<strong>Lakeland</strong> Area<br />
<strong>Transportation</strong> <strong>Projects</strong><br />
<strong>Lakeland</strong> Economic Development Council<br />
November 29, 2010
On-Going Roadway <strong>Projects</strong><br />
<strong>City</strong> and State <strong>Projects</strong><br />
• Waring Road Extension<br />
• SR 33 – USFP “East/West Road”<br />
• Polk Parkway @ Pace Road Interchange<br />
• Carpenters Way<br />
• Edgewood Extension<br />
• State Road 33
On-Going Roadway <strong>Projects</strong><br />
County <strong>Projects</strong><br />
• <strong>Lakeland</strong> Highlands Road<br />
– Polk Parkway to CR 540A<br />
• Harden Boulevard Improvements<br />
– Polk Parkway to West Pipkin Road<br />
• Additional southbound Lane<br />
• Intersection realignment at Pipkin/Old Highway 37<br />
Intersection<br />
• County Line Road<br />
– SR 60 to Ewell Road
On-Going Roadway <strong>Projects</strong><br />
Other <strong>Projects</strong><br />
• Wabash Extension Project Development &<br />
Environment Study<br />
– Ariana Street to Harden Boulevard<br />
• Beacon Road Alignment Study<br />
– Harden Boulevard to Wabash Extension<br />
• County Line Road @ Interstate 4: Ramp<br />
Signalization
Waring Road Extension<br />
West Pipkin Road to Old Medulla Road<br />
• Two-lane construction, Four-lane ROW<br />
• Construction Completed: July 2010<br />
• Construction Cost: Approx. $2.3 Million<br />
• Funded by FDOT, Polk County and <strong>City</strong> <strong>of</strong><br />
<strong>Lakeland</strong>
Waring Road Extension
SR 33 – USFP<br />
East-West Road
SR 33 –USFP<br />
East-West Road<br />
SR 33 @ N. FirstPark to Polk Parkway @ Pace Road<br />
• $34.8 Million through Federal ARRA Program<br />
• Two- and four-lane roadway with multi-use<br />
path<br />
• FDOT allocated additional funding to<br />
complete full project concept<br />
• Right-<strong>of</strong>-Way dedicated by Williams<br />
Company and BDG I-4 (Brown)
SR 33 – USFP<br />
East-West Road<br />
• Design/Build Contract –<br />
Commenced on 2/9/10<br />
• Contract time ends on<br />
12/27/11<br />
• Project approaching 40%<br />
completion<br />
• Final construction plans<br />
released on 11/01/10<br />
• Embankment work,<br />
drainage installation
E-W Road – Looking south toward FirstPark
USF Loop Road – Looking north near Polk Parkway
Polk Parkway/Pace Road<br />
Interchange
Polk Parkway/Pace Road<br />
Interchange<br />
• Construction Cost Estimate: $30 million<br />
• Includes four-lane improvement on Polk<br />
Parkway between Pace Road and Interstate 4<br />
• Connects East-West Road with Pace Road<br />
• Construction Complete: September 2011
Pace Road Interchange - Looking Southwest
Berkley Road<br />
Future Mt. Olive Road Ext.<br />
Pace Road Interchange - Looking East
Polk Parkway/Pace Road<br />
Interchange<br />
• Scheduled Completion:<br />
September 2011<br />
• $.25 toll will be collected on<br />
SB <strong>of</strong>f- and NB on-ramps<br />
• SUNPASS-only toll collection<br />
on new ramps (similar to UCF<br />
exit on SR 417)<br />
• Paving <strong>of</strong> SB lanes,<br />
embankment work, earthwork<br />
for SB SUNPASS lane, bridge<br />
beam placement<br />
Pace Road Interchange - Looking North
Carpenters Way<br />
Wedgewood G.C.<br />
Best Buy<br />
Target
Carpenters Way<br />
• Two-lane improvement,<br />
culvert replacement and<br />
sidewalk installation<br />
• Work continues on mid- and<br />
eastern segment. Church<br />
access closed from the east<br />
• Eastern section expected to<br />
be open on December 6 th , at<br />
which time west section will<br />
be closed<br />
• Potential for early-February<br />
2011 completion, depending<br />
on weather
Crevasse Street Extension<br />
• Final alignment<br />
determination and partial<br />
design underway.<br />
Construction not<br />
programmed<br />
• 2-lane cross-section<br />
• Coordination with<br />
development community<br />
o Gateway Commons<br />
• 4-lane cross-section<br />
on west end
Harden Blvd<br />
S. Florida<br />
Avenue<br />
