Based on many experiences, the last minute little changes from one discipline cause large issues for another discipline. The plumbing drawings should reflect the clear scope of work and the application of separate systems on their own drawings will provide better definition of the intended work. Examples of this are as follows: Sheet Number: P001 P002 P100 P201 P202 P301 P401 P501 P601 Sheet Description: Plumbing Title Sheet, Drawing Index Plumbing Schedules, Notes, Water Calculations Site Plan – Plumbing 1 st Floor Plan – Plumbing and Medical Gas Plans 2 nd Floor Plan – Plumbing and Medical Gas Plans Enlarged Floor Plans - Plumbing Piping Diagrams Details Controls 3.12 Best Practices for Electrical Drawings Electrical Documentation Purpose The purpose of the Electrical Drawings are intended to depict all electrical devices & components required to provide safe, reliable electrical systems. Based upon the current trend in healthcare environments for new medical and surgical procedures that are constantly changing, a greater emphasis is needed for expandable electrical systems. Content Based upon the complexity and scale of the project, the information provided on the electrical drawings should show clear description of the work required for the project. In many cases, the project may involve the documentation of existing electrical systems and should clearly identify new versus existing devices and equipment. The need for modern digital communication systems will also require clear documentation of these systems as they relate to the critical systems within the facility. These systems are presently reviewed only for routing as it pertains to fire rated wall penetrations. The title page should clearly define the project location and vicinity by graphical means. The applicable building codes should be stated. A drawing index is recommended to clearly identify all the unique systems that may be involved. (OSHPD Best Practices) Page 52 DRAFT FINAL, Sept. 2011
Several drawings contain essential information such as Load Calculations, One-Line Diagrams, Panel Schedules and drawing details. These documents usually follow the physical device locations placed on the floor plans. Checklist of Key Items: 1. All electrical plans and specifications signed by the electrical engineer of record. 2. List of symbols and abbreviations used on plans and their meaning. 3. Correct electrical code version cited. 4. Room names and numbers on all plan sheets. 5. Provide wall fire ratings & legend. 6. Single line diagram of the electrical system showing normal source and segregation of the essential electrical system. Clearly identify components as normal, critical, life safety, or equipment. 7. Site plan showing service entrance, distribution system, service transformer, and generator location. 8. Drawings showing details of all switchboards, panels, and equipment. 9. Load calculations or other approved methods showing verification of load capacity for all equipment and conductors. Show effect on both normal and emergency system. 10. Panel schedules with totalized, tabulated loads. Panel schedules shall indicate rating of panel, feeder conductor, feeder overcurrent protective device, branch/system (critical, life safety, equipment) and loads served. 11. Clearly indicate the AIC ratings of all panelboards & distribution boards. 12. Schedules of ratings of equipment requiring electrical connection. 13. Schedule showing all feeders phase and ground conductors, conduit sizes, estimated lengths, and overcurrent protective devices. 14. Location and power source for all wiring devices, including receptacles, lights, switches, junction boxes, power outlets, and telephone outlets. 15. Fire alarm system. Provide specifications for equipment, show location of all devices, and show connection to life safety power source. Indicate if power limited. 16. Nurse call system. Provide specifications for equipment, show location of all devices, and show connection to power source. Indicate if power limited. 17. All equipment must be listed, labeled, or certified by a Nationally Recognized Testing Laboratory including X-ray and diagnostic equipment. (OSHPD Best Practices) Page 53 DRAFT FINAL, Sept. 2011
- Page 1 and 2: [On inside Title Page: Many of the
- Page 3 and 4: • Part 1 of Title 24 is the Calif
- Page 5 and 6: Rapid Review Unit The Rapid Review
- Page 7 and 8: Section 2: Geologic Hazards Investi
- Page 9 and 10: equested, CGS will review the suppl
- Page 11 and 12: under OSHPD regulations. Please see
- Page 13 and 14: Another approach to creating better
- Page 15 and 16: create confusion. The discipline ha
- Page 17 and 18: applicable phasing must be clearly
- Page 19 and 20: addresses, and project Websites, ma
- Page 21 and 22: • Plumbing fixture counts for pub
- Page 23 and 24: (OSHPD Best Practices) Page 23 DRAF
- Page 25 and 26: • Treatment of listed floor slab
- Page 27 and 28: • References to the prescriptive
- Page 29 and 30: Provisions of California Fire Code
- Page 31 and 32: Existing Special Conditions The sam
- Page 33 and 34: Enlarged Drawings Provide enlarged
- Page 35 and 36: 3.6 Door Schedule Purpose The door
- Page 37 and 38: Existing or Special Conditions Exis
- Page 39 and 40: approved “shake table testing.”
