TALLINN – KOHTLA-JÄRVE – NARVA<br />
Reconstruction of the Tallinn – Kohtla-Järve –<br />
Narva transmission pipelines (old pipe 38 bar<br />
change to new pipe 55 bar) and 10 GRS.<br />
Russia is going to do the same - replace the pipe<br />
from Narva to St Petersburg.<br />
Opening the direct connection between Estonia and<br />
Russia from St. Petersburg side and that would<br />
enable us to comply with the N-1 criterion of gas<br />
network.<br />
Estimated construction period in 2015-2022.