CLAUSE - I<br />

CONDITIONS OF CONTRACT<br />

All compensation/penalty or o<strong>the</strong>r sums of money payable by <strong>the</strong> Contractor to Corporation under<br />

<strong>the</strong> terms of this contract may be deducted from, or paid by, <strong>the</strong> sale or a sufficient part of his<br />

security deposit or from <strong>the</strong> interest arising <strong>the</strong>re from, or from any sums which may be due or may<br />

become due to <strong>the</strong> Contractor by <strong>the</strong> Corporation on any account whatsoever and in <strong>the</strong> event of<br />

his security deposit being reduced by reason of any such deduction or sales as a<strong>for</strong>esaid <strong>the</strong><br />

Contractor shall within ten days <strong>the</strong>reafter make good in cash or Bank Draft any sum or sums<br />

which may have been deducted from, or raised by, sale of <strong>the</strong> security deposit or any part <strong>the</strong>reof.<br />

CLAUSE - II<br />

PENALTY FOR DELAY :<br />

Time is deemed to be essence of <strong>the</strong> contract on <strong>the</strong> part of <strong>the</strong> Contractor. The time allowed <strong>for</strong><br />

carrying out <strong>the</strong> <strong>work</strong> as entered in <strong>the</strong> tender shall be strictly observed by <strong>the</strong> Contractor and shall<br />

be reckoned from <strong>the</strong> date on which <strong>the</strong> written order to commence <strong>the</strong> <strong>work</strong> is given to <strong>the</strong><br />

Contractor. On receipt of <strong>the</strong> <strong>work</strong> order, <strong>the</strong> Contractor will give a schedule of construction and<br />

stick to <strong>the</strong> time schedule during execution. In case he fails to observe <strong>the</strong> approved time schedule<br />

during <strong>the</strong> intermediate period of <strong>the</strong> execution of <strong>work</strong>, penalty will be levied and will be recovered<br />

@ 0.5 % on <strong>the</strong> value of <strong>work</strong> lagging behind <strong>for</strong> every week delay in execution of <strong>the</strong> portion or<br />

component of <strong>work</strong> <strong>for</strong> which programme is given in <strong>the</strong> time schedule subject to maximum of 10%<br />

of <strong>the</strong> contract price.<br />

The penalty thus recovered at different stages may be waived in full or part if <strong>the</strong> authorized person<br />

of <strong>IDCO</strong> in-charge of <strong>the</strong> <strong>work</strong> is satisfied that <strong>the</strong> Contractor has made up <strong>the</strong> delay at subsequent<br />

stages and <strong>the</strong> <strong>work</strong> proceeds as per original time schedule. The decision of <strong>the</strong> authorized officer<br />

in charge of <strong>the</strong> <strong>work</strong> is final and binding as regards recovery and waive of penalty at <strong>the</strong><br />

intermediate stages of <strong>the</strong> execution of <strong>the</strong> <strong>work</strong>.<br />

If <strong>the</strong> <strong>work</strong> is delayed at <strong>the</strong> completion stage <strong>the</strong> penalty levied cannot be considered <strong>for</strong> waiver<br />

unless <strong>the</strong> <strong>work</strong> is finished in all respect within <strong>the</strong> time schedule. The <strong>work</strong> should not be<br />

considered as finished until such date as <strong>the</strong> Corporation shall satisfy as <strong>the</strong> date on which <strong>the</strong><br />

<strong>work</strong> is finished after necessary rectification of defects as pointed out by <strong>the</strong> Corporation or its<br />

authorized officer are fully complied with by <strong>the</strong> Contractor to <strong>the</strong> satisfaction. The entire amount of<br />

penalty to be paid under provision of this Clause shall not exceed 10% of <strong>the</strong> contract value of <strong>the</strong><br />

<strong>work</strong>.<br />