<strong>Cost</strong>s <strong>of</strong> the Project<br />

The project entails the design and construction <strong>of</strong> capital improvements including river bank<br />

stabilization, track reconstruction, and rail-highway grade crossing improvements. Track<br />

reconstruction and rail-highway grade crossing improvements are included for both the A-OK<br />

and BNSF portions <strong>of</strong> the project.<br />

Capital <strong>Cost</strong>s<br />

These costs include not only construction costs, but also design and project management costs.<br />

The estimated cost <strong>of</strong> the first phase <strong>of</strong> the project, including design and construction, is<br />

$32,105,949. Construction would be initiated in the second quarter <strong>of</strong> 2010 and would be<br />

completed in 2011, with approximately $20.8 million expended in 2010, and $11.3 million in<br />

2011. The drawdown <strong>of</strong> funds is tabulated in Table 2.<br />