how to do business with goaa - Orlando International Airport
how to do business with goaa - Orlando International Airport
how to do business with goaa - Orlando International Airport
Create successful ePaper yourself
Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.
“HOW TO DO BUSINESS WITH GOAA”<br />
Current/Future Construction Plans<br />
Mike Patterson<br />
Direc<strong>to</strong>r of Construction<br />
Friday, September 21, 2012
Agenda<br />
– Background Information<br />
• Projects by Calendar Year (CY)<br />
– Project Updates<br />
• Upcoming Projects<br />
Friday, September 21, 2012
Construction Cost Overview<br />
CY 2003-2012<br />
Year # Projects Paid<br />
2003 111 $137.6M<br />
2004 109 $ 72.7M<br />
2005 136 $ 71.0M<br />
2006 164 $ 88.4M<br />
2007 149 $142.2M<br />
2008 133 $171.6M<br />
2009 125 $148.3M<br />
2010 114 $ 55.0M<br />
2011 151 $ 57.9M<br />
2012 98 $ 33.5M<br />
Friday, September 21, 2012
Highlights of Upcoming Projects<br />
• BP-402F, Electrical Branch Segregation SE Quadrant, All Levels<br />
• BP-408A, Permanent Bus & Taxi Hold Lot<br />
• BP-408B, Cell Lot & Return <strong>to</strong> Terminal A Road<br />
• BP-411, Taxiway A Rehabilitation and Improvements<br />
• BP-432, Optimization of Checked Baggage Inspection Systems (CBIS)<br />
• BP-434, Runway 18R-36L Rehabilitation and Related Work<br />
• BP-435, Light Fixture Replacement for Garages A, B, and Terminal Top<br />
• BP-438, Baggage Make-Up Ventilation Improvements<br />
• BP-439, Landside Emergency Power Generation Expansion<br />
• V-629, Add Two New Flat Plate Make-Up Carousels<br />
• V-642, Hyatt Cold Water Pipe Replacement – Phase 3<br />
• V-645, Smoke Control Improvements, Hyatt Atrium and Level 3 Core<br />
Friday, September 21, 2012
BP-402F, Electrical Branch Segregation<br />
SE Quadrant, All Levels<br />
Project Scope<br />
Upgrade existing emergency<br />
power distribution system and<br />
segregate the various load<br />
types in<strong>to</strong> separate branches<br />
in the SE Quadrant of the<br />
Landside Terminal.<br />
Construction Cost<br />
$2.5 M<br />
Emergency Power Distribution<br />
Branch Typical Loads<br />
Life Safety* Fire Alarm, Egress Lighting, Fire Shutters<br />
Critical* Smoke Evacuation, Eleva<strong>to</strong>rs, Lift Stations<br />
Security Access Control, CCTV, Paging<br />
Equipment Public Area Lighting, Ticket Counters, BHS<br />
Duration<br />
Jan. 2013 – Dec. 2013<br />
*Infrastructure installed in BP-402<br />
Friday, September 21, 2012
BP-408A, Permanent Bus & Taxi Hold Lot<br />
Project Scope<br />
Construct a bus and taxi<br />
hold facility, including<br />
associated restroom and<br />
covered seating areas.<br />
Construction Cost<br />
$3 M<br />
Duration<br />
Sep. 2013 – Feb. 2014<br />
Friday, September 21, 2012
BP-408B, Cell Lot & Return <strong>to</strong> Terminal A Road<br />
Project Scope<br />
Add a Return <strong>to</strong> Terminal<br />
A Ramp and construct<br />
new cell phone lot.<br />
Construction Cost<br />
$13 M<br />
AIRPORT BOULEVARD<br />
(SOUTH BOUND)<br />
NEW CELL LOT<br />
(227 +/- SPACES)<br />
RETURN TO TERMINAL “A” ROAD<br />
