03<br />

OUR<br />

OPERATIONS<br />

A sAFe, relIAble and eFFICIent network<br />

Major works in progress 2010–11 continued<br />

Description<br />

Cost ($)<br />

Before<br />

2010–11 2010–11<br />

Total cost<br />

to date<br />

Practical<br />

completion<br />

date<br />

Comments<br />

Nepean TS to<br />

Narellan ZS Feeder<br />

Nepean ZS<br />

Establishment<br />

North Eastern Creek<br />

ZS Establishment<br />

North Warragamba<br />

ZS Augmentation<br />

Northmead ZS<br />

Redevelopment<br />

Nowra ZS<br />

Augmentation<br />

Oran Park<br />

Establishment –<br />

Line Works<br />

Penrith TS<br />

Redevelopment<br />

Port Kembla ZS<br />

Redevelopment<br />

Ringwood ZS<br />

Redevelopment<br />

Rouse Hill SS<br />

Establishment<br />

Russell Vale ZS<br />

Augmentation<br />

Rydalmere ZS<br />

Redevelopment<br />

Sch<strong>of</strong>ields ZS<br />

Establishment<br />

Sherwood ZS<br />

Augmentation<br />

South Granville ZS<br />

Redevelopment<br />

South Nowra ZS<br />

Augmentation<br />

782 58,761 59,543 Aug 2012 Construct an new 66kV<br />

underground electricity line.<br />

466,491 3,648,968 4,115,459 Aug 2012 Construct a new 66/11kV indoor<br />

substation to replace the existing<br />

Camden substation.<br />

11,731,634 1,602,831 13,334,465 May 2012 Construct a new<br />

132/11kV substation.<br />

5,181,635 715,200 5,896,835 Complete Install a new transformer and<br />

associated switchgear.<br />

31,496 726,360 757,856 April 2014 Redevelop the existing substation<br />

with a new 33/11kV indoor<br />

control building.<br />

3,853,889 3,439,794 7,293,683 Sept 2011 Install two transformers with higher<br />

capacity units.<br />

1,634,391 7,257,890 8,892,281 July 2012 Construct two new 132kV electricity<br />

lines to supply Oran Park ZS.<br />

28,037,961 5,742,246 33,780,207 Feb 2012 Construct a new 132/33kV<br />

indoor substation.<br />

26,068 190,004 216,072 Nov 2013 Construct a new 33/11kV indoor<br />

substation to replace the existing<br />

Port Kembla substation.<br />

1,099 56,373 57,472 Oct 2013 Install new 11kV switchgear<br />

and associated equipment.<br />

12,234,619 100,407 12,335,026 Complete Developed a new indoor<br />

132kV switching station.<br />

6,856,504 98,433 6,954,937 Sept 2012 Replace two transformers with<br />

higher capacity units.<br />

5,330,532 1,672,495 7,003,027 Oct 2015 Rebuild existing 66/11kV substation<br />

with indoor 66kV GIS switchgear.<br />

5,073,844 11,741,398 16,815,242 July 2012 Construct a new 132/11kV<br />

indoor substation.<br />

6,133,578 368,304 6,501,882 Complete Replace existing transformers<br />

with low noise units.<br />

192,790 1,409,177 1,601,967 Oct 2013 Construct a new 33/11kV<br />

indoor substation.<br />

2,558,957 2,258,978 4,817,935 Oct 2011 Replace existing transformer with<br />

higher capacity unit. Construct a<br />

new control room to house new<br />

11kV switchboard.<br />

22