Legacy Project<br />

Project Progress<br />

• The first infrastructure measures in the areas of<br />

water supply, electricity and road construction, as<br />

well as the first drilling activities, were undertaken<br />

in 2011.<br />

• About 120 employees from different countries are<br />

currently working at <strong>K+S</strong> Potash Canada GP on the<br />

construction of the new site. By 2023, more than<br />

300 jobs should be created.<br />

• In 2012, we anticipate an investment volume of<br />

CAD 200 million (about € 160 million), which will<br />

continue to be used for infrastructure measures<br />

and water supply, as well as engineering work and<br />

drilling.<br />

• In 2013, the investment level should reach<br />

CAD 830 million* (a good € 640 million) and be<br />

used for drilling and the start of the factory’s<br />

construction.<br />

* There may still be considerable shifts in the allocation of expenditure to the investment periods<br />