Site Plans If the project involves outside (exterior) electrical work, then it should be clearly shown in the site plan documentation. Based upon the complexity of the project, the site plan should be developed into multiple documents such as: o o o Site Plan – Electrical Power Site Plan – Lighting Site Plan – Low Voltage Systems Floor Plans It is recommended to follow the architectural floor plan nomenclature for sheet order and sheet numbering in order to simplify the logical sequence of cross-coordination with all trades (disciplines). Traditionally, the floor plans provide the documentation of the architectural features as a shaded background and the electrical devices are prominently shown on top of these locations. Enlarged Drawings The drawings that contain a significant amount of information require much more space to clearly communicate the scope of work. These drawings tend to be the ¼” scale or larger, in order to show exact placements and or intent. In addition, these drawings may comprise several elevations to demonstrate the intent. Organization and Approach The electrical drawings represent work that is closely coordinated with many other disciplines such as architectural, structural, mechanical, and plumbing. The need to have very well coordinated drawings is especially important with respect to mechanical and plumbing equipment. Reflected ceiling plans are another key coordination effort. Many of the design issues that arise from plan review are from non-concurrent referenced plans such as a reflected ceiling plan or mechanical plan indicating fire/smoke damper locations, for example. Based on many experiences, the last minute little changes from one discipline cause large issues for another discipline. Drawing Content The electrical drawings should reflect the clear scope of work and the application of separate systems on their own drawings will provide better definition of the intended work. Examples of this are as follows: Sheet Description: o o o o o o Electrical Title Sheet, Drawing Index Schedules, Notes, Lighting Schedules Site Plan – Electrical Site Plan – Lighting Site Plan – Low Voltage / Communication Floor Plan – Electrical (OSHPD Best Practices) Page 54 DRAFT FINAL, Sept. 2011
o o o o o o o o Floor Plan – Lighting Floor Plan – Low Voltage Systems (Voice/Data, Nurse Call, TV) Floor Plan – Fire Alarm One Line Diagram Panel Schedules Panel Schedules Enlarged Floor Plans – Electrical Details Existing Conditions Projects that occur within existing spaces require an additional level of care and planning. The need for good site investigation and documentation requires a significant level of time and costs of the design team. In many cases, the initial scope of a project may be significantly altered once the existing infrastructure is evaluated. The emphasis should be placed on field investigations, followed by clear documentation of the existing facility restraints regarding the project. The existing electrical and low voltage systems in most cases, must stay operational and thus significant work-around planning must be developed. Showing much of the existing infrastructure helps to convey the true scope of work to the trades involved and minimize future scope changes. (OSHPD Best Practices) Page 55 DRAFT FINAL, Sept. 2011
- Page 3 and 4: • Part 1 of Title 24 is the Calif
- Page 5 and 6: Rapid Review Unit The Rapid Review
- Page 7 and 8: Section 2: Geologic Hazards Investi
- Page 9 and 10: equested, CGS will review the suppl
- Page 11 and 12: under OSHPD regulations. Please see
- Page 13 and 14: Another approach to creating better
- Page 15 and 16: create confusion. The discipline ha
- Page 17 and 18: applicable phasing must be clearly
- Page 19 and 20: addresses, and project Websites, ma
- Page 21 and 22: • Plumbing fixture counts for pub
- Page 23 and 24: (OSHPD Best Practices) Page 23 DRAF
- Page 25 and 26: • Treatment of listed floor slab
- Page 27 and 28: • References to the prescriptive
- Page 29 and 30: Provisions of California Fire Code
- Page 31 and 32: Existing Special Conditions The sam
- Page 33 and 34: Enlarged Drawings Provide enlarged
- Page 35 and 36: 3.6 Door Schedule Purpose The door
- Page 37 and 38: Existing or Special Conditions Exis
- Page 39 and 40: approved “shake table testing.”
- Page 41 and 42: Drawing Content Equipment may inclu
- Page 43 and 44: Drawing Content For details that pr
- Page 45 and 46: Details that provide information on
- Page 47 and 48: Early in the design process, it is
- Page 49 and 50: • Identify any equipment that req
- Page 51 and 52: • Identify any equipment that req
- Page 53: Several drawings contain essential
- Page 57 and 58: Section 4: Inspector of Record Best
- Page 59 and 60: • Approved program flexes; • Ra
- Page 61 and 62: 9. The IOR shall submit verified co
- Page 63 and 64: • Log and record areas that by de
- Page 65 and 66: • Inspections completed by the us
- Page 67 and 68: Logging Inspection Requests 1. When
- Page 69 and 70: Preconstruction Meetings A preconst
- Page 71 and 72: • Explain code requirements for s
- Page 73 and 74: Concluding Remarks An IOR needs to
- Page 75 and 76: Although including the TIO Program
- Page 77 and 78: Owner The Owner is responsible for
- Page 79 and 80: Inspections The TIO Program should
- Page 81 and 82: The construction of hospitals in Ca
- Page 83 and 84: Instruction Bulletins (IBs), prepar
- Page 85 and 86: Changes will undoubtedly be require
- Page 87 and 88: Proper execution of these and the o
- Page 89 and 90: contingencies, that concur with def
- Page 91 and 92: and help in determining the cause o
- Page 93 and 94: have discovered that bids only cove
- Page 95 and 96: Best Practice 7: Determine whether
- Page 97 and 98: OSHPD believes the key to receiving
- Page 99 and 100: the design assistance from the manu
- Page 101 and 102: Permit Phase Best Practice 15: Keep
- Page 103 and 104: Comment and Process Review The deci
o<br />
o<br />
o<br />
o<br />
o<br />
o<br />
o<br />
o<br />
Floor Plan – Lighting<br />
Floor Plan – Low Voltage Systems (Voice/Data, Nurse Call, TV)<br />
Floor Plan – Fire Alarm<br />
One Line Diagram<br />
Panel Schedules<br />
Panel Schedules<br />
Enlarged Floor Plans – Electrical<br />
Details<br />
Existing Conditions<br />
<strong>Project</strong>s that occur within existing spaces require an additional level <strong>of</strong> care <strong>and</strong> planning. The<br />
need <strong>for</strong> good site investigation <strong>and</strong> documentation requires a significant level <strong>of</strong> time <strong>and</strong> costs <strong>of</strong><br />
the design team. In many cases, the initial scope <strong>of</strong> a project may be significantly altered once the<br />
existing infrastructure is evaluated.<br />
The emphasis should be placed on field investigations, followed by clear documentation <strong>of</strong> the<br />
existing facility restraints regarding the project.<br />
The existing electrical <strong>and</strong> low voltage systems in most cases, must stay operational <strong>and</strong> thus<br />
significant work-around planning must be developed.<br />
Showing much <strong>of</strong> the existing infrastructure helps to convey the true scope <strong>of</strong> work to the trades<br />
involved <strong>and</strong> minimize future scope changes.<br />
(OSHPD <strong>Best</strong> <strong>Practices</strong>) Page 55 DRAFT FINAL, Sept. 2011