«byggnin» – Building Swedish style<br />
<strong>Rhomberg</strong> structural engineering teams in Sweden<br />
Since September<br />
2009, nine structural<br />
engineering workers<br />
have been living and working in<br />
Malmö , Sweden – far from their home<br />
base in Vorarlberg. The team members<br />
around foremen Jürgen Moosmann and<br />
Christoph Speckle faced challenges not<br />
just in their professional lives. All the<br />
employees spent the whole of the first<br />
month in Malmö. Then a shift system<br />
was devised which allowed the employees<br />
to take turns in spending a week<br />
with their families.<br />
Track slab FROM COPEN-<br />
HAGEN/DK TO MALMÖ/SE<br />
The professional challenge came in<br />
the form of a twelve kilometre long<br />
rail line, which must be constructed as<br />
track slab by April 2010. It will form<br />
part of the future rail link between<br />
the city centres of Copenhagen and<br />
Malmö. The teams were given a week<br />
of special training in <strong>Rhomberg</strong> Station<br />
to deal with the special demands of<br />
concreting the track slab.<br />
PERSONNEL SERVICE<br />
SUPPORTS THE STRUCTURAL<br />
ENGINEERING TEAMS IN<br />
SWEDEN<br />
Personnel Assistant Kim Grive prepared<br />
the “Swedes” with a refresher<br />
course in English sufficient for the<br />
linguistic challenge and stands by to<br />
provide help or advice to the team at<br />
any time.<br />
Reinhard Moosmann<br />
DATES & FACTS<br />
Client Banverket Produktion<br />
Quantities approx. 41 million euro<br />
Construction period September 2009 to March<br />
2010 (scheduled)<br />
Construction works 13.2 km track slab with<br />
6 turnouts (10,000 m 3 concrete), 5 km ballasted<br />
track, 6 expansion joints)<br />
Precision landing in high rise development<br />
Only 8 months for Blocks A and B in Sandgrubenweg Housing Development, Bregenz/AUT<br />
Right next door to <strong>Rhomberg</strong> headquarters<br />
in Bregenz/AUT, <strong>Rhomberg</strong><br />
specialists demonstrated to a circle of<br />
interested colleagues how to complete<br />
a construction project, perfectly and<br />
on-time. Karl Fussenegger and his<br />
team built Blocks A and B in record<br />
time. Work started in January 2009,<br />
the last touch was completed in<br />
August – and that happened despite<br />
the extraordinary challenges the architecture<br />
posed for the various tradesmen.<br />
Some interesting details: the surveying<br />
work was carried out by our<br />
new surveyor Christoph Pachoinig in<br />
agreement with the foreman to the<br />
great satisfaction of all the project<br />
participants. During the coldest part of<br />
the year, the team kept themselves fit<br />
with “healthy snacks”. Throughout the<br />
whole construction period, the hardhat<br />
policy was strictly observed by<br />
everyone present on site.<br />
Josef Boss<br />
DATES & FACTS<br />
Client <strong>Rhomberg</strong> <strong>Bau</strong> GmbH<br />
Construction period Blocks A and B<br />
January to August 2009<br />
Feature Pilot project for sustainability in multistorey<br />
residential buildings that have the qualities of detached<br />
houses<br />
Quantities 6,700 m 3 concrete, 500 tonnes steel,<br />
14,000 m 2 deck formwork, 5,000 m 2 wall formwork,<br />
2,500 m circular formwork, 25,000 manhours<br />