implemented <strong>to</strong> inform the public, schedule activities with respect <strong>to</strong> recreation, <strong>and</strong><br />

cooperate with <strong>to</strong>ur opera<strong>to</strong>rs. In addition, the rest of Lake Tahoe would still be available<br />

for boating recreation.<br />

b) The proposed project does not involve the expansion of existing or the construction of<br />

new recreational facilities. No impact.<br />

Mitigation Measure Rec-1: Boating Access<br />

Work will be coordinated with <strong>to</strong>ur boat opera<strong>to</strong>rs in Lake Tahoe <strong>to</strong> determine the<br />

least disruptive days <strong>and</strong> hours <strong>to</strong> conduct work. Work will occur during these days<br />

<strong>and</strong> time periods <strong>to</strong> the extent possible.<br />

The U. S. Coast Guard will be contacted <strong>to</strong> coordinate dissemination of information<br />

<strong>and</strong> <strong>to</strong> potentially assist with boater compliance <strong>and</strong> diver safety.<br />

Emerald Bay will require traffic control for mo<strong>to</strong>rized boat traffic for up <strong>to</strong> 6 hours per<br />

day for an estimated 4 weeks during barrier installation <strong>and</strong> 4 weeks during barrier<br />

removal, <strong>and</strong> during some alternative treatment work. Non-mo<strong>to</strong>rized boats <strong>and</strong><br />

escorted mo<strong>to</strong>rized boats may be allowed <strong>to</strong> pass through the mouth if the water<br />

level is high enough <strong>to</strong> allow passage <strong>and</strong> maintain the safety of the divers.<br />

Public notices will be used <strong>to</strong> inform the public of temporary boat traffic control.<br />

Work will be scheduled during the mornings <strong>and</strong> on weekdays <strong>to</strong> the extent possible.<br />

No boat traffic control would occur during the weekend, unless there is a need <strong>to</strong> resecure<br />

a barrier.<br />

A boat will be positioned at the mouth of Emerald Bay <strong>to</strong> inform the public of project<br />

activities <strong>and</strong> provide information on when they can proceed in<strong>to</strong> the bay.<br />

Overnight boaters in Emerald Bay will be informed of the temporary boat traffic<br />

control <strong>to</strong> allow departure prior <strong>to</strong> the start of work.<br />

To the extent possible, all installation <strong>and</strong> removal activities will be scheduled<br />

outside of the high recreation period between the Memorial Day <strong>and</strong> Labor Day<br />

weekends.<br />

Asian Clam Control Project IS/MND<br />

Emerald Bay State Park<br />

California Department of Parks <strong>and</strong> Recreation<br />

67