06.05.2014 Views

Integrating Environmental, Engineering and Constructability ...

Integrating Environmental, Engineering and Constructability ...

Integrating Environmental, Engineering and Constructability ...

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

What is the Final Horizontal Layout?<br />

This layout depicts all project facilities for permitting <strong>and</strong><br />

l<strong>and</strong> acquisition purposes<br />

In many cases, permits must be obtained for exactly<br />

what will be built, so a certain amount of engineering<br />

must be done at an early stage<br />

In a perfect world, micrositing occurs prior to submitting<br />

major permit applications <strong>and</strong> conducting NEPA (or<br />

state equivalent) review<br />

• Failure to do so often means the need to do permit<br />

modifications, supplemental EISs, <strong>and</strong>/or variances during<br />

construction<br />

In the real world things aren’t that simple.<br />

• If possible, permit for flexibility<br />

Wind Energy Services<br />

Wind Energy Services

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!