Duration<br />
Sep. 2013 – Sep. 2014<br />
TAXIWAY “J”<br />
Friday, September 21, 2012
BP-408B, Taxiway A Widening and Related Work<br />
Project Scope<br />
Add a Return <strong>to</strong> Terminal A<br />
Ramp and construct new cell<br />
phone lot.<br />
Construction Cost<br />
$13 M<br />
Duration<br />
Sep. 2013 - Sep. 2014<br />
Friday, September 21, 2012
BP-432, Optimization of Checked Baggage Inspection<br />
Systems (CBIS)<br />
Project Scope<br />
Modify CBIS in Pods C<br />
and D <strong>to</strong> optimize<br />
performance. Scope<br />
includes the<br />
replacement of the BP-<br />
214 make-up system<br />
and all required<br />
infrastructure<br />
improvements.<br />
Construction Cost<br />
$25 M<br />
Duration<br />
Jan. 2013 – Mar. 2014<br />
Friday, September 21, 2012
BP-434, Runway 18R-36L Rehabilitation and Related Work<br />
Project Scope<br />
Rehabilitate Runway 18R-36L,<br />
including repaving shoulders, blast<br />
pads and joint replacement.<br />
Construction Cost<br />
$18 M<br />
Duration<br />
Nov. 2013 – Aug. 2014<br />
Friday, September 21, 2012
BP-435, Light Fixture Replacement for Garages A, B,<br />
and Terminal Top<br />
Project Scope<br />
Replacement of over<br />
11,000 light fixtures in the A<br />
and B side structural<br />
parking garages and the<br />
terminal <strong>to</strong>p parking<br />
garage.<br />
Construction Cost<br />
$3 M<br />
Duration<br />
Jul. 2013 – Jun. 2014<br />
Friday, September 21, 2012
BP-438, Baggage Make-Up Ventilation Improvements<br />
Project Scope<br />
Upgrade the ventilation<br />
systems <strong>to</strong> meet current<br />
code requirements at<br />
Landside Terminal, Level 2.<br />
Construction Cost<br />
$5 M<br />
Duration<br />
Sep. 2013 – Mar. 2014<br />
Friday, September 21, 2012
BP-439, Landside Emergency Power Generation Expansion<br />
Project Scope<br />
Expand the emergency<br />
power generation capacity<br />
and building at the<br />
southwest end of the<br />
Landside Terminal.<br />
Construction Cost<br />
$12 M<br />
Duration<br />
May 2013 – May 2014<br />
Friday, September 21, 2012
V-629, Add Two New Flat Plate Make-Up<br />
Carousels<br />
Project Scope<br />
Furnish and install<br />
two new flat plate<br />
make-up carousel on<br />
Level 2, B-Side<br />
baggage make-up<br />
area.<br />
Construction Cost<br />
$500,000<br />
Duration<br />
Jan. 2013 – Jun. 2013<br />
Friday, September 21, 2012
V-642, Hyatt Cold Water Pipe<br />
Replacement – Phase 3<br />
Project Scope<br />
Replace existing<br />
galvanized <strong>do</strong>mestic<br />
water main located on<br />
the 4 th level of the<br />
Hyatt Hotel.<br />
Construction Cost<br />
$275,000<br />
Duration<br />
Oct. 2012 – April 2013<br />
Friday, September 21, 2012
V-645, Smoke Control Improvements<br />
Hyatt Atrium and Level 3 Core<br />
Project Scope<br />
Install three new smoke<br />
exhaust fans in the Hyatt<br />
Hotel and two in the Level 3<br />
center core area.<br />
Construction Cost<br />
$700,000<br />
Duration<br />
Nov. 2012 – Mar. 2013<br />
Friday, September 21, 2012
Potential Upcoming Projects<br />
