20.05.2014 Views

Non Technical Summary - Partnerships for Renewables

Non Technical Summary - Partnerships for Renewables

Non Technical Summary - Partnerships for Renewables

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

Traffic and Transport – Chapter 7 continued ><br />

The northern route will facilitate the delivery of the turbine<br />

components and general site equipment and, <strong>for</strong> this<br />

reason; the northern route is the intended abnormal loads<br />

route. It is anticipated that the southern route will be used<br />

<strong>for</strong> the transfer of aggregate and ready mix concrete to the<br />

development site.<br />

Both routes will use Clissold Road to access the site and,<br />

upon reaching the main prison buildings, vehicles will route<br />

north along an improved access track and then northwest<br />

along a purpose built access track which will provide<br />

access to each of the turbine sites.<br />

The intended abnormal loads route has been subject to<br />

further assessment to identify potential sections of the<br />

route that will require highway widening works in order to<br />

facilitate the transfer of the turbine components. Three such<br />

sections, referred to as ‘pinch points’, have been identified<br />

and the following provides a brief summary of their location<br />

and mitigation works required:<br />

• Pinch Point A: Medina Wharf/Arctic Road junction – minor<br />

widening of the Arctic Road carriageway and relocation of<br />

boundary fencing and associated gate posts (upon exit<br />

from Medina Wharf).<br />

• Pinch Point B: Arctic Road/A3020 junction – rein<strong>for</strong>cement<br />

of the inside radius and widening of the carriageway into<br />

the verge area opposite the junction. Relocation of<br />

street furniture.<br />

• Pinch Point C: A3020/Clissold Road – localised widening<br />

of Clissold Road and minor footway rein<strong>for</strong>cement on the<br />

inside radius.<br />

Highway widening works at Pinch Points B and C will be<br />

permanent and subject to detailed design and liaison with<br />

the Isle of Wight Council. The detailed design of highway<br />

widening works at Pinch Point A will be temporary and<br />

subject to continued liaison with the owners of Medina Wharf.<br />

The impact of construction-related traffic on the proposed<br />

access routes has been calculated, in percentage terms,<br />

relative to the <strong>for</strong>ecast background traffic in 2013 as the<br />

opening year of construction.<br />

It is predicted that there will be an increase in total traffic<br />

flows during the assessment period of:<br />

• Survey Site 1 (Northern Route) – A3020 (Newport Road):<br />

Increase in total traffic of 0.02% and increase in HGVs<br />

of 0.02%<br />

• Survey Site 2 (Southern Route) – A3020 (Medina Way):<br />

Increase in total traffic of 0.13% and increase in HGVs<br />

of 0.13%<br />

There will also be two days during the construction<br />

programme when a maximum of 154 HGV movements<br />

per day (77 in and 77 out) <strong>for</strong> turbine foundation concrete<br />

deliveries will occur. In addition 18 abnormal load deliveries<br />

are required within the 6-month construction programme.<br />

Although both these activities will have a disproportionate<br />

but temporary effect on the highway network neither will<br />

exceed the 10% threshold increase in daily traffic flow.<br />

Increases in daily traffic flow below 10% are not normally<br />

perceived by road users due to the fluctuating nature of<br />

background traffic flow.<br />

Effects on road users and adjacent residential properties<br />

are considered to be not significant and works on the<br />

highway at each of the pinch points will affect road users<br />

and adjacent properties at varying degrees but only <strong>for</strong> a<br />

relatively short time period. Since there will be some impact<br />

during the construction of the site and during the mitigation<br />

works within the highway it is appropriate to make provision<br />

<strong>for</strong> some additional management in the <strong>for</strong>m of a Traffic<br />

Management Plan (TMP) to reduce the potential <strong>for</strong> effects<br />

as far as reasonably possible; this will also ensure any<br />

residual effects on highway safety are reduced. In addition to<br />

the TMP an Environmental Management Plan (EMP) will also<br />

be provided to reduce as far as possible the impacts of all<br />

abnormal load deliveries.<br />

It is considered that the local transport network would be<br />

able to absorb the additional traffic movements associated<br />

with the construction of the wind energy development and,<br />

there<strong>for</strong>e, that no significant effects would occur.<br />

Noise – Chapter 8<br />

Hoare Lea Acoustics (HLA) was commissioned by PfR to<br />

undertake a noise impact assessment <strong>for</strong> the construction and<br />

operation of the proposed Camp Hill Wind Energy Development.<br />

Two types of noise are emitted from wind turbines.<br />

Aerodynamic noise is produced by the movement of the<br />

blades through the air often characterised as a ‘swish’ and<br />

mechanical noise can come from the components within the<br />

turbine itself such as gearboxes and mechanisms to vary<br />

the direction of the turbine. Recent progress in reducing the<br />

noise from turbines has been considerable particularly, in<br />

relation to mechanical noise.<br />

The noise assessment established the difference between<br />

wind turbine noise and the naturally occurring noise<br />

level at homes (residential properties) nearest to the<br />

proposed development and measured these against levels<br />

required by planning guidance. Government guidance<br />

<strong>for</strong> this assessment procedure is called ETSU-R-97, The<br />

Assessment and Rating of Noise from Wind Farms and<br />

specifies that noise limits should be set relative to existing<br />

background noise levels and reflect a variation in wind<br />

speeds. In general terms, during the daytime, noise from<br />

Section continues overleaf ><br />

06

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!