- Page 41 and 42: Drawing Content Equipment may inclu
- Page 43 and 44: Drawing Content For details that pr
- Page 45 and 46: Details that provide information on
- Page 47 and 48: Early in the design process, it is
- Page 49 and 50: • Identify any equipment that req
- Page 51: • Identify any equipment that req
- Page 55 and 56: o o o o o o o o Floor Plan - Lighti
- Page 57 and 58: Section 4: Inspector of Record Best
- Page 59 and 60: • Approved program flexes; • Ra
- Page 61 and 62: 9. The IOR shall submit verified co
- Page 63 and 64: • Log and record areas that by de
- Page 65 and 66: • Inspections completed by the us
- Page 67 and 68: Logging Inspection Requests 1. When
- Page 69 and 70: Preconstruction Meetings A preconst
- Page 71 and 72: • Explain code requirements for s
- Page 73 and 74: Concluding Remarks An IOR needs to
- Page 75 and 76: Although including the TIO Program
- Page 77 and 78: Owner The Owner is responsible for
- Page 79 and 80: Inspections The TIO Program should
- Page 81 and 82: The construction of hospitals in Ca
- Page 83 and 84: Instruction Bulletins (IBs), prepar
- Page 85 and 86: Changes will undoubtedly be require
- Page 87 and 88: Proper execution of these and the o
- Page 89 and 90: contingencies, that concur with def
- Page 91 and 92: and help in determining the cause o
- Page 93 and 94: have discovered that bids only cove
- Page 95 and 96: Best Practice 7: Determine whether
- Page 97 and 98: OSHPD believes the key to receiving
- Page 99 and 100: the design assistance from the manu
- Page 101 and 102: Permit Phase Best Practice 15: Keep
Several drawings contain essential in<strong>for</strong>mation such as Load Calculations, One-Line Diagrams,<br />
Panel Schedules <strong>and</strong> drawing details. These documents usually follow the physical device<br />
locations placed on the floor plans.<br />
Checklist <strong>of</strong> Key Items:<br />
1. All electrical plans <strong>and</strong> specifications signed by the electrical engineer <strong>of</strong> record.<br />
2. List <strong>of</strong> symbols <strong>and</strong> abbreviations used on plans <strong>and</strong> their meaning.<br />
3. Correct electrical code version cited.<br />
4. Room names <strong>and</strong> numbers on all plan sheets.<br />
5. Provide wall fire ratings & legend.<br />
6. Single line diagram <strong>of</strong> the electrical system showing normal source <strong>and</strong> segregation <strong>of</strong> the<br />
essential electrical system. Clearly identify components as normal, critical, life safety, or<br />
equipment.<br />
7. Site plan showing service entrance, distribution system, service trans<strong>for</strong>mer, <strong>and</strong><br />
generator location.<br />
8. Drawings showing details <strong>of</strong> all switchboards, panels, <strong>and</strong> equipment.<br />
9. Load calculations or other approved methods showing verification <strong>of</strong> load capacity <strong>for</strong> all<br />
equipment <strong>and</strong> conductors. Show effect on both normal <strong>and</strong> emergency system.<br />
10. Panel schedules with totalized, tabulated loads. Panel schedules shall indicate rating <strong>of</strong><br />
panel, feeder conductor, feeder overcurrent protective device, branch/system (critical, life<br />
safety, equipment) <strong>and</strong> loads served.<br />
11. Clearly indicate the AIC ratings <strong>of</strong> all panelboards & distribution boards.<br />
12. Schedules <strong>of</strong> ratings <strong>of</strong> equipment requiring electrical connection.<br />
13. Schedule showing all feeders phase <strong>and</strong> ground conductors, conduit sizes, estimated<br />
lengths, <strong>and</strong> overcurrent protective devices.<br />
14. Location <strong>and</strong> power source <strong>for</strong> all wiring devices, including receptacles, lights, switches,<br />
junction boxes, power outlets, <strong>and</strong> telephone outlets.<br />
15. Fire alarm system. Provide specifications <strong>for</strong> equipment, show location <strong>of</strong> all devices, <strong>and</strong><br />
show connection to life safety power source. Indicate if power limited.<br />
16. Nurse call system. Provide specifications <strong>for</strong> equipment, show location <strong>of</strong> all devices, <strong>and</strong><br />
show connection to power source. Indicate if power limited.<br />
17. All equipment must be listed, labeled, or certified by a Nationally Recognized Testing<br />
Laboratory including X-ray <strong>and</strong> diagnostic equipment.<br />
(OSHPD <strong>Best</strong> <strong>Practices</strong>) Page 53 DRAFT FINAL, Sept. 2011