Update on major industrial projects<br />
Roll-out<br />
Q1 2010<br />
Q2 2010<br />
Q3 2010<br />
India<br />
Yerraguntla<br />
Italy<br />
Matera<br />
New Line<br />
2.3 mt/y<br />
cement equivalent<br />
capacity<br />
Kiln Revamping<br />
0.9 mt/y (+0.2 mt/y)<br />
cement capacity<br />
clinker production started in Q1<br />
grinding line ready in Q2<br />
kiln fire-up in Q1 (in advance vs.<br />
prior forecast)<br />
2.5 mt/y additional<br />
capacity available<br />
in Q2<br />
Morocco<br />
Ait Baha<br />
New Line<br />
2.2 mt/y<br />
cement capacity<br />
31% capacity increase in the<br />
country<br />
19 % variable costs reduction vs.<br />
old Agadir plant<br />
1.1 mt/y additional<br />
capacity available<br />
in Q3<br />
Roll-out<br />
… … H2 2012<br />
Bulgaria<br />
Devnya<br />
New Line<br />
2.7 mt/y<br />
cement capacity<br />
~20 % cement capacity increase<br />
Stepping stone to increase Eastern<br />
Europe exposure through a<br />
network of grinding centres<br />
Kiln fire-up<br />
not before H2 2012<br />
<strong>Italcementi</strong> <strong>Group</strong> Mediobanca – Copenhagen Roadshow, 16 June 2010<br />
27