Ward Improvement Plan:<br />

<strong>Finsbury</strong> <strong>Park</strong><br />

Scheme location and details Description of scheme Why Investment is needed<br />

Andover Estate - environmental<br />

<strong>improvement</strong>s<br />

Category:<br />

Sub-category:<br />

Priority:<br />

Approx cost:<br />

1 - High<br />

£280,000<br />

Funds secured: £144,281<br />

Estate <strong>improvement</strong>s<br />

Estate security / permeability<br />

To carry out a range of landscape, conservation and<br />

environmental <strong>improvement</strong>s to the entire estate<br />

following years of neglect, through continued<br />

regeneration of housing stock and other associated<br />

building/construction works.<br />

Develop a master <strong>plan</strong> for improving green spaces<br />

throughout the estate, focusing on improving verges,<br />

rationalising hedge <strong>plan</strong>ting, tree pits and areas at the<br />

perimeter of the estate. This element of the proposal<br />

does not include <strong>improvement</strong>s to large open green<br />

space or the creation of any new amenity, play or<br />

community gardening spaces.<br />

Money is also needed for a redundant kickabout area<br />

and the conversion of Sue Davies football pitch to a<br />

community garden.<br />

10 new PTZ cameras would be provided on the main<br />

thoroughfares on the entire estate (cost £140k),<br />

lighting would be provided and underground garages<br />

at old Andover would be refurbished.<br />

S106 allocated from 67-83 Seven Sisters Rd<br />

(£184,281.30, 07/2012) to<strong>ward</strong>s improved pedestrian<br />

permeability, security/CCTV and play space on the<br />

Andover Estate (including Corker Walk and Sue<br />

Davies Pitch). £40k of this covers the Andover<br />

Security Lighting Project, a separate WIP scheme.<br />

The estate has undergone large scale<br />

refurbishment over the past few years. LBI<br />

Housing is working with Groundwork to develop a<br />

proposal to further enhance the estate’s external<br />

spaces, specifically to rationalise and enhance<br />

<strong>plan</strong>ting estate wide, carry out community safety<br />

<strong>improvement</strong>s, explore opportunities for community<br />

gardening and to improve the Sue Davies football<br />

pitch. Our proposal with Groundwork is part of a<br />

bigger urban design scheme, focusing on <strong>plan</strong>ting<br />

with the creation of conservation areas and largely<br />

to assist with designing out crime.<br />

Once final designs and project costs have been<br />

developed, Groundwork’s experienced fundraiser<br />

will be able to support research and work with the<br />

TRA to apply for extra funding in order to<br />

implement the changes. This fundraising work is<br />

free of charge on the basis that Groundwork is<br />

commissioned to project manage the works if any<br />

funding is secured by Groundwork. Groundwork’s<br />

current quotation for managing through to delivery<br />

of the scheme is £20k, with LBI Housing and the<br />

TRA requiring a further £80k to use across the<br />

Andover Estate on landscaping schemes.<br />

Additional visible CCTV units would also be<br />

provided to act as a possible deterrent for criminal<br />

acts and increase the overall security of the estate.<br />

Additional lighting would help support the new<br />

cameras.<br />

24 June 2013 Page 76


Andover Estate - security / lighting project<br />

Category: Estate <strong>improvement</strong>s<br />

Sub-category: Estate security / permeability<br />

Priority: 1 - High<br />

Approx cost: £60,000<br />

Funds secured: £40,000<br />

TRA led initiative to improve existing and install<br />

additional lighting on the estate to support the new<br />

CCTV cameras being installed there. The majority of<br />

the scheme will be to light the areas not currently<br />

covered by existing lighting.<br />

S106 allocated from 67-83 Seven Sisters Rd. (£40k,<br />

07/2012) as part of a larger allocation to Andover<br />

Estate.<br />

Investigation ongoing to determine full cost of scheme.<br />

It is required by the TRA and residents of the<br />

estate to help in the prevention of crime and to<br />

safeguard the residents of the estate. It also acts<br />

to give the residents confidence that the estate is a<br />

safe environment.<br />

<strong>Finsbury</strong> <strong>Park</strong> Community Hub H&S and<br />

Refurbishment<br />

Category:<br />

Sub-category:<br />

Priority:<br />

Approx cost:<br />

Community facilities<br />

1 - High<br />

£150,000<br />

Funds secured: £58,140<br />

Community space<br />

A long overdue refurbishment and repairs programme<br />

of the<br />

Community Hub. To perform H&S adaptations and<br />

implement modifications to the main hall, increase<br />

security and decorate the building.<br />

S106 allocated to<strong>ward</strong>s physical <strong>improvement</strong>s to the<br />

<strong>Finsbury</strong> <strong>Park</strong> Community Hub from 189-219 Isledon<br />

