Major works in progress 2010–11 continued<br />

Description<br />

Cost ($)<br />

Before<br />

2010–11 2010–11<br />

Total cost<br />

to date<br />

Practical<br />

completion<br />

date<br />

Comments<br />

East Richmond ZS<br />

Establishment<br />

Fairfax Lane<br />

TS Busbar<br />

Augmentation<br />

Figtree ZS<br />

Establishment<br />

Gerringong ZS<br />

Augmentation<br />

Glenorie ZS<br />

Establishment<br />

Granville ZS<br />

Establishment<br />

Holroyd Bulk<br />

Supply Point<br />

Huntingwood ZS<br />

Establishment<br />

Jasper Rd ZS<br />

Redevelopment<br />

Kemps Creek ZS<br />

Redevelopment<br />

Lawson TS<br />

Redevelopment<br />

Liverpool ZS<br />

Establishment<br />

Mittagong ZS<br />

Augmentation<br />

Mobile Zone<br />

Substation<br />

Acquisitions<br />

Mt Ousley ZS<br />

Establishment<br />

Mungerie Park ZS<br />

Establishment<br />

333,940 5,776,352 6,110,292 Sept 2012 Construct a new 33/11kV indoor<br />

substation to replace the existing<br />

Richmond ZS.<br />

– 2,316 2,316 Aug 2012 To maintain transformer capacity<br />

by installing 132kV circuit breaker<br />

and installing or replacing 132kV<br />

busbar protection on several<br />

bus sections.<br />

82,912 1,895,324 1,978,236 May 2013 Establish a new 33/11kV indoor<br />

zone substation. Rebuild<br />

existing 33kV electricity line<br />

to a higher rating.<br />

2,037,103 2,244,138 4,281,241 June 2012 Replace two existing transformers<br />

with higher capacity units.<br />

Replace all switchgear.<br />

14,262 132,180 146,442 Aug 2013 Construct a new 33/11kV<br />

modular substation.<br />

13,778,640 11,652,294 25,430,934 April 2012 Construct a new 132/11kV<br />

indoor substation to replace<br />

the existing substation.<br />

– 59,694 59,694 April 2013 Works associated with the new<br />

TransGrid Bulk Supply Point.<br />

– 82,585 82,585 Oct 2013 Construct a new<br />

132/11kV substation.<br />

4,755,078 981,126 5,736,204 Complete Replace 11kV indoor switchgear.<br />

214,854 3,864,336 4,079,190 Mar 2012 Extend control room to<br />

accommodate new 11kV<br />

switchboard.<br />

11,082,994 1,754,961 12,837,955 June 2012 Rebuild existing 132/66kV<br />

substation with indoor 66kV<br />

GIS switchgear.<br />

13,404,477 8,010,775 21,415,252 Mar 2012 Construct a new 132/33kV<br />

indoor substation.<br />

92,885 797,950 890,835 Dec 2011 Install a third transformer and<br />

associated switchgear.<br />

4,317,464 2,259,175 6,576,639 Aug 2011 Establish new 132/11kV and<br />

66/11kV mobile substations.<br />

16,903,782 916,461 17,820,243 May 2012 Establish a new 33/11kV<br />

indoor substation.<br />

26,955,765 1,814,243 28,770,008 Complete Construct a new 132/22kV<br />

indoor substation.<br />

<strong>Endeavour</strong> <strong>Energy</strong> <strong>Annual</strong> <strong>Performance</strong> <strong>Report</strong> 2010–11<br />

21

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!