• Landside Ticket Lobby Renovation/Remodeling<br />
– V-663, Ticket Lobby Program – Relocate American Airlines<br />
– V-664, Ticket Lobby Program – Relocate Jet Blue Airlines<br />
– BP-440, Ticket Lobby Program – Communications, Rooms, Level 3<br />
– Others…..<br />
• Airside 4 Infrastructure/Renovation Projects<br />
– 90’s Wing Gate Conversion<br />
– FIS/CBP Renovation/Expansion<br />
– Central Chiller Plant<br />
• South <strong>Airport</strong> APM Complex<br />
– APM Guideway<br />
– APM Station<br />
– Parking Garage<br />
– Site Work/Utilities<br />
– Roadway/Bridges<br />
Friday, September 21, 2012
“HOW TO DO BUSINESS WITH GOAA”<br />
CONSTRUCTION SERVICES
Delivery Systems:<br />
– Design/Bid/Build<br />
– Design/Build<br />
– Shortlisting<br />
– Construction Management<br />
Contract Types:<br />
– Lump Sum<br />
– Unit Price<br />
“HOW TO DO BUSINESS WITH GOAA”<br />
CONSTRUCTION SERVICES<br />
Contract Process:<br />
– Bid and Award<br />
– Construction Committee<br />
– Professional Services Committee<br />
– Authority Board<br />
Friday, September 21, 2012
“HOW TO DO BUSINESS WITH GOAA”<br />
CONSTRUCTION SERVICES<br />
Normal Contracting Process (Non-Federally Funded):<br />
– ≤ $300K: Direct Negotiated <strong>with</strong> Continuing Contrac<strong>to</strong>rs<br />
– $300K - $2M: Public Bid or Bid Among Continuing Contrac<strong>to</strong>rs<br />
– ≥ $2M: Public Bid<br />
Federally Funded Projects:<br />
– Public Bid<br />
Friday, September 21, 2012
“HOW TO DO BUSINESS WITH GOAA”<br />
CONSTRUCTION SERVICES<br />
Current Continuing Contrac<strong>to</strong>rs:<br />
Vertical (Thru Jan 2015):<br />
BRPH Construction Services, Inc.<br />
Clancy & Theys Construction Company<br />
Gomez Construction Company<br />
H.W. Davis Construction, Inc.<br />
R.L. Burns, Inc.<br />
Verde Construction Managers, LLC<br />
Horizontal (Thru Mar 2013):<br />
CEM Enterprises, Inc.<br />
Gibbs & Register, Inc.<br />
JCB Construction, Inc.<br />
Prime Construction Group, Inc.<br />
Electrical (Thru Mar 2013):<br />
Electric Services, Inc.<br />
The New Florida Industrial Electric, Inc.<br />
H.L. Pruitt Corporation<br />
Mor<strong>to</strong>n Electric, Inc.<br />
Roofing (Thru Apr 2014):<br />
Advanced Roofing, Inc.<br />
General Works, LLC<br />
P&A Roofing and Sheet Metal, Inc.<br />
Signage (Thru July 2014):<br />
AC Signs, LLC<br />
The Baron Group, Inc.<br />
Friday, September 21, 2012
“HOW TO DO BUSINESS WITH GOAA”<br />
CONSTRUCTION SERVICES<br />
Construction Opportunities:<br />
• Continuing Contrac<strong>to</strong>rs<br />
• GOAA Website<br />
• Local Newspapers (Sunday & Wednesday)<br />
• Call Office of Small Business Development<br />
• Tenant Projects<br />
Project Designations:<br />
• “BP”: Bid Package, Public Bid and Award<br />
• “G”: Graphics/Signage, using Continuing Contrac<strong>to</strong>r<br />
• “V”: Vertical Package, using Continuing Contrac<strong>to</strong>r<br />
• “H”: Horizontal Package, using Continuing Contrac<strong>to</strong>r<br />
• “E”: Electrical Package, using Continuing Contrac<strong>to</strong>r<br />
• “R”: Roofing Package, using Continuing Contrac<strong>to</strong>r<br />