Cleveland<br />
Heights Blvd<br />
<strong>Lakeland</strong><br />
Highlands Rd<br />
Edgewood Drive Extension<br />
South Florida Avenue to Harden Boulevard<br />
N<br />
Beacon Rd<br />
Grasslands<br />
Edgewood Dr<br />
Polk Pkwy (Toll)
Edgewood Drive Extension<br />
South Florida Avenue to Harden Boulevard<br />
• Current activities:<br />
• West End: Ditch relocation, soils mitigation to support road,<br />
excavation for retention pond (May 2011 completion).<br />
• East End: Demolition <strong>of</strong> trees and various structures (February<br />
2011 completion).<br />
• Utility Relocation: Spring/Summer 2011<br />
• Road Construction: Advertisement scheduled for Late<br />
Summer 2011<br />
• Start <strong>of</strong> Construction: Fall 2011<br />
• Open to Traffic in Fall 2012<br />
• Federal and County funding
Palmeden Drive<br />
Placida Place<br />
Placida Avenue<br />
S. Florida Ave<br />
Edgewood Drive Extension<br />
South Florida Avenue to Harden Boulevard<br />
Windsor Street<br />
Prado Place
Lincoln Avenue<br />
Eden Parkway<br />
Edgewood Drive Extension<br />
South Florida Avenue to Harden Boulevard<br />
Southwest<br />
Middle School<br />
Edgewood Drive<br />
Prado Place
State Road 33
State Road 33<br />
Interstate 4 @ Exit 33 to Old Combee/Deeson Pointe<br />
• Four-laning, intersection, sidewalk<br />
and bus stop improvements<br />
• Design nearing completion.<br />
Advertised expected in Spring 2011<br />
with construction beginning in<br />
Summer 2011<br />
• Funded through agreements with<br />
USF Polytechnic, Bridgewater and<br />
FDOT<br />
• December 6 th Public Hearing (6 to 8<br />
p.m.) – Days Inn @ 4502 N Socrum<br />
Loop Road
State Road 33<br />
Interstate 4 @ Exit 33 to Old Combee/Deeson Pointe
<strong>Lakeland</strong><br />
Highlands Road
<strong>Lakeland</strong> Highlands Road<br />
Polk Parkway to CR 540A<br />
• Implemented by Polk County<br />
• Construction Cost: Approximately $12 Million<br />
• Construction Began: February 2010<br />
• Estimated Completion: Late 2011<br />
• Current activities: Waterline & stormwater<br />
drainage, pond, curb & gutter, subgrade<br />
installation
County Line Road<br />
Ewell Road to State Road 60<br />
• Implemented by Polk County<br />
• Widening from two to four lanes<br />
• Construction Cost: Approx. $6.5 Million<br />
• Construction Start: Early December 2010<br />
• Contract Schedule: 408 Days
Harden Boulevard<br />
Improvements
Harden Boulevard<br />
Improvements<br />
Polk Parkway to West Pipkin Road<br />
• Addition <strong>of</strong> second southbound through-lane<br />
• Realignment <strong>of</strong> Harden/Pipkin/Old Highway<br />
37 Intersection<br />
• Funded through Harden Parkway CRA and<br />
Polk County<br />
• Construction Underway
• $1.052 million received from<br />
State Economic Development<br />
Trust Fund (OTTED)<br />
• GTECH Corporation, LEDC and<br />
<strong>City</strong> prepared funding<br />
application.<br />
• Signal warrant analysis is<br />
underway.<br />
• Analysis includes South<br />
Frontage Road – County Line<br />
Road intersection<br />
County Line Road<br />
@ Interstate 4<br />
Signalization Improvements
Wabash Avenue Extension<br />
Ariana Street to Harden Boulevard<br />
• PD&E Study Underway<br />
• Two alternative corridors<br />
presented on October 12 th<br />
• Study completion in 2011<br />
• Coordination w/ Beacon<br />
Road Alignment Study
Wabash Avenue Extension<br />
Ariana Street to Harden Boulevard
Wabash Avenue Extension<br />
Beacon Corridor to Polk Parkway
Wabash Avenue Extension<br />
Polk Parkway to Harden Boulevard
Parker Street<br />
Massachusetts Ave. to North Lake Parker Ave.
Other Important Initiatives<br />
• Polk TPO 2035 Mobility<br />
<strong>Transportation</strong> Vision Plan<br />
– Currently underway<br />
– Roadway, Transit,<br />
Bicycle/Pedestrian and<br />
Operational <strong>Projects</strong><br />
– Basis for Future Priorities<br />
– Adoption scheduled for<br />
December 7 th @ 9 a.m.<br />
– http://www.2035mobilityvisionplan.org