2nd <strong>Dhaka</strong>-<strong>Chittagong</strong> National Highway (Expressway)<br />
Request for Qualification Document<br />
5 TECHNICAL DEFINITION AND DESCRIPTION<br />
5.1 Technical Definition<br />
The detail functional specifications to be met by the Project Company will be<br />
defined in the Request for Proposal (RFP), but broadly it will consist <strong>of</strong> the<br />
following:<br />
(a) Site investigation, detailed design <strong>and</strong> production <strong>of</strong> all drawings <strong>of</strong> all project<br />
components<br />
(b) Construction <strong>of</strong> roads (at grade or elevated) (the highway or elevated<br />
expressway, access/approach/connecting roads etc.);<br />
(c) Construction <strong>of</strong> required number <strong>of</strong> bridges with river training;<br />
(d) Construction <strong>of</strong> required number <strong>of</strong> culverts;<br />
(e) Construction <strong>of</strong> interchanges;<br />
(f) Construction <strong>of</strong> flyovers;<br />
(g) Construction <strong>of</strong> toll plazas;<br />
(h) Installation <strong>of</strong> computerized toll collection system;<br />
(i) Development <strong>of</strong> service areas with all required facilities;<br />
(j) Adequate lighting <strong>of</strong> important <strong>and</strong> strategic locations / sections / points;<br />
(k) The relocation / resettlement <strong>of</strong> the inhabitants, owners etc. <strong>of</strong><br />
approximately 1544 hectare <strong>of</strong> l<strong>and</strong> (as per Conceptual Design) to be<br />
acquired for at grade level road but no study has been done for elevated<br />
expressway;<br />
(l) Construction <strong>of</strong> RoBs;<br />
(m) Construction <strong>of</strong> underpasses <strong>and</strong> overpasses;<br />
(n) Safety devices;<br />
(o) Construction <strong>of</strong> service roads;<br />
(p) Construction <strong>of</strong> wayside amenities<br />
(q) Construction <strong>of</strong> Lay-byes<br />
The Government will be responsible for the acquisition <strong>of</strong> l<strong>and</strong> <strong>and</strong> relocation<br />
/ resettlement <strong>of</strong> the l<strong>and</strong> owners, inhabitants, etc., where it is necessary for the<br />
project work.<br />
The Government or the concerned agencies will also assist the Investor <strong>and</strong><br />
will take necessary steps to relocate the utility connections i.e. electricity, gas,<br />
<strong>Roads</strong> <strong>and</strong> <strong>Highways</strong> <strong>Department</strong> 10