04.05.2014 Views

Strategy Survival Guide

Strategy Survival Guide

Strategy Survival Guide

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

• The severity of the risk - categories for severity might be Critical (that is, adverse effect such that<br />

continuation of the project is unacceptable), Major, Significant, and Minor<br />

• The risk owner - each risk should be assigned to an individual who is best placed to monitor it and<br />

manage any necessary actions<br />

• The response to the risk which either reduces the probability of the risk happening or reduces the<br />

damaging effects of the risk should it happen<br />

• The current status of the risk itself and progress of any actions relating to the management of the<br />

risk.<br />

A risk log should be reviewed and updated regularly.<br />

References<br />

The Risk Support Team at HM Treasury are responsible for implementing the <strong>Strategy</strong> Unit report on<br />

handling risk in government and provides guidance on all aspects of risk management, including the<br />

Principles of Managing Risks to the Public.<br />

Managing risks<br />

In Practice: SU GM Crops Project<br />

The SU GM Crops project formed one strand of a highly-charged and controversial dialogue around the<br />

role of GM technology in the UK. This had the two-fold impact of (1) increasing the number of risks<br />

faced by the project, and (2) raising the stakes in the event of things going wrong. In this context, active<br />

management of risks was essential.<br />

The team worked together to identify risks and to assign to them both impacts and probabilities. The<br />

possible consequences of each risk were identified, and responsibility for preventative actions assigned<br />

to specific team members. Risks varied from the relatively prosaic – e.g. team members leaving partway<br />

through the project (which happened twice in this instance) – to the much more dramatic – e.g. the<br />

US bringing a case against the EU under the WTO, in respect of policy on GM (which happened<br />

towards the end of the project).<br />

Many of the risks identified in the risk register came to pass during the project. The fact that the team<br />

had already thought about these risks undoubtedly made them easier to deal with, although the use of a<br />

risk register in itself was not a panacea. For example:<br />

• In several cases the team’s assessment of impact or probability proved inaccurate. For<br />

example, the early departure of team members was classed as medium / high impact but only<br />

medium probability – in the event, two team members left early, but the impact if anything was<br />

positive, because it enabled different skills to be brought into the project at different stages.<br />

• Even where risks were identified, it was not always possible to mitigate against them or to deal<br />

effectively with the consequences. For example, the availability of good data from the parallel<br />

Science Review was identified early on as a key risk. But despite best efforts from the SU and<br />

the Science Review team, the timing of the two strands restricted the opportunities for datasharing.<br />

• Some risks were missed completely – partly because the team did not keep the risk register<br />

fully up to date. For example, the team failed to identify and prepare for the impact of a reshuffle<br />

of Ministers on the governance of the project.<br />

Overall, however, the use of active risk management techniques enabled the team to steer a successful<br />

course through a potential minefield, relatively unscathed.<br />

<strong>Strategy</strong> <strong>Survival</strong> <strong>Guide</strong> – <strong>Strategy</strong> Skills<br />

Page 71

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!