23.04.2014 Views

Boring - Trenchless International

Boring - Trenchless International

Boring - Trenchless International

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

istt news<br />

April 2010 - <strong>Trenchless</strong> <strong>International</strong><br />

South African award<br />

recognises HDD project<br />

A reticulation project in South Africa, using horizontal directional drilling to connect ten buildings in<br />

Johannesburg’s CBD, has received the 2009 SASTT Award for Excellence.<br />

The Joop van Wamelen SASTT Award<br />

was presented to Managing Member<br />

Sam Efrat and General Manager Marco<br />

Camarda of <strong>Trenchless</strong> Technologies cc<br />

at the SASTT Annual General Meeting<br />

by the outgoing SASTT President Johann<br />

Wessels. The award ceremony took place<br />

at the regional offices of Johannesburg<br />

Water in Midrand on 2 February 2010.<br />

Award ceremony L-R, Marco Camarda,<br />

Samuel Efrat and Johann Wessels.<br />

Fast facts<br />

• Contractor: <strong>Trenchless</strong><br />

Technologies cc<br />

• Employer: ABSA Bank<br />

Limited<br />

• Project Managers: Mokala<br />

Collins/JM Henrey &<br />

Associates Joint Venture<br />

• Consultants: Taemane/SDE<br />

and Asak/LC.<br />

The project<br />

The works involved connecting ten of<br />

ABSA Bank’s buildings in Johannesburg’s<br />

CBD with 100 underground sleeves for<br />

electricity, gas, fibre optic, as well as low<br />

temperature hot water and chilled water.<br />

Drilling took place from building basement-to-basement<br />

beneath the busy CBD<br />

roadways, at depths of up to 16 metres,<br />

using horizontal directional drilling.<br />

Sleeve diameters ranged in size from<br />

160, 225, 450, 500, 560 and 710 mm using<br />

PE 100 PN 8 HDPE pipe. The 160 mm and<br />

225 mm sleeves were installed in bundles<br />

of three, four or six pipes. The ten month<br />

contract had a value of R13 million<br />

($US1.7 million). The type of contract<br />

document used was the NEC3.<br />

Challenges and solutions<br />

The ABSA building’s basement floors<br />

were originally designed to support<br />

the weight of a typical sedan vehicle.<br />

Consequently the Terra-Jet 7520 automatic<br />

rod loading system was removed to<br />

decrease the machine weight and propping<br />

was undertaken from the floor below<br />

to support all areas over which the drill<br />

needed to travel into the required positions<br />

within basements.<br />

A floor to sprinkler height restriction<br />

required that all equipment be less than<br />

2.1 metres in height. Consequently the<br />

Terra-Jet 7520 was further modified by<br />

removing the operator cabin, rebuilding<br />

the hydraulic oil tank at a lower position<br />

and lowering the encapsulating body work<br />

such that the remodelled drill resembled a<br />

tank with a height of only 1.8 metres.<br />

The majority of the installations took<br />

place in clay whilst the remaining 20 were<br />

in rock. The presence of the rock necessitated<br />

the use of percussive hammer and<br />

rock reamers to expand the holes to the<br />

required diameters.<br />

Lateral support ground anchors were<br />

encountered during drilling on 26 of the<br />

Terra-Rock Air Percussion Head<br />

OD 95.<br />

TCI Roller low torque rock reamer.<br />

crossings. The presence and position of<br />

these were unforeseen, and resulted in<br />

the entanglement of drilling equipment<br />

in several instances. Drilling tools were<br />

pulled, pushed and rotated until they<br />

became free or broke the ground anchoring<br />

cables. In two instances the entangled<br />

cable would not break and an acetylene<br />

oxygen cutter was modified and inserted<br />

within the bore to cut the cable and free<br />

the drilling tools.<br />

In order to gain access to the drill face,<br />

coring to remove concrete lateral walls<br />

from 300 – 500 mm thick was required.<br />

Containment of the large volumes of bentonite<br />

and spoil was a necessity as the<br />

basements are maintained in a pristine<br />

condition and in daily use. This was made<br />

possible using specially constructed tanks<br />

and brick burms.<br />

The removal of bentonite to the surface<br />

was one of the greatest challenges the<br />

project faced. Initially pumping, which<br />

is by far the preferred method of spoil<br />

removal did not look feasible. This was<br />

due to requiring extremely long pipe<br />

lengths – of up to 600 metres – to remove<br />

the bentonite from basement-to-basement<br />

up the vehicular ramps. However, at the<br />

planning stage the idea was put forward<br />

