06.05.2014 Views

Haubenschild Farms Final Report - The Minnesota Project

Haubenschild Farms Final Report - The Minnesota Project

Haubenschild Farms Final Report - The Minnesota Project

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

<strong>The</strong> <strong>Minnesota</strong> <strong>Project</strong> August 2002<br />

Results to Date<br />

In September 1999, construction was complete and the manure began to be fed to the<br />

digester. On September 9, the engine was started using propane in order to heat the manure<br />

in the tank. By October 1, biogas production was sufficient to fuel the engine.<br />

Electricity and Biogas Production<br />

Figure 2 shows the production of biogas and electricity by the installation from October 1,<br />

1999 until July 7, 2000. As the bacteria in the digester have grown and flourished, and as<br />

the herd size was expanded, the measured biogas output of the digester steadily increased<br />

from about 30,000 cubic feet/day of biogas in October 1999 to about 70,000 cubic feet/day<br />

by July 2000, where it has remained fairly constant.<br />

Figure 2: Measured Biogas and Electricity Production to Date 20<br />

160<br />

90,000<br />

140<br />

80,000<br />

Electricity Production<br />

(kW)<br />

120<br />

100<br />

80<br />

60<br />

40<br />

20<br />

Electricity Production, weekly<br />

average (kWh/hr)<br />

Average Daily Biogas Production,<br />

1 week average (cubic feet/day)<br />

70,000<br />

60,000<br />

50,000<br />

40,000<br />

30,000<br />

20,000<br />

10,000<br />

Biogas Production<br />

(cubic feet/day)<br />

0<br />

0<br />

1-Oct-99<br />

3-Dec-99<br />

4-Feb-00<br />

9-Apr-00<br />

9-Jun-00<br />

11-Aug-00<br />

13-Oct-00<br />

15-Dec-00<br />

16-Feb-01<br />

20-Apr-01<br />

22-Jun-01<br />

24-Aug-01<br />

26-Oct-01<br />

28-Dec-01<br />

1-Mar-02<br />

3-May-02<br />

5-Jul-02<br />

20 Biogas volume is calculated from meter readings of biogas going into the generator. If the generator is<br />

down or cannot accomidate the full volume of biogas produced, the biogas is flared and will not be metered.<br />

During engine down time, biogas production is estimated from the average biogas production during engine<br />

operating hours on a weekly basis. However, since at least July 2000, the digester has been producing excess<br />

biogas that cannot be accommodated even with the engine in service, so full biogas production is not known.<br />

20

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!