What is the Final Horizontal Layout?<br />
This layout depicts all project facilities for permitting <strong>and</strong><br />
l<strong>and</strong> acquisition purposes<br />
In many cases, permits must be obtained for exactly<br />
what will be built, so a certain amount of engineering<br />
must be done at an early stage<br />
In a perfect world, micrositing occurs prior to submitting<br />
major permit applications <strong>and</strong> conducting NEPA (or<br />
state equivalent) review<br />
• Failure to do so often means the need to do permit<br />
modifications, supplemental EISs, <strong>and</strong>/or variances during<br />
construction<br />
In the real world things aren’t that simple.<br />
• If possible, permit for flexibility<br />
Wind Energy Services<br />