THE ESTIMATED COST OF FUTURE DEVELOPMENTS<br />
Project mil € year<br />
Paldiski – Kiili pipeline<br />
DN700 PN55, 47 km<br />
28 2014-2016<br />
Gas Metering Station (Paldiski) 3<br />
2015-2016<br />
Loo GRS rek. (55/38) 4<br />
2015-2016<br />
Balticconnector, 80 km 100 ?<br />
Compressor station (Paldiski) 22 ?<br />
Karksi GMS (reverse metering) 5 ?<br />
Tallinn-Kohtla-Järve-Narva pipeline<br />
(200 km) and 10 GRS<br />
Sum: 317<br />
EU grants … % ?<br />
155 2015-2022