Rd (£58,140k, 01/2013)<br />

to address some pressing H&S issues and to<br />

continue offering an appropriate and safe space for<br />

social, recreational, learning, training &<br />

development activities.<br />

<strong>Finsbury</strong> <strong>Park</strong> Community Hub, Holloway<br />

Neighbourhood Group, Manor<br />

Gardens Welfare Trust<br />

Category:<br />

Sub-category:<br />

Priority:<br />

Approx cost:<br />

Funds secured: £0<br />

Community facilities<br />

Community support funding<br />

1 - High<br />

£35,000<br />

The out<strong>ward</strong> image of the three bidding organisations<br />

does not reflect the breadth of services offered nor<br />

adequately show their impact in the community. The<br />

three organizations need to develop a PR and<br />

Communications Strategy to properly position them<br />

and increase success of fundraising activities.<br />

A professionally managed communications<br />

strategy increases the chances of attracting<br />

funding in an increasingly competitive environment.<br />

It is in the interest of the WP and LBI that the<br />

largest members of the <strong>ward</strong> partnership succeed<br />

in their efforts to attract funding, thus releasing the<br />

pressure for funding and allowing more funds to<br />

flow to smaller organisations.<br />

24 June 2013 Page 77


<strong>Finsbury</strong> <strong>Park</strong> Creative Hub<br />

Category: Community facilities<br />

Sub-category: Arts<br />

Priority: 1 - High<br />

Approx cost: £152,900<br />

Funds secured: £60,000<br />

This three year project will bring together a broad<br />

range of partners to deliver a comprehensive<br />

programme of community arts engagement activities,<br />

public art and training opportunities.<br />

The project is seeking S106 funding and will also lever<br />

an additional £60,000 from Arts <strong>Council</strong> England to<br />

support the development of a coherent programme of<br />

works as part of a broader place making initiative.<br />

This is a strategic project that the arts service will be<br />

leading and co-ordinating on behalf of the project<br />

partners.<br />

Creating opportunities to engage the wider public<br />

in the arts; providing training opportunities;<br />

contributing to wider place making initiative through<br />

public art;<br />

Holloway Neighbourhood Group -<br />

Community Development Programme<br />

Category:<br />

Sub-category:<br />

Priority:<br />

Approx cost:<br />

Funds secured: £0<br />

Community facilities<br />

Community support funding<br />

1 - High<br />

£85,000<br />

A sustained programme of community development<br />

work which will encourage and support neighbourhood<br />

action and reach out to more people in need through<br />

the following projects:<br />

*Supported Volunteering Opportunities for people with<br />

mental health issues<br />

*Timebank Holloway<br />

*Meet my Street - a project to encourage neighbourly<br />

support for isolated or vulnerable people<br />

*Healthy Holloway - stress management in the<br />

workplace to support local small and medium sized<br />

businesses to build healthy workforces<br />

The Fairness Commission and the <strong>Council</strong>'s<br />

corporate strategy both point to the importance of<br />

reducing health inequalities and of building strong<br />

communities where people can engage in civic life<br />

and contribute through giving time to support local<br />

action.<br />

Investment will provide pump priming funding to<br />

kick start these initiatives to increase opportunities<br />

for people to improve their neighbourhoods and<br />

improve their health. Investment will also help<br />

attract longer-term charitable support.<br />

24 June 2013 Page 78


Manor Gardens Centre<br />

Category: Community facilities<br />

Sub-category: Community space<br />

Priority: 1 - High<br />

Approx cost: £137,400<br />

Funds secured: £30,000<br />

Painting of external parts of buildings, including<br />

windows, railings and metal fire escape (£42k);<br />

