Your Questions:<br />
Q.1 We continuously read about ASCI Training Programme in your Newsletter. What is ASCI Training Programme ?<br />
How can we participate in this Training Programme ?<br />
A.1 In order to enhance administrative, technical and project implementation capacities, Administrative Staff<br />
College of India, Hyderabad organizes five days training programme for Public Representatives and Officials of<br />
Municipal Corporations. This training programme is financially supported by UN-HABITAT. The main objectives<br />
of this programme is to develop capacities of participants regarding maintenance of improved facilities provided<br />
by project and get acquainted with best practices in other parts of the country for better service delivery to<br />
citizens.<br />
Q.2 I am continuously reading your six issues of newsletter and understand about project activities on a regular<br />
basis. However, so far no articles is being published regarding water, sanitation, health, etc. and responsibilities<br />
of general community. If you could kindly include this suggestion then, this will increase the importance of<br />
newsletter.<br />
A.2 It is encouraging to note that, you read our newsletter on a regular basis. We acknowledge your concern<br />
regarding roles and responsibilities of community on issues like water, sanitation and health. We will definitely<br />
consider your suggestion. Our editorial team will publish relevant information very soon on identified topics.<br />
Q.3 There are provisions for construction of Treatment Plants in project cities for safe disposal of wastewater. Are<br />
they safe and beneficial in a long run?<br />
A.3 Treatment Plants constructed in Bhopal, Indore, Gwalior and Jabalpur of M.P for safe disposal of wastewater,<br />
human excreta etc. will be technically reliable. The design and structure of these treatment plants are prepared<br />
with support from International Engineers and Consultants. These plants will cater the need of projected urban<br />
population for 20-25 years. In addition, there is a provision in the design to modify as per future needs.<br />
Q.4 We have read about Public Relations Consultants in last issue of newsletter. What will be the responsibility of<br />
Public Relations Consultants in project activities?<br />
A.4 Public Relations Consultants are important unit in this project. Their main responsibilities would be to inform<br />
community about project activities and ensure active public participation in the project. This unit would use<br />
extensive media based strategy to inform community about importance and utility of project improved facilities.<br />
This unit will also inform community about problems and hurdles faced by the beneficiaries during construction<br />
work well in advance. It will work as interface between community and project officials.<br />
<strong>Project</strong> Progress: At a Glance<br />
Contact Address of the <strong>Project</strong> Implementation Units:-<br />
<strong>Project</strong> Newsletter<br />
A Publication of MP Urban (ADB) <strong>Project</strong><br />
(Urban Water Supply & Environmental Improvement <strong>Project</strong> in Madhya Pradesh)<br />
From the Editor's Desk:<br />
Greetings on the occasion of Deepawali and Eid.<br />
Dear Readers, we are enthusiastic with overwhelming response received from you for<br />
our newsletter. With this, we are publishing the seventh issue of the project newsletter.<br />
Although the month had a number of holidays on the occasion of Deepawali and Eid<br />
festivals project was successful in implementation of targeted activities.<br />
th<br />
A State Level Review meeting was organized on 9 Oct. 2006 under the chairmanship<br />
of Hon'ble Minister Shri Jayant Mallaiya, UADD, GoMP to review the status of<br />
proposed project activities. He expressed his satisfaction with the progress of the<br />
project so far.<br />
A high-level mission led by Shri Tadashi Kondo, Country Director, Asian Development<br />
Bank (ADB), New Delhi visited the state and reviewed the implementation progress in<br />
this month. Two Technical Clearance Committee meetings were also organized during<br />
the month, in which, the technical clearance was accorded to 12 packages. This will<br />
help us to expedite implementation process.<br />
An Empowered Committee Meeting was organized in this month. Committee has<br />
accorded the approval for award of contracts to the invited tenders for Indore and<br />
Gwalior.<br />
We wish to receive your encouraging support continuously.<br />
(HARI RANJAN RAO)<br />
Review Meeting by Hon'ble Minister<br />
th<br />
A State Level Meeting was organized on 9 Oct. 2006 under the Chairmanship of<br />
Hon'ble Shri Jayant Mallaiya, Minister, Urban Administration and Development<br />
Department (UADD) GoMP to review the progress of project activities. He<br />
expressed his satisfaction over progress of project. This meeting was attended by<br />
Shri Sewaram, Secretary, UADD, Shri Malay Shrivastava, Commissioner, UADD,<br />
