodology for execution of<br />

each item of work at the time of execution of agreement.<br />

6. All machineries will be arranged by the Contractor at his own cost in proper time.<br />

7. The Contractor shall abide by the relevant Act like Minimum wages, Employees Provident Fund, ESI etc.<br />

and Rules and Regulations in force of the state of Orissa from time to time for the labour employed in construction<br />

work. The contractor shall be fully and solely responsible for any compensation/ fine that may be imposed for<br />

violation of the said Rules/Regulations/Act.<br />

8. For any bad quality of work the amount of award given by any consumer court/ judicial court will be<br />

recovered from the executing Contractor.<br />

9. Where the agreement rates are more than 25% of the estimated rate, no extra quantity beyond the<br />

agreement quantity should be executed without the prior written approval of competent authority of <strong>IDCO</strong>.<br />

10. Additional performance security shall be deposited by the successful bidder when the bid amount is<br />

seriously unbalanced i.e. less than the estimated cost by more than 10%. In such an event the successful bidder<br />

will deposit the additional performance security to the amount of the differential cost of the bid amount and 90% of<br />

the estimated cost in shape of Bank draft or Bank Guarantee of any nationalized Bank.<br />

11. For any additional quantities up to 25% on any item, the Contractor will be paid at the approved tender<br />

rate.<br />

16

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!