<strong>ESTLINK</strong> 1 & 2<br />

Raine Pajo<br />

Technical director<br />

October 5


Synchronous areas in Europe<br />

Capacity: : 90 GW<br />

Peak load: : 60 GW<br />

Consumption: : 400 TWh<br />

Population: : 20 mln<br />

Capapcity: 85 GW<br />

Peak load: 60 GW<br />

Consumption: 400 TWh<br />

Population: 65 mln<br />

NORDEL<br />

Capacity: 310 GW<br />

Peak load:180<br />

GW<br />

Consumption: : 1200 TWh<br />

Population: : 280 mln<br />

ATSOI<br />

Capacity: 610GW<br />

Peak load: 390 GW<br />

Consumption: 2500 TWh<br />

Population: 450 mln<br />

UKTSOA<br />

UCTE<br />

UPS/IPS<br />

HVDC cable<br />

HVDC B2B<br />

HVAC tie line


HARKU<br />

<strong>ESTLINK</strong> 1 VSC-tehnology<br />

ESPOO<br />

" - "<br />

" + "


<strong>ESTLINK</strong> 1 two project phases<br />

Decision<br />

Cable ready<br />

Sales of ownership to national<br />

grid companies<br />

2004 2005 2006 2007 2008 2009<br />

2010<br />

Commercial project 2006-2009<br />

(2013)<br />

• Investors are traders; Exemption valid<br />

Infrastructure project earliest 2010<br />

(latest 2013)<br />

• Investors are national grid companies<br />

• Project based investment, revenues from<br />

special fee paid by Estlink users<br />

• Part of domestic regulated asset base, i.e,<br />

included in the domestic grid tariffs<br />

• Owners have privileged rights for capacity;<br />

use-it-or-lose-it<br />

• Open access for all market participants


• Shareholders of NEL own all capacity in both directions<br />

• NEL will organize the following auctions:<br />

• Year Auction<br />

• Month Auction<br />

• Day Auction<br />

• Free Capacity Auction<br />

<strong>ESTLINK</strong> 1 auctions<br />

• Shareholders of NEL can sell their capacity at year, month and day<br />

auctions<br />

• All unused capacity for next day will be sold to third parties at free<br />

capacity auction<br />

• Every day there will be offered around 700 MW of free capacity for next<br />

day


<strong>ESTLINK</strong> 1 operation<br />

Estlink Usage [MW]<br />

400<br />

300<br />

200<br />

100<br />

0<br />

-100<br />

-200<br />

-300<br />

-400<br />

EST-FIN<br />

FIN-EST<br />

4.01.2007<br />

3.02.2007<br />

5.03.2007<br />

4.04.2007<br />

4.05.2007<br />

3.06.2007<br />

3.07.2007<br />

2.08.2007<br />

1.09.2007<br />

1.10.2007<br />

• Estlink has been in operation since January 4, 2007;<br />

• Estlink has been used in both directions, but mainly in direction from Estonia to Finland;<br />

• Average capacity usage during first 9 month has been 67,5%.


Good correlation with prices at NordPool<br />

Estlink usage during week 39<br />

NordPool average price<br />

Estlink usage<br />

35<br />

30<br />

25<br />

20<br />

15<br />

10<br />

5<br />

0<br />

09.24.07<br />

09.24.07<br />

09.25.07<br />

09.26.07<br />

09.27.07<br />

09.28.07<br />

09.29.07<br />

09.29.07<br />

09.30.07<br />

NordPool Spot average price<br />

[€/MWh]<br />

300<br />

250<br />

200<br />

150<br />

100<br />

50<br />

0<br />

-50<br />

-100<br />

-150<br />

Estlink Usage [MW]


<strong>ESTLINK</strong> 1 system services and operation<br />

• <strong>ESTLINK</strong> 1 is operated by Estonian and Finnish TSO – good cooperation<br />

• <strong>ESTLINK</strong> 1 has been sucessful used also for the frequency regulation &<br />

POD in Finland<br />

• <strong>ESTLINK</strong> 1 has been tested for black-start in Estonia<br />

• Maximum capacities at Harku:<br />

- From Estonia to Finaland 383 MW (02.02)<br />

- from Finland to Estonia 281 MW (27.05)<br />

• Energy transmitted through Harku 8 months:<br />

- From Estonia to Finland 1130 GWh<br />

- From Finland to Estonia 18 GWh


<strong>ESTLINK</strong> 2


•NO INTERCONNECTORS = NO COMPETITION<br />

⇒ HIGHER PRICES<br />

The strategic goal of the Baltics<br />

•The main goal is to integrate the Baltic power<br />

system to the Scandinavian and West-European<br />

power systems<br />

•The development of electricity markets in the Baltic<br />

Sea region<br />

• Improve security of supply<br />

•The Baltics should have about similar transmission<br />

capacity towards East and West


Three strategic connections of Baltics<br />

2012-2018<br />

635 MW<br />

365 MW<br />

3000 MW<br />

700 MW<br />

700 MW<br />

3000 MW<br />

1000 MW


Strategic connections in Baltics and Nordel<br />

2012-2018<br />

200-750 MW<br />

800 MW<br />

600 MW<br />

400-600 MW<br />

700 MW<br />

600 MW<br />

800-1000 MW<br />

300 MW<br />

600 MW<br />

1000 MW


Estlink 2 Estonia-Finland HVDC<br />

• Capacity 600 MW<br />

• Losses ca. 1,5 - 2%<br />

• Energy availability: 98%<br />

• Life-time 40 a.<br />

• Cost: ca 200 MEUR;<br />

• Estonian TSO : 100 MEUR (50%);<br />

• Finnis TSO: 100 MEUR (50%);<br />

• <strong>ESTLINK</strong> 2 influence to household ca 1,5 s/kWh (Estonian)<br />

• Time schedule:<br />

• start: 2006 a.<br />

• Cooperation with Fingrid: 2007 detsember<br />

• Commissioning 2012-2013


Fenno-Skan 1<br />

<strong>ESTLINK</strong> 2 tehnology<br />

A<br />

C<br />

B<br />

NorNed<br />

Fenno-Skan 2


<strong>ESTLINK</strong> 2 tehnology


Synchronous operation with<br />

UCTE


Conclusion<br />

6 criterias for new connections<br />

• Production optimisation and energy exchange<br />

• consumer and producer benefits + congestion rents<br />

• Reduced risk of power shortage<br />

• Changes in losses<br />

• Lower risk of energy shortage<br />

• Trade in regulating power and ancillary services<br />

(POD)<br />

• The value of a better-functioning market


Vision of 1 PWh Baltic Sea market<br />

9<br />

TWh<br />

390<br />

TWh<br />

NW Russia<br />

150 TWh<br />

IE<br />

420<br />

TWh<br />

UK<br />

Baltics<br />

25 TWh<br />

Russia<br />

780 TWh<br />

510<br />

TWh<br />

Centrel<br />

260 TWh<br />

480<br />

TWh<br />

UCTE<br />

Iberia<br />

280 TWh<br />

320<br />

TWh


Thank You!