Maintenance and Administration A TIO Program must be submitted with every plan review application and an essential element of its successful implementation is the ongoing effort by the project team through the construction process. It is particularly important for the Design Professional of Record to keep all aspects of the OSHPD-approved program current with evolving project conditions. Although these conditions will generally include tests, inspections, and milestones, they will almost certainly include information on responsible personnel as the project team members become known or as they change over the course of the project. The TIO is not a rarely referenced static program; rather, it constitutes a dynamic document that the entire project team must regularly reference as a benchmark for ongoing quality assurance. Format Although OSHPD has developed and published TIO documents and forms that are available to the public on the OSHPD Website, these documents were designed to be used as tools or guides only. Hospitals with particular projects working with unique groups of companies and individuals will almost certainly benefit by customizing TIO Programs by creating hospital-specific templates to best suit the conditions. Because of the repetitive nature of much of the information included in the TIO Program, particularly when the project team does not change dramatically from project to project, TIO Programs that are developed around the specific hospitals for which they apply offer a more user-friendly approach than those that have been based on the Projects, Design Professionals, or OSHPD. Regardless of the preferred format, all TIO Programs should be created by Design Professionals who are thinking critically about the work scope and how to best preserve design intent and maintain construction quality. Instruments Traditionally the Design Professionals of Record create and maintain TIO Programs using the standard OSHPD Forms. Although this is acceptable, it may not reflect a best practice approach to the State’s requirements because of the concentrated involvement that is required for the ongoing TIO Program implementation over the course of the project. Depending on the size and nature of the construction projects, alternate means for developing and maintaining the integrity of the construction quality may offer better solutions for achieving the objectives of the TIO Program requirements. Generally, it is considered a Best Practice for the IOR to manage the activities that keep the TIO Program current in the field in coordination with and on behalf of the POR. Contract Drawings (OSHPD Best Practices) Page 74 DRAFT FINAL, Sept. 2011

Although including the TIO Program within the sheets of the OSHPD-approved and large-format construction drawings is possible, this approach is cumbersome to maintain. Personnel, firms, tests, inspections, and milestones are dynamic because of the nature of the project. Keeping the TIO Program documentation current with dynamic conditions by changing the information on large-format construction drawings may be time consuming and does not serve the project progress. Rather, a stand-alone 8 ½ x 11 document that is approved separately from the rest of the project and can easily be transmitted to others on the team may offer a more manageable approach. Revisions to the approved TIO Program that do not change the intent of the original approved plans, specifications and / or code required tests or inspections do not constitute a Material Alteration as defined in the California Administrative Code (CAC), Section 7-111 and are not required to be submitted to OSHPD for review and approval as noted in (CAC), Section 7-153. Instructions Within the first pages of the TIO Program should be “Instructions” to the project personnel for the proper implementation of the Program. Along with clarifying the expectations for its use, the “Instructions” should clearly define the responsibilities of the project participants as they relate to the TIO Program. Instructions are optional. Although the forms OSH-FD-303A and OSH-FD-303S1 that are posted to the OSHPD Website are acceptable instruments to use for the TIO Program development, they do not include Instructions. EXAMPLE: (OSHPD Best Practices) Page 75 DRAFT FINAL, Sept. 2011

Maintenance <strong>and</strong> Administration<br />

A TIO Program must be submitted with every plan review application <strong>and</strong> an essential element <strong>of</strong><br />

its successful implementation is the ongoing ef<strong>for</strong>t by the project team through the construction<br />

process. It is particularly important <strong>for</strong> the <strong>Design</strong> Pr<strong>of</strong>essional <strong>of</strong> Record to keep all aspects <strong>of</strong> the<br />

OSHPD-approved program current with evolving project conditions. Although these conditions<br />

will generally include tests, inspections, <strong>and</strong> milestones, they will almost certainly include<br />

in<strong>for</strong>mation on responsible personnel as the project team members become known or as they<br />

change over the course <strong>of</strong> the project. The TIO is not a rarely referenced static program; rather, it<br />

constitutes a dynamic document that the entire project team must regularly reference as a<br />

benchmark <strong>for</strong> ongoing quality assurance.<br />

Format<br />

Although OSHPD has developed <strong>and</strong> published TIO documents <strong>and</strong> <strong>for</strong>ms that are available to<br />

the public on the OSHPD Website, these documents were designed to be used as tools or guides<br />

only. Hospitals with particular projects working with unique groups <strong>of</strong> companies <strong>and</strong> individuals<br />

will almost certainly benefit by customizing TIO Programs by creating hospital-specific templates<br />

to best suit the conditions. Because <strong>of</strong> the repetitive nature <strong>of</strong> much <strong>of</strong> the in<strong>for</strong>mation included in<br />

the TIO Program, particularly when the project team does not change dramatically from project to<br />

project, TIO Programs that are developed around the specific hospitals <strong>for</strong> which they apply <strong>of</strong>fer<br />

a more user-friendly approach than those that have been based on the <strong>Project</strong>s, <strong>Design</strong><br />

Pr<strong>of</strong>essionals, or OSHPD. Regardless <strong>of</strong> the preferred <strong>for</strong>mat, all TIO Programs should be<br />

created by <strong>Design</strong> Pr<strong>of</strong>essionals who are thinking critically about the work scope <strong>and</strong> how to best<br />

preserve design intent <strong>and</strong> maintain construction quality.<br />

Instruments<br />

Traditionally the <strong>Design</strong> Pr<strong>of</strong>essionals <strong>of</strong> Record create <strong>and</strong> maintain TIO Programs using the<br />

st<strong>and</strong>ard OSHPD Forms. Although this is acceptable, it may not reflect a best practice approach<br />

to the State’s requirements because <strong>of</strong> the concentrated involvement that is required <strong>for</strong> the<br />

ongoing TIO Program implementation over the course <strong>of</strong> the project. Depending on the size <strong>and</strong><br />

nature <strong>of</strong> the construction projects, alternate means <strong>for</strong> developing <strong>and</strong> maintaining the integrity <strong>of</strong><br />

the construction quality may <strong>of</strong>fer better solutions <strong>for</strong> achieving the objectives <strong>of</strong> the TIO Program<br />

requirements. Generally, it is considered a <strong>Best</strong> Practice <strong>for</strong> the IOR to manage the activities that<br />

keep the TIO Program current in the field in coordination with <strong>and</strong> on behalf <strong>of</strong> the POR.<br />

Contract Drawings<br />

(OSHPD <strong>Best</strong> <strong>Practices</strong>) Page 74 DRAFT FINAL, Sept. 2011