Roads and Highways Department<br />

Volume 8 – Foreign Aided Project Management Manual<br />

Section 5 – Guidelines for Preparation of Foreign Aided Projects<br />

will work with the MIS & Estates Circle to ensure that additions and improvements are made (as<br />

required) so that the Central Monitoring System continues to meet the requirements of all<br />

donors and FAPs.<br />

All FAPs shall record progress and disbursements in the RHD Central Management System.<br />

This system will be used by PIU as the main system for recording <strong>project</strong> accounting information<br />

and by the PCU for recording overall loan <strong>management</strong> information. Project reports shall be<br />

based on data generated from the CMS.<br />

The Director-Audit and Accounts shall be primarily responsible for financial audit of FAPs.<br />

Projects may be subject to ‘internal audit’ by auditors appointed and coordinated through the<br />

Director of Audit and Accounts. The external audits are conducted by the Comptroller Auditor<br />

General (CAG) in accordance with the provisions in the constitution. The Terms of Reference for<br />

these auditors shall be agreed between the Comptroller Auditor General (CAG) and the relevant<br />

donor agencies. This will include the specific conditionality required by different development<br />

partners or funding agencies.<br />

During the <strong>project</strong> and on its completion, the PIU shall ensure that all relevant <strong>project</strong><br />

information (e.g. date of construction, extent and type of the works) is completed in the RHD<br />

Central Management System (CMS).<br />

All important <strong>project</strong> documents (including inception and completion reports; economic, social,<br />

environment, resettlement and LA etc studies; technical reports such as hydrological and<br />

geotechnical reports; as-built records; contract documents) shall be archived through the MIS,<br />

RHD library and entered into the RHD document database. Electronic documents shall be<br />

stored centrally and linked to the RHD docum ent database for future reference.<br />

Where <strong>project</strong>s have multiple PIUs (e.g. each with different consultants or in different RHD<br />

zones) then the CMS will also be used to compile the accounts of these different components to<br />

review overall loan <strong>management</strong> in Dhaka.<br />

The SE-Monitoring and PCUs shall work together to review the performance, progress and<br />

budgets of FAPs using Central Management System.<br />

5.3.9 Training, HRD and Staff Systems<br />

The training components of all FAPs will be carried out in accordance with the RHD Training<br />

Policy. The Chief Engineer has issued an office order directing all the Project Directors to act<br />

through the RHD Training Centre (RHD TC) in respect of the use of training funds as approved<br />

by the Senior Management Committee.<br />

Issue 1 April 2005 Page 5.11