Shri Sunil Sood, Hon'ble Mayor, Municipal Corporation, Bhopal.<br />
Shri V.N. Shejwalkar, Hon'ble Mayor, Municipal Corporation, Gwalior,<br />
Smt.(Dr.) Umashashi Sharma, Hon'ble Mayor, Municipal Corporation, Indore,<br />
Shri Hari Ranjan Rao, <strong>Project</strong> Director, MP Urban (ADB) <strong>Project</strong>, Commissioners<br />
from Municipal Corporation, Bhopal/Indore/Jabalpur and other Senior Govt.<br />
Officials from <strong>Project</strong> Management and <strong>Project</strong> Implementation Units.<br />
<br />
<br />
<br />
<br />
<br />
<br />
<br />
<br />
<br />
<br />
<br />
Year : 1, Issue: 7<br />
Month : Oct 06<br />
In this issue<br />
Review Meeting by<br />
Hon'ble Minister<br />
Empowered Committee<br />
Meeting<br />
Visit of ADB Mission<br />
ASCI Training,<br />
Hyderabad<br />
City Steering<br />
Committee Meeting,<br />
Gwalior<br />
Workshop on 'Open<br />
defecation free city'<br />
Technical Clearance<br />
Committee Meeting<br />
Site Visits of Public<br />
Relations Consultants<br />
TPRM Meeting, Kerala<br />
Your Questions<br />
<strong>Project</strong> progress: At a<br />
glance<br />
Editor:Shri Hari Ranjan Rao IAS<br />
Editorial Board: Shri A.K.Gupta, Dr.Manisha Telang, Smt. Meera Mathur, Graphics: Shri Deepak Jog<br />
For comments: Public Relations Consultants, MP Urban (ADB) <strong>Project</strong><br />
Beej Bhawan, Arera Hills, Bhopal - 462011<br />
Ph.:- 91 755-2763060/61/62/ Fax: 91 755 2763868 e mail : uwseimp@yahoo.com, prciirm@yahoo.co.in<br />
Website: http://www.mpurban.org/mpadb/default.asp<br />
Issued in Public Interest<br />
Designed & Printed by : Box Corugators and Offset Printers, Bhopal. Tel:0755-2587551, 2587651<br />
Hon'ble Shri Jayant Mallaiya, Minister UADD, in the review meeting
Empowered Committee Meeting:<br />
th<br />
Meeting of Empowered Committee was organized on 10 Oct. 2006 under the chairmanship of Chief<br />
Secretary. This meeting was attended by Shri Sumit Bose, Principal Secretary, Finance, GoMP, Shri Sewaram,<br />
Secretary, UADD, GoMP, Shri P.C. Meena, Secretary, PHED, GoMP,<br />
Shri Malay Shrivastava, Commissioner, UADD, GoMP, Shri Hari Ranjan Rao, <strong>Project</strong> Director, MP Urban (ADB)<br />
<strong>Project</strong>. After detailed deliberations the following decisions were taken in the meeting:<br />
<br />
The committee directed to achieve the targets by March 2007, by putting special efforts;<br />
<br />
To expedite the implementation schedule, bids shall first be cleared by MIC before obtaining<br />
concurrence of ADB and clearance from TE & AC and / or EC;<br />
<br />
The committee approved the bid for design and construction of 7RCC overhead reservoirs for<br />
water supply at Indore and construction of 132/33 KV sub stations and transmission line of<br />
water supply Indore;<br />
<br />
The committee approved the bid for rehabilitation of existing water treatment plant and pumping<br />
station at Gwalior.<br />
Visit of ADB Mission:<br />
ADB Mission comprising of Shri Tadashi Kondo, Country Director, Shri Narhari Rao, Principal Economist,<br />
Shri. Shamit Chakravarti, Program Officer, Shri Anil Motwani, <strong>Project</strong> Implementation Officer (Transport),<br />
Shri Vallabh Karbar Rao, Energy Specialist and Shri Ashok Shrivastava, <strong>Project</strong> Implementation Officer (Urban<br />
th<br />
th<br />
Development) visited Bhopal to review on-going as well as pipe line projects from 11 -12 Oct. 2006. The mission<br />
objectives were to review the implementation progress, e-procurement system, FIAP status and status of clearances<br />
required from various agencies. The mission discussed the technicalities of the project at length with the <strong>Project</strong><br />
Director and other staff members of PMU & PMC. Mission desired expedient award of the packages and<br />
disbursement.<br />
ASCI Training, Hyderabad:<br />
4 batch of training programme for officers and public<br />
th<br />
4 batch of training programme for officers and public<br />
th<br />
th<br />
representatives was organized from 9 -13 Oct. 2006 at<br />
Administrative Staff College of India (ASCI), Hyderabad<br />
under Water for Asian Cities Programme supported by<br />
UN-HABITAT. This training programme was attended by<br />
22 Corporators and other Senior Officials from project<br />
cities.<br />
The objective of the training programme is to get<br />
participants acquainted to best practices related to<br />
policies, legal, technical, behavioral, financial and social<br />
aspects of infrastructure development to ensure<br />
effective service delivery for water supply and sanitation<br />
programme.<br />
City Steering Committee Meeting, Gwalior:<br />
Participants in ASCI Training, Hyderabad<br />
th<br />
City Steering Committee meeting in Gwalior was organized on 18 Oct. 2006 under the chairmanship of<br />
Shri Komal Singh, Divisional Commissioner, Gwalior. This meeting was attended by Hon'ble Mayor<br />
