Const./Ops<br />
Red Flags/<br />
Northern<br />
Edge<br />
Major<br />
Construction<br />
<strong>Elmendorf</strong><br />
Proposed Construction Timeline<br />
<strong>Apr</strong><br />
<strong>13</strong><br />
May <strong>13</strong> Jun <strong>13</strong> Jul <strong>13</strong> Aug <strong>13</strong> Sep <strong>13</strong><br />
RWY34<br />
Closed<br />
20 - 31<br />
May<br />
TWY Papa<br />
29 <strong>Apr</strong> - 7 Jun<br />
Tie Down Install<br />
(C<strong>13</strong>0/C17 Ramp)<br />
<strong>13</strong> May – 30 Jun<br />
East Ramp<br />
Re-Design<br />
28 May – 2<br />
Jun<br />
(Unfunded)<br />
Northern<br />
Edge<br />
<strong>13</strong>-30 Jun<br />
RWY06 Full-Length<br />
Closed<br />
1 Jul – 24 Jul<br />
RWY 24 Relocated<br />
Threshold<br />
25 Jul – 15 Aug<br />
I n t e g r i t y - S e r v i c e - E x c e l l e n c e<br />
Red Flag <strong>13</strong>-3<br />
8-25 Aug<br />
TWY N<br />
15 Aug – 30 Sep<br />
West Ramp Hot Pit Construction<br />
1 Jul – 31 Oct <strong>13</strong><br />
NOTES:<br />
- Depicted exercise dates include aircraft arrival and departure windows<br />
- Completing Twy P , Twy N and runway construction simultaneously will lower project costs and<br />
consolidate impact from runway/taxiway closures<br />
- Runway 24 threshold will be temporarily relocated by 1,000’ (first 1,000’ will be closed) from 25<br />
July to 15 August, providing 9,000’ of usable runway surface