Friday, September 21, 2012
“HOW TO DO BUSINESS WITH GOAA”<br />
CONSTRUCTION SERVICES<br />
Unique Aspects <strong>to</strong> Construction on the <strong>Airport</strong>:<br />
– ID Badge Requirement<br />
– E-Verify<br />
– AOA Access<br />
– Insurance<br />
– Bonds<br />
– Night Work<br />
– MWBE/LDB/DBE Programs<br />
– Coordination<br />
– Safety<br />
– Public Environment<br />
– No Impact <strong>to</strong> <strong>Airport</strong> Operations<br />
Continuing Initiatives<br />
– Energy Conservation<br />
– Water Conservation<br />
– Maintain Infrastructure Focus<br />
Friday, September 21, 2012
“HOW TO DO BUSINESS WITH GOAA”<br />
ENGINEERING SERVICES
“HOW TO DO BUSINESS WITH GOAA”<br />
ENGINEERING SERVICES<br />
Design Procurement Process (Non-Federally Funded):<br />
– ≤ $2M: Direct Negotiated <strong>with</strong> Continuing Design Consultant<br />
– ≥ $2M: Public Advertisement, Qualification Based Selection<br />
Federally Funded Projects:<br />
– Public Advertisement, Qualification Based Selection<br />
Friday, September 21, 2012
Current Design Consultants:<br />
“HOW TO DO BUSINESS WITH GOAA”<br />
ENGINEERING SERVICES<br />
Architectural (Thru Feb 2013):<br />
Civil (Thru Jul 2013):<br />
MEP (Thru Nov 2012):<br />
Environmental (Thru May 2014):<br />
KBJ Architects, Inc.<br />
MLM-Martin Architects, Inc.<br />
Rhodes & Bri<strong>to</strong> Architects, Inc.<br />
Avcon, Inc.<br />
DMJM Aviation, Inc.<br />
Kimley-Horn and Associates, Inc.<br />
Engineering & Environmental Design, Inc.<br />
Matern Professional Engineering<br />
TLC Engineering for Architecture, Inc.<br />
AECOM USA, Inc.<br />
Nodarse & Associates, Inc.<br />
Geotechnical Environmental Consultant, Inc.<br />
Friday, September 21, 2012
“HOW TO DO BUSINESS WITH GOAA”<br />
ENGINEERING SERVICES<br />
Current Design Consultants:<br />
Specialty (Thru Mar 2013):<br />
Transportation (Thru Aug 2014):<br />
Building Envelope (Thru May 2013):<br />
Lea+Elliot, Inc. – APM Systems<br />
HDR Engineering, Inc.<br />
CMC, A Florida Joint Venture<br />
MACTEC – Building Envelope<br />
Gale Associates, Inc. – Building Envelope<br />
Friday, September 21, 2012
“HOW TO DO BUSINESS WITH GOAA”<br />
ENGINEERING SERVICES<br />
Upcoming Design Projects<br />
– Runway 18R-36L Rehabilitation<br />
– Landside Ticket Lobby Modifications<br />
– Return <strong>to</strong> Terminal A Road/Bus and Taxi Hold Facility<br />
– Commercial Curb Improvements<br />
– Airside 4 Infrastructure/Renovations<br />
– South <strong>Airport</strong> APM Complex<br />
Friday, September 21, 2012
“HOW TO DO BUSINESS WITH GOAA”<br />
ENGINEERING SERVICES<br />
Unique Aspects <strong>to</strong> Design Services on the <strong>Airport</strong>:<br />
– ID Badge Requirement<br />
– E-Verify<br />
– AOA Access<br />
– Insurance<br />
– GOAA Design Guidelines<br />
– Documenting Existing Conditions<br />
– Phasing vs. <strong>Airport</strong> Operations<br />
– Coordination <strong>with</strong> Adjacent and Future Projects<br />
– MWBE/LDB/DBE Programs<br />
Continuing Initiatives<br />
– Energy Conservation/Sustainability<br />
– BIM<br />
Friday, September 21, 2012