Planning Commission<br />
File No.: USE2012 0001<br />
February 9,2012<br />
Page 4 <strong>of</strong> 11<br />
ANALYSIS<br />
Staff solicited comments from Community Development Building Department, CBJ Streets, CBJ<br />
General Engineering, CBJ Assessor's Office, Fire Department, CBJ L<strong>and</strong>s <strong>and</strong> Resources, Alaska<br />
Department <strong>of</strong>Transportation, CBJ Parks <strong>and</strong> Recreation, <strong>and</strong> CBJ Public Works.<br />
Comments Received:<br />
Charlie Ford, Building Codes Official, CBJ Building Department<br />
The Building Department has no issues with the modifications.<br />
Brent Fischer, Director, CBJ Parks <strong>and</strong> Recreation<br />
Parks <strong>and</strong> Recreation has no concerns with this project.<br />
Dan Jager, Fire Marshall, Fire Department<br />
The only concern on fire code <strong>and</strong> requirements is the driving surface or "drivescape"<br />
being able to withst<strong>and</strong> the weight <strong>of</strong>at least a 75,000 poundfire truck. Ifthat can be<br />
guaranteed <strong>and</strong>that the surface will holda rig that size without it sinking into the ground,<br />
then this is ok as far as fire review goes.<br />
The applicant provided additional information on January 25, 2012 (See Attachment 6). The<br />
additional information explained that the fire lane will be constructed to accommodate a 75,000<br />
pound fire truck <strong>and</strong> the fire lane will be maintained all year to include snow plowing in the winter.<br />
Ron King, Chief Regulatory Surveyor, CBJ General Engineering<br />
Final design may require stormwater run<strong>of</strong>fcalculations <strong>and</strong> tweaking <strong>of</strong>the site plan. In<br />
addition, they will need to specifY maintenance with schedule <strong>of</strong>the Best Management<br />
Practices (BMPs). This will be clarifiedduring buildingpermit review but we shouldgive<br />
a heads-up to the designer.<br />
will address these<br />
David Epstein, Pr<strong>of</strong>essional Engineer, Alaska Department <strong>of</strong> Transportation Southeast Region,<br />
provided staffwith correspondence that DOT/PF sent on February 3,2012, (See Attachment 5) in<br />
response to a letter addressed to DOT/PF on January 25, 2012 (See Attachment 4).<br />
Based on the letters between the Church <strong>of</strong>Jesus Christ<br />
<strong>of</strong> Transportation & Public Facilities it appears that a final layout <strong>of</strong>the access to the site has not