<strong>Cost</strong>s <strong>of</strong> the Project<br />
The project entails the design and construction <strong>of</strong> capital improvements including river bank<br />
stabilization, track reconstruction, and rail-highway grade crossing improvements. Track<br />
reconstruction and rail-highway grade crossing improvements are included for both the A-OK<br />
and BNSF portions <strong>of</strong> the project.<br />
Capital <strong>Cost</strong>s<br />
These costs include not only construction costs, but also design and project management costs.<br />
The estimated cost <strong>of</strong> the first phase <strong>of</strong> the project, including design and construction, is<br />
$32,105,949. Construction would be initiated in the second quarter <strong>of</strong> 2010 and would be<br />
completed in 2011, with approximately $20.8 million expended in 2010, and $11.3 million in<br />
2011. The drawdown <strong>of</strong> funds is tabulated in Table 2.<br />