Repairs of loose tiles on roof of central buildings<br />

(£1.4k); Re-surfacing of car park (£18,000); New roof<br />

and decoration of covered space at back of House no.<br />

6, used as entrance by Age UK <strong>Islington</strong> (£6k);<br />

Refurbishment of small kitchen areas in House no.7<br />

and 8 (£12k); Refurbishment of toilets - 3 in central<br />

buildings, 1 in House no.6, 2 in House no.7, 1 in<br />

House no.8 and 1 in House no.9 (£36k); Painting and<br />

re-carpeting of halls and stairways in Houses no.6, 7,<br />

8 and 9 (£18k); New doors in Community Café (£3k);<br />

New door to Dame Geraldine Hall (£1k)<br />

s106 allocated from 556-564 Holloway Rd (£30k,<br />

07/2012)<br />

The Manor Gardens Centre provides a range of<br />

high quality accessible services to meet the<br />

changing requirements for health and well-being of<br />

people in <strong>Islington</strong> from the buildings comprising 6-<br />

9 Manor Gardens. These services take the form of<br />

projects directly managed by the Manor Gardens<br />

Welfare Trust and the provision of serviced office<br />

and meeting space for partners in the local<br />

community sharing our vision.<br />

Mayton Street Festival community event<br />

Category: Community facilities<br />

Sub-category: Community support funding<br />

Priority: 1 - High<br />

Approx cost: £4,000<br />

Funds secured: £0<br />

Following the successful revival of the Mayton Street<br />

Festival last year (with 850 attendees) we want to put<br />

on an even better event this year. The street festival<br />

will contribute to better community involvement and<br />

renewed pride in the local area. Using the Old Fire<br />

Station as the base for the festival means that we can<br />

draw on the building’s long history in the area of<br />

tackling poverty and contributing to the economic and<br />

social vibrancy of the area.<br />

In a recent <strong>ward</strong> consultation event held at the Old<br />

Fire Station, participants said that their top priority<br />

was strengthening the sense of community.<br />

Holding a festival in the street is a very direct way<br />

of engaging directly with local people and can help<br />

generate pride and boost interest in an area. The<br />

event will be free, and with mass publicity we<br />

expect local residents to turn out in force.<br />

24 June 2013 Page 79


Old Fire Station, Mayton Street<br />

Category: Community facilities<br />

Sub-category: Community space<br />

Priority: 1 - High<br />

Approx cost: £92,352<br />

Funds secured: £49,645<br />

A programme of refurbishment to transform local<br />

community facilities at the Old Fire Station, home of<br />

the Holloway Neighbourhood Group. Work includes:<br />

painting and decorating of communal areas and<br />

general <strong>improvement</strong>s to the main hall and reception<br />

signage (£54,425); repairs to toilets and <strong>improvement</strong>s<br />

to disabled access bathrooms (£4,187); replacing two<br />

boilers (£12,740); refit of our WebRoom (£6,000);<br />

renovation of the Garden Room and improving access<br />

to our outside space (£15,000).<br />

106 allocated from 3-5 Thane Villas (£49,645,<br />

07/2012) to<strong>ward</strong>s <strong>improvement</strong>s<br />

To make significant and much needed<br />

<strong>improvement</strong>s to the Old Fire Station to enhance<br />

local people's experience of the centre, to improve<br />

facilities for smaller groups and to enable us to<br />

generate increased revenue from venue hire. HNG<br />

has never been able to imagine a full-scale<br />

refurbishment programme before and we see this<br />

as a key opportunity to really improve and<br />

strengthen a vital community asset<br />

Andover Bright Start Creche<br />

Category: Community facilities<br />

Sub-category: Community support funding<br />

Priority: 2 - Medium<br />

Approx cost: £80,000<br />

Funds secured: £0<br />

To continue offering the Under Fives Childcare<br />

provision at the Hub.<br />

<strong>Finsbury</strong> <strong>Park</strong> Ward has the second highest child<br />