Shri Vivek Narayan Shejwalkar, District Collector, Gwalior, Shri Hari Ranjan Rao, <strong>Project</strong> Director, Shri B.M. Sharma,<br />
Commissioner Municipal Corporation, Gwalior, Members of Mayor-in-Council and other officials. Shri Komal Singh,<br />
Divisional Commissioner, Gwalior suggested to procure all water meters at one time and also prepare time bound<br />
strategy for its installation. It was also suggested, to do the detail engineering survey so that, all technical problems<br />
are handled scientifically.<br />
Shri Hari Ranjan Rao, <strong>Project</strong> Director suggested to obtain No Objection Certificate for land acquisition from the<br />
concerned department so that, the implementation of proposed works can be started immediately after getting their<br />
sanctions.<br />
Workshop on Open Defecation Free City:<br />
Realizing the need for a practical urban environmental sanitation approach that recognizes the challenges<br />
inherent in achieving to move towards sanitary disposal of human excreta and the given scenario of urbanization<br />
where the services related to basic amenities have been deteriorating, a brain storming session was held on<br />
th<br />
19 Oct. 2006. The Officials of MP Urban (ADB) <strong>Project</strong>, the <strong>Project</strong> Management Consultants, Design and<br />
Supervision Consultant, UN-HABITAT, Water Aid, NGO partners and Nagar Nigam representatives participated<br />
in the discussion. Choices and options for the following categories were discussed:<br />
<br />
Access to Sewer System Network <br />
Access to Septic Tank<br />
<br />
Access to community toilet <br />
Defecating in open<br />
The discussion culminated to the genesis of consensus over the following options:<br />
<br />
Selection of technology is subject to availability of space;<br />
<br />
Financial management would be according to identified techniques;<br />
<br />
Behaviour change is possible only through Information, Education and Communication (IEC)<br />
strategies.<br />
Technical Clearance Committee Meeting:<br />
th<br />
th<br />
Technical Clearance Committee meetings were organized on 7 & 27 Oct. 2006 under the chairmanship of<br />
Shri Hari Ranjan Rao, <strong>Project</strong> Director. This meeting was attended by Shri R.S. Nema, Chief Engineer, PHED,<br />
Shri M.A. Khan, Dy. <strong>Project</strong> Director (Technical), Shri S.K. Gupta, Joint Director, Institutional Finance, GoMP and<br />
<strong>Project</strong> Managers from Indore, Jabalpur, Gwalior and Bhopal. In these meetings technical clearance was given to<br />
the following projects: Construction of RCC overhead service reservoir and ground service reservoir, additional<br />
works for 25 MLD capacity STP at Maholi Damkheda, sanitary sewers in Zone-I, including Allied works in Bhopal;<br />
6450 m long clear water pumping main with allied works for rehabilitation of existing pumping main from water<br />
treatment plant at Motijheel to Jayendraganj Tank; RCC overhead and ground service reservoir, storm water<br />
drainage system for Gadhaipura supply, multi Jet type and Woltmann type water meters for domestic / nondomestic<br />
consumers at Gwalior; clear water rising main and feeder mains, maintenance of mechanical multi Jet<br />
type water meters for all commercial consumers and above 20 mm size for domestic consumers, storm water<br />
drainage for Adhartal and Cherital area, Trunk sewer and outfall sewer for the core areas, 120 MLD capacity<br />
water treatment plant with clear water pumping station and 33 KV sub-station at Jabalpur.<br />
Site Visits of Public Relations<br />
Consultants:<br />
Public Relations Consultants visited all four project<br />
cities viz.: Bhopal, Gwalior, Jabalpur and Indore in the<br />
month of Oct. 2006 to get acquainted with actual status<br />
of water supply, sewerage and solid waste.<br />
Consultants had also discussed in detail about actual<br />
status of solid waste disposal with officials from <strong>Project</strong><br />
Implementation Unit (PIU), Community Development<br />
Experts and Team Leaders of Design and Supervision<br />
Consultants (DSC). Hon'ble Mayor Smt. Sushila<br />
Singh, Jabalpur, Public Representatives and officials<br />
from Municipal Corporations suggested PRC to<br />
develop effective strategy for IEC activities.<br />
Tripartite Portfolio Review Meeting (TPRM), Kerala:<br />
PRC team in meeting with<br />
Smt. Susheela Singh, Hon'ble Mayor, Jabalpur<br />
TPRM was organized on 30-31 Oct. 2006 in Kovalam, Kerala. This meeting was attended by representatives<br />
from Govt. of India, Govt. of M.P. and Asian Development Bank (ADB). The following issues were discussed in<br />
this meeting:<br />
<br />
Physical and Financial progress of targets of ADB funded projects;<br />
<br />
Status of contract award for different packages;<br />
<br />
Compliance of major Loan covenants;<br />
Government of India desired that targets for award and disbursement, fixed by the state must be achieved<br />
under all circumstances within the stipulated timeframe.