bid document for the work - IDCO

bid document for the work - IDCO bid document for the work - IDCO

20.04.2014 Views

PREAMBLE TO THE SCHEDULE OF QUANTITIES 1. The quantities given in this Schedule of Quantities are liable to variation. Such variation in quantities shall not, however, vitiate the contract in any way whatsoever and Contractor shall be paid for actual measured quantities of work executed by them at the rates given in the tender. 2. The rate quoted shall include all the operations, materials, equipments etc. mentioned in the specifications of respective items of work required to complete job. 3. The rate quoted shall include all statutory taxes in force of local body, State or Central Govt., such as Entry Tax, VAT, Octroi, Sales Tax, VAT. Contract Sales Tax, Royalty etc., the cost of all carriage of materials, labour, tools and plants, curing and finishing, centering and shuttering, loading and unloading, storage, insurance and all other incidental charges etc. complete. 4. The rates quoted in the Schedule of Quantities are to be full and inclusive of the works described in the Schedule of Quantities, specification including all costs and expenses which may be required for the execution of the work described together with other associated items such as general risks, liabilities and obligations, construction of temporary stores, fencing, watching, lighting, insurance of men and materials, cleaning of site and building after completion of work. 5. The Contractor shall submit various samples of materials for the work. Only such materials as are approved shall be used in the work. All samples of approved materials shall be kept at site in the custody of the clients and shall be handed over to the Contractor after completion of the work. 6. All extra or additional work done by order of Engineer-in-charge shall be valued at the rate and prices set out in the contract, if applicable. For extra items where rate is not available in the contract the rate shall be determined as under. a) If the rate can be derived from similar items existing in the contract, it will be derived so. b) If the rate can not be derived from the existing item of contract, and the rate is existing in the schedule of rate, it will be paid at schedule of rate. c) If the rate is not existing in the schedule of rate but can be derived from analogous items existing in the schedule of rate, the rate will be derived accordingly. 60

d) If the rate can not be derived as per above clauses mentioned at (a), (b) & (c), the rate for such items is to be arrived at by actual analysis taking into consideration the market value of materials and actual labour involved. 10 % extra shall be allowed towards over head and profit. 7. All the measurement shall be jointly taken by Contractor’s representative and Engineerin-charge of the work at site and they shall be jointly signed. Any dispute arising out of this shall be referred to the Authorised Officer’s of the Corporation and his decision shall be binding on both the parties. 8. Purchase vouchers of materials in original shall be produced for verification on demand by the Authorized Officer of the Corporation. Carriage or transport charges shall not be considered for the purpose of this payment. 8. Any deviation between specifications, schedule of quantities and drawings found by the Contractor, the same shall be brought to the notice of the Authorized Officer of the Corporation immediately. 10. In case of doubt regarding the meaning and scope of specifications of different items of works and in case of variation in the provisions of IS Specification, CPHEEO Manual National Building Code and Orissa Detailed Standard Specification and I.R.C., MORTH specification, the decision of the Chairman- Managing Director, IDCO will be final and binding, and no extra claim over and above the accepted agreement, rules will be payable to the Contractor on this account. 11. The Contractor shall carry out the electrical, sanitary and water supply through the agency as approved by the Corporation whose name shall be submitted to the authorized officer for approval. All works carried out shall comply with Rules, Bye-laws, and regulations in force. All testing fees for materials as required shall be borne by the Contractor only. 12. All formalities such as obtaining approvals for water supply, drainage and fire fighting installations, getting the works inspected or tested in the presence of concerned officials obtaining completion certificates for the installation and final connection of water supply and drainage for the building shall be the responsibility of the Contractor and no extra payment shall be payable to the Contractor on this account. 13. The work of plumbing and drainage shall be carried out by skilled plumbers in line and level as instructed and as per good engineering practice. 61

d) If <strong>the</strong> rate can not be derived as per above clauses mentioned at (a), (b) & (c), <strong>the</strong> rate<br />

<strong>for</strong> such items is to be arrived at by actual analysis taking into consideration <strong>the</strong> market<br />

value of materials and actual labour involved. 10 % extra shall be allowed towards over<br />

head and profit.<br />

7. All <strong>the</strong> measurement shall be jointly taken by Contractor’s representative and Engineerin-charge<br />

of <strong>the</strong> <strong>work</strong> at site and <strong>the</strong>y shall be jointly signed. Any dispute arising out of<br />

this shall be referred to <strong>the</strong> Authorised Officer’s of <strong>the</strong> Corporation and his decision shall<br />

be binding on both <strong>the</strong> parties.<br />

8. Purchase vouchers of materials in original shall be produced <strong>for</strong> verification on demand<br />

by <strong>the</strong> Authorized Officer of <strong>the</strong> Corporation. Carriage or transport charges shall not be<br />

considered <strong>for</strong> <strong>the</strong> purpose of this payment.<br />

8. Any deviation between specifications, schedule of quantities and drawings found by <strong>the</strong><br />

Contractor, <strong>the</strong> same shall be brought to <strong>the</strong> notice of <strong>the</strong> Authorized Officer of <strong>the</strong><br />

Corporation immediately.<br />

10. In case of doubt regarding <strong>the</strong> meaning and scope of specifications of different items of<br />

<strong>work</strong>s and in case of variation in <strong>the</strong> provisions of IS Specification, CPHEEO Manual<br />

National Building Code and Orissa Detailed Standard Specification and I.R.C., MORTH<br />

specification, <strong>the</strong> decision of <strong>the</strong> Chairman- Managing Director, <strong>IDCO</strong> will be final and<br />

binding, and no extra claim over and above <strong>the</strong> accepted agreement, rules will be<br />

payable to <strong>the</strong> Contractor on this account.<br />

11. The Contractor shall carry out <strong>the</strong> electrical, sanitary and water supply through <strong>the</strong><br />

agency as approved by <strong>the</strong> Corporation whose name shall be submitted to <strong>the</strong><br />

authorized officer <strong>for</strong> approval. All <strong>work</strong>s carried out shall comply with Rules, Bye-laws,<br />

and regulations in <strong>for</strong>ce. All testing fees <strong>for</strong> materials as required shall be borne by <strong>the</strong><br />

Contractor only.<br />

12. All <strong>for</strong>malities such as obtaining approvals <strong>for</strong> water supply, drainage and fire fighting<br />

installations, getting <strong>the</strong> <strong>work</strong>s inspected or tested in <strong>the</strong> presence of concerned officials<br />

obtaining completion certificates <strong>for</strong> <strong>the</strong> installation and final connection of water supply<br />

and drainage <strong>for</strong> <strong>the</strong> building shall be <strong>the</strong> responsibility of <strong>the</strong> Contractor and no extra<br />

payment shall be payable to <strong>the</strong> Contractor on this account.<br />

13. The <strong>work</strong> of plumbing and drainage shall be carried out by skilled plumbers in line and level<br />

as instructed and as per good engineering practice.<br />

61

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!