Ground anchor in rocky bore.<br />

Pilot drill and bentonite collection.<br />

to core holes through the slabs and enable<br />

vertical pumping along the shortest<br />

route to reduce pumping lengths to less<br />

than 200 metres.<br />

For the first six months of contract no<br />

drilling was allowed during the ‘freeze<br />

period’ from the 26th of the preceding<br />

month to the 5th of the following month.<br />

This was to prevent any potential damage<br />

to cables and infrastructure during<br />

the busy end of month banking period.<br />

This resulted in a very tight work schedule<br />

necessitating crews to work day and night<br />

shifts, seven days a week.<br />

The location of drilling equipment on<br />

either side of the walls was required<br />

through concrete, rock and at depths of<br />

up to 16 metres. <strong>Trenchless</strong> Technology<br />

cc made use of the radio detection i-track<br />

system and tracked the equipment horizontally<br />

from the basements on either side<br />

of each crossing.<br />

Confined access into basements via<br />

vehicular ramps required short six metre<br />

lengths of HDPE pipe to be individually<br />

transported down into basements where<br />

they were butt-welded into long continuous<br />

lengths for installation.<br />

Whilst in the museum the only access<br />

was by means of a lift and pipe lengths<br />

were limited to three metres. Here, and<br />

in other confined and storage areas and<br />

plant rooms, the bentonite was collected<br />

in tanks and removed in ‘wheelie’ bins.<br />

In two instances the HDPE pipe was<br />

hammered into the completed bore from<br />

the drill machine side in a pipe ramming<br />

operation, as there was no access to pull<br />

the piping in from the opposite side of the<br />

bore.<br />

The benefits of using <strong>Trenchless</strong><br />

Technology for the ABSA project<br />

The installations were exceptionally<br />

deep, precluding conventional excavation<br />

methodology. There was no damage<br />

to roadways and existing buried infrastructure,<br />

nor was there any disruption<br />

to pedestrian and vehicular traffic in the<br />

busy CBD area. Cost savings were also<br />

significant when compared to other possible<br />

methodologies.<br />

Why HDD?<br />

HDD allowed the insertion of the preferred<br />

HDPE sleeves without requiring the<br />

installation of a temporary pipe or permanent<br />

rigid pipe, followed by the HDPE pipe<br />

installation. HDD required no thrust abutment<br />

wall, and also allowed for adequate<br />

steering accuracy. The equipment is selfpropelled<br />

and capable of drilling in a wide<br />

range of soil conditions including clay and<br />

rock. It is also sufficiently compact and<br />

manoeuvrable to be able to operate in the<br />

confined basement spaces.<br />

Six metre lengths of HDPE piping.<br />

<strong>Trenchless</strong> Technologies cc was established<br />

in 1991 and to date have completed<br />

over 220,000 metres of trenchless pipeline<br />

rehabilitation and new installation works.<br />

They have been the Southern African<br />

agent for Terra AG since 1993.<br />

Previous awards include the SAICE<br />

Pretoria Branch Award for Technical<br />

Maxi-Rig Directional Drills<br />

Auger <strong>Boring</strong> Machines<br />

Product Tooling & Accessories<br />

Mud Pump & Cleaning Systems<br />

Oil & Gas Drill Rigs<br />

Mid-Size Directional Drills<br />

Completed installation with basement<br />

returned to their pristine condition.<br />

Excellence in 2000, along with the City<br />

of Tshwane and consultants Bigen<br />

Africa, for the rehabilitation of sewers<br />

in Mamelodi. The SASTT Award<br />

of Excellence in 2007, along with<br />

Johannesburg Water and Consultants<br />

Vela VKE for the rehabilitation of sewers<br />

pipes in Klipspruit Basin.<br />

Exceptional Force … Reliable Results.<br />

For 40 years, customers worldwide have<br />

come to know American Augers as a<br />

dedicated manufacturer of underground<br />

technology equipment, which includes<br />

state-of-the-art horizontal directional<br />

drills, earth boring machines, mud pump<br />

and cleaning systems, oil and gas drill<br />

rigs, and various product tooling or<br />

accessory items. Each of the product<br />

categories produce equipment that<br />

maintains rugged, unsurpassed power,<br />

and industry leading designs.<br />

istt news<br />

April 2010 - <strong>Trenchless</strong> <strong>International</strong><br />

18<br />

AA Company island Ad TI.indd 1<br />

12/14/09 4:57 PM<br />

19

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!