7 JANUARY 2009<br />

Installation of the temporary systems<br />

starts on the first 5 km. This work is<br />

done by a consortium of <strong>Rhomberg</strong><br />

Bahntechnik and K.E.M. Montage.<br />

16 FEBRUARY 2009<br />

Work kicks off for installation of the<br />

railway technology. A lot has already<br />

been done (status as of November<br />

2009):<br />

• 60% of temporary systems are<br />

installed (20.8 km of 34.4 km)<br />

• 55% of the backfill concrete has<br />

been cast (62,014 m 3 of 113,093 m 3 )<br />

• 28% of the side paths are built<br />

(19,150 m of 69,140 m)<br />

• 18% of the spring mass system is in<br />

place (5,820 m of 24,000 m)<br />

• 3.5% of the firefighting water pipes<br />

are installed (1,200 m of 35,000 m)<br />

• 33% of the firefighting water wells<br />

are completed (one of 3)<br />

NOVEMBER 2009<br />

Work has started on the planning<br />

of the fixed trackway, the doors and<br />

gates for the lock systems, the ventilation<br />

systems and the firefighting water<br />

system.<br />

Work on the remaining areas of<br />

the contract scope (cable systems,<br />

structural engineering, noise protection<br />

walls and electrical engineering<br />

systems) is running at full speed.<br />

2010<br />

Planned start of the installation of<br />

electrical engineering systems.<br />

Dirk Diederich<br />

For the latest updates on how<br />

the project is progressing please visit<br />

www.alptransit-brenner.at<br />

(German language website).<br />

“Work in Unterinntal<br />

has got off to a good<br />

start. Last year we set<br />

up the entire project<br />

organization, and we<br />

have already made<br />

significant progress. With our highly<br />

motivated team and the efforts of<br />

the entire <strong>Rhomberg</strong> Group, we are<br />

confident that we will also be able<br />

to meet all future challenges to the<br />

complete satisfaction of our Client<br />

and that we will bring the project to a<br />

successful completion.”<br />

Robert Kumpusch, ARGE ATB<br />

KEY DATA FOR THE BRENNER FEEDER LINE<br />

PROJECT IN UNTERINNTAL/AUT<br />

Total amount of concrete 290,000 m 3<br />

Length of side paths 69,000 m<br />

Length of spring mass system 24,000 m<br />

Length of fixed trackway 71,000 m<br />

Total track length 142,000 m<br />

Total cable length 1,095,000 m<br />

Total length of fibre optic conduits 995,000 m<br />

Total length of firefighting water pipes 35,000 m<br />

Noise protection walls 27,000 m 2<br />

Total number of plant rooms 43<br />

RAILWAY ENGINEERING ALPTRANSIT BRENNER | NEW DIMENSIONS 31