Non Technical Summary - Partnerships for Renewables
Non Technical Summary - Partnerships for Renewables
Non Technical Summary - Partnerships for Renewables
You also want an ePaper? Increase the reach of your titles
YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.
Traffic and Transport – Chapter 7 continued ><br />
The northern route will facilitate the delivery of the turbine<br />
components and general site equipment and, <strong>for</strong> this<br />
reason; the northern route is the intended abnormal loads<br />
route. It is anticipated that the southern route will be used<br />
<strong>for</strong> the transfer of aggregate and ready mix concrete to the<br />
development site.<br />
Both routes will use Clissold Road to access the site and,<br />
upon reaching the main prison buildings, vehicles will route<br />
north along an improved access track and then northwest<br />
along a purpose built access track which will provide<br />
access to each of the turbine sites.<br />
The intended abnormal loads route has been subject to<br />
further assessment to identify potential sections of the<br />
route that will require highway widening works in order to<br />
facilitate the transfer of the turbine components. Three such<br />
sections, referred to as ‘pinch points’, have been identified<br />
and the following provides a brief summary of their location<br />
and mitigation works required:<br />
• Pinch Point A: Medina Wharf/Arctic Road junction – minor<br />
widening of the Arctic Road carriageway and relocation of<br />
boundary fencing and associated gate posts (upon exit<br />
from Medina Wharf).<br />
• Pinch Point B: Arctic Road/A3020 junction – rein<strong>for</strong>cement<br />
of the inside radius and widening of the carriageway into<br />
the verge area opposite the junction. Relocation of<br />
street furniture.<br />
• Pinch Point C: A3020/Clissold Road – localised widening<br />
of Clissold Road and minor footway rein<strong>for</strong>cement on the<br />
inside radius.<br />
Highway widening works at Pinch Points B and C will be<br />
permanent and subject to detailed design and liaison with<br />
the Isle of Wight Council. The detailed design of highway<br />
widening works at Pinch Point A will be temporary and<br />
subject to continued liaison with the owners of Medina Wharf.<br />
The impact of construction-related traffic on the proposed<br />
access routes has been calculated, in percentage terms,<br />
relative to the <strong>for</strong>ecast background traffic in 2013 as the<br />
opening year of construction.<br />
It is predicted that there will be an increase in total traffic<br />
flows during the assessment period of:<br />
• Survey Site 1 (Northern Route) – A3020 (Newport Road):<br />
Increase in total traffic of 0.02% and increase in HGVs<br />
of 0.02%<br />
• Survey Site 2 (Southern Route) – A3020 (Medina Way):<br />
Increase in total traffic of 0.13% and increase in HGVs<br />
of 0.13%<br />
There will also be two days during the construction<br />
programme when a maximum of 154 HGV movements<br />
per day (77 in and 77 out) <strong>for</strong> turbine foundation concrete<br />
deliveries will occur. In addition 18 abnormal load deliveries<br />
are required within the 6-month construction programme.<br />
Although both these activities will have a disproportionate<br />
but temporary effect on the highway network neither will<br />
exceed the 10% threshold increase in daily traffic flow.<br />
Increases in daily traffic flow below 10% are not normally<br />
perceived by road users due to the fluctuating nature of<br />
background traffic flow.<br />
Effects on road users and adjacent residential properties<br />
are considered to be not significant and works on the<br />
highway at each of the pinch points will affect road users<br />
and adjacent properties at varying degrees but only <strong>for</strong> a<br />
relatively short time period. Since there will be some impact<br />
during the construction of the site and during the mitigation<br />
works within the highway it is appropriate to make provision<br />
<strong>for</strong> some additional management in the <strong>for</strong>m of a Traffic<br />
Management Plan (TMP) to reduce the potential <strong>for</strong> effects<br />
as far as reasonably possible; this will also ensure any<br />
residual effects on highway safety are reduced. In addition to<br />
the TMP an Environmental Management Plan (EMP) will also<br />
be provided to reduce as far as possible the impacts of all<br />
abnormal load deliveries.<br />
It is considered that the local transport network would be<br />
able to absorb the additional traffic movements associated<br />
with the construction of the wind energy development and,<br />
there<strong>for</strong>e, that no significant effects would occur.<br />
Noise – Chapter 8<br />
Hoare Lea Acoustics (HLA) was commissioned by PfR to<br />
undertake a noise impact assessment <strong>for</strong> the construction and<br />
operation of the proposed Camp Hill Wind Energy Development.<br />
Two types of noise are emitted from wind turbines.<br />
Aerodynamic noise is produced by the movement of the<br />
blades through the air often characterised as a ‘swish’ and<br />
mechanical noise can come from the components within the<br />
turbine itself such as gearboxes and mechanisms to vary<br />
the direction of the turbine. Recent progress in reducing the<br />
noise from turbines has been considerable particularly, in<br />
relation to mechanical noise.<br />
The noise assessment established the difference between<br />
wind turbine noise and the naturally occurring noise<br />
level at homes (residential properties) nearest to the<br />
proposed development and measured these against levels<br />
required by planning guidance. Government guidance<br />
<strong>for</strong> this assessment procedure is called ETSU-R-97, The<br />
Assessment and Rating of Noise from Wind Farms and<br />
specifies that noise limits should be set relative to existing<br />
background noise levels and reflect a variation in wind<br />
speeds. In general terms, during the daytime, noise from<br />
Section continues overleaf ><br />
06