Best Practices for Project Management, Design, and Construction of ...

Best Practices for Project Management, Design, and Construction of ... Best Practices for Project Management, Design, and Construction of ...

10.05.2014 Views

Preparation for the Preconstruction Meeting Above all else, the IOR should be prepared. The IOR should have all information received from the owner and architect available and needs to review this prior to the meeting. This information should include: • Approved drawings, • Project specifications, • Project schedule, and • A copy of an inspection request. The IOR should be familiar with the project schedule and the actual work taking place. If advanced notice of the preconstruction meeting is given at the owners meeting, it then becomes part of the meeting minutes and will be carried forward until the preconstruction meeting takes place. During the Meeting Meetings are usually run by the AOR, the EOR, the POR, or the general contractor. Participation by other contractors and subcontractors will vary based on their level of preparation and experience. During the pre-construction meeting the general contractor should be able to give assurances regarding personnel and materials to complete the work. The OSHPD field staff will do the following: • Establish and define lines of communication among subcontractors, contractors, design professionals, the IOR, and OSHPD field staff. • Identify and review the requirements of the Hospital Seismic Safety Act of 1983 and Title 24, Part 1, Chapter 7 of the CCR. • Summarize the overall duties, observation, and coordination functions of the AOR or SEOR as required by Title 24, Part 1, Chapter 7 of the CCR, including preparation of Amended Construction Documents and verified reports, site visits to verify work, and certification and submittals to OSHPD. • Summarize the overall duties of the IOR, reporting relationships, and the IOR’s responsibility to verify compliance with the plans, specifications, and applicable codes. • Discuss required coordinated review of the project by OSHPD representatives (CO, FLSO, and DSE). • Identify specific and/or unusual code and project requirements. (OSHPD Best Practices) Page 70 DRAFT FINAL, Sept. 2011

• Explain code requirements for shop drawings, submittal, review, and approval. Outline procedures for meeting the requirements and how submittals will impact project schedule. • Explain the procedures and requirements for approving Amended Construction Documents. Review the approved TIO Program. • Discuss the schedule for submittal of deferred approval items to avoid delays in construction. • Request scheduling requests from owners and contact information for the hospital representative. The IOR should do the following: • Ask how the contractors intend to accomplish the work and allow them to walk you through the construction process. • Review the specifications. Frequently the subcontractor is unaware of the unique requirements of the project and may not have reviewed the specifications. • Give a copy of the inspection request to all parties and review who looks at the work prior to inspection, reasons for rejection, how the IOR will notify them, and what the notification requirements are. It is important to stipulate the quality standards expected so that all responsible parties will adhere to the inspection requirements. • Review the TIO Program requirements. • Briefly review the noncompliance procedures. • Review what the IOR wants to see and at what stage the IOR must perform inspections. • Discuss material inspection upon arrival at the project. • Ensure that contractors and subcontractors understand how facilities are coordinated through the IOR and the project manager. • Make it clear to the contractor that the IOR is not responsible for reviewing the adequacy of the contractor’s safety program. • If OSHPD field representatives are not present, describe AHJ involvement and review the requirements and procedures with contractors and subcontractors. It is always a good idea to conduct a site assessment after the meeting to review the installation process and setup. This allows everyone to have a clear picture. The preconstruction meeting is an opportune time to bring up fire stopping of penetrations and to inform the contractor that all penetrations will have to be completed per a listed testing agency such as Underwriters Laboratories (UL). Engineering judgments should only be used in extreme cases. Bringing such issues to the contractor’s attention early should mitigate potential problems. (OSHPD Best Practices) Page 71 DRAFT FINAL, Sept. 2011

Preparation <strong>for</strong> the Preconstruction Meeting<br />

Above all else, the IOR should be prepared. The IOR should have all in<strong>for</strong>mation received from<br />

the owner <strong>and</strong> architect available <strong>and</strong> needs to review this prior to the meeting. This in<strong>for</strong>mation<br />

should include:<br />

• Approved drawings,<br />

• <strong>Project</strong> specifications,<br />

• <strong>Project</strong> schedule, <strong>and</strong><br />

• A copy <strong>of</strong> an inspection request. The IOR should be familiar with the project schedule <strong>and</strong><br />

the actual work taking place. If advanced notice <strong>of</strong> the preconstruction meeting is given at<br />

the owners meeting, it then becomes part <strong>of</strong> the meeting minutes <strong>and</strong> will be carried<br />

<strong>for</strong>ward until the preconstruction meeting takes place.<br />

During the Meeting<br />

Meetings are usually run by the AOR, the EOR, the POR, or the general contractor. Participation<br />

by other contractors <strong>and</strong> subcontractors will vary based on their level <strong>of</strong> preparation <strong>and</strong><br />

experience. During the pre-construction meeting the general contractor should be able to give<br />

assurances regarding personnel <strong>and</strong> materials to complete the work.<br />

The OSHPD field staff will do the following:<br />

• Establish <strong>and</strong> define lines <strong>of</strong> communication among subcontractors, contractors, design<br />

pr<strong>of</strong>essionals, the IOR, <strong>and</strong> OSHPD field staff.<br />

• Identify <strong>and</strong> review the requirements <strong>of</strong> the Hospital Seismic Safety Act <strong>of</strong> 1983 <strong>and</strong> Title<br />

24, Part 1, Chapter 7 <strong>of</strong> the CCR.<br />

• Summarize the overall duties, observation, <strong>and</strong> coordination functions <strong>of</strong> the AOR or<br />

SEOR as required by Title 24, Part 1, Chapter 7 <strong>of</strong> the CCR, including preparation <strong>of</strong><br />

Amended <strong>Construction</strong> Documents <strong>and</strong> verified reports, site visits to verify work, <strong>and</strong><br />

certification <strong>and</strong> submittals to OSHPD.<br />

• Summarize the overall duties <strong>of</strong> the IOR, reporting relationships, <strong>and</strong> the IOR’s<br />

responsibility to verify compliance with the plans, specifications, <strong>and</strong> applicable codes.<br />

• Discuss required coordinated review <strong>of</strong> the project by OSHPD representatives (CO,<br />

FLSO, <strong>and</strong> DSE).<br />

• Identify specific <strong>and</strong>/or unusual code <strong>and</strong> project requirements.<br />

(OSHPD <strong>Best</strong> <strong>Practices</strong>) Page 70 DRAFT FINAL, Sept. 2011

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!