poverty index in the country. The crèche is a<br />

fundamental service to the community. Places for<br />

young children are in short supply in the <strong>ward</strong> as a<br />

result of the increase in population, -and is<br />

expected to grow even further in the immediate<br />

future when the new homes on Six Acres come on<br />

stream.<br />

Current funding runs out in April 2012 and if no<br />

funding streams are secured by then, the service<br />

will have to be shut down. Funding is requested to<br />

fund the creche for two years<br />

24 June 2013 Page 80


Andover Community Communication<br />

Enhancement Project<br />

Category:<br />

Sub-category:<br />

Priority:<br />

Approx cost:<br />

Funds secured: £0<br />

Estate <strong>improvement</strong>s<br />

Estate security / permeability<br />

2 - Medium<br />

£34,000<br />

To purchase and install badly needed notice boards<br />

for the estate, lighted bollards to forge path through<br />

landscaped area at Corker Walk and the<br />

creation/installation of estate based maps for visitors<br />

and emergency services to use when entering the<br />

estate.<br />

One of the main criticisms of the Andover for our<br />

Emergency Services is the lack of road<br />

signs/estate maps to guide them to specific<br />

locations. This investment would eradicate this<br />

problem.<br />

Additional lighted bollards along the path way at<br />

Corker Walk would help define this walkway as a<br />

natural path leading from the estate to Seven<br />

Sisters Road. It also aids to help light up this area<br />

which currently has no lights and is used heavily at<br />

night by pedestrian traffic. This scheme is also<br />

heavily supported by the TRA.<br />

Andover Estate - road resurfacing<br />

Category: Transport and streetscape<br />

Sub-category: Highway maintenance<br />

Priority: 2 - Medium<br />

Approx cost: £60,000<br />

Funds secured: £0<br />

To resurface entire stretch of Old Andover Road.<br />

One of the main arteries through the estate and<br />

onto Hornsey Road end of the estate is via Old<br />

Andover Road. The blocks within this area are<br />

soon to have Decent Homes works commencing<br />

there and would only be complemented by the<br />

resurfacing of what amounts to a very poor road.<br />

The current state of the Old Andover Road exerts a<br />

sense of neglect and timely deterioration, coupled<br />

with the effects of years of continued construction<br />

use. We are therefore asking for and additional<br />

£60k for the resurfacing of this complete road way.<br />

24 June 2013 Page 81


Andover Estate - youth and community trust<br />

Category: Community facilities<br />

Sub-category: Community space<br />

Priority: 2 - Medium<br />

Approx cost: £29,195<br />

Funds secured: £0<br />

Andover Youth & Community Trust New Kitchen<br />

(£7,000)<br />

Andover Youth & Community Trust Technology<br />

upgrade. We would like to upgrade our current 10<br />

Laptops within the multimedia suite with more up to<br />

date Apple Mac Pros (£16,000, LOW priority)<br />

Andover Youth & Community Trust Redecoration<br />

Scheme. The centre has not been decorated inside or<br />

outside since 2007 and the outside need’s brightening<br />

up to improve the look of the front of the building<br />

(£3,500, LOW priority)<br />

Andover Youth & Community Trust New Shutters<br />

Scheme (£2,695)<br />

The current kitchen has been in situ since 1994<br />

and we would like to renew the kitchen. We would<br />

like to improve our kitchen so that it meets any<br />

health & safety requirements and that it is up to<br />

date with today’s standards.<br />

We would like to enable young people & Adults to<br />

get a chance to use the most up to date technology<br />

available and to improve our very slow Toshiba<br />

Laptops. We would like to offer the same<br />

opportunities to our users as they are offered at<br />

HNG.<br />

To help us regenerate the building in aid of getting<br />

more of the community involved in our sessions &<br />

to make the building more inviting.<br />

This particular area has not been improved within<br />

the last 18yrs and requires investment to improve<br />

access to the building. The current grills on the<br />

front have been in place since 1994 , These are<br />

now very worn and have become very hard to open<br />

for Volunteers. We would like to get a small<br />

electronic shutter that covers the main front door<br />

area.<br />

B2B Somali Arts and Education<br />

Category: Community facilities<br />

Sub-category: Community support funding<br />

Priority: 2 - Medium<br />

Approx cost: £18,000<br />

Funds secured: £5,000<br />

This is a arts and Crafts Project base in Grafton<br />

Primary School. this project develops the Somali<br />

women and others, who attend the project skills to<br />

making saleable products, so the women can be<br />

encourage to develop further skills. Participants, are<br />

both Somali women and from diverse backgrounds<br />

and include mothers, single women and women whose<br />

children have grown up. They learn various skills:<br />

sewing, pattern cutting, printing and associated<br />

English language and numeracy skills.<br />

This investment is need to encourage women, to<br />

look in future employment such as the creative<br />

industry. Either to work as machines or as pattern<br />

cutters but also to work from home in future and<br />

take up commission's form so B2B can develop<br />

online sales, market stalls, for handmade products,<br />

as well a shop to sale products in the future.<br />

AlsoB2B has had advice and training from various<br />

agencies about developing our social enterprise,<br />

including Women’s Resourc, The funding to be<br />

finish by March July, But the project will carry on to<br />

develop further, marketing, on-line shop and as<br />

well marketing.<br />

24 June 2013 Page 82


Bennett Court Community Centre - external<br />

decoration<br />

Category:<br />

Sub-category:<br />

Priority:<br />

Approx cost:<br />

Funds secured: £0<br />

Estate <strong>improvement</strong>s<br />

Community space<br />

2 - Medium<br />

£25,000<br />

External decorations to building<br />

&<br />

Heating Renewal in centre<br />

Bennett Court CC is currently well utilised,<br />

particularly for asuccessful children’s nursery.<br />

However, it is in a poor state due to years of<br />

neglect to the external decoration. The decoration<br />

of the external fabric of the building would be<br />

relatively inexpensive but provide a better looking<br />

facility which could lead to increased usage.<br />

The current heating system in place is the original<br />

heating system and covers two main areas of the<br />

centre when a speratate system for each area is<br />

needed.<br />

FinFuture<br />

Category: Community facilities<br />

Sub-category: Community support funding<br />

Priority: 2 - Medium<br />

Approx cost: £50,000<br />

Funds secured: £0<br />

FinFuture is an independent registered charity with<br />

Development Trust status. All other FinFuture<br />

initiatives are based entirely on working in partnership<br />

with other organisations that have an interest in<br />

improving quality of life in our neighbourhood.<br />

FinFuture owns the FinSpace building and this is<br />

sustained by rental income from its tenants and from<br />

income generated by hiring out its meeting rooms.<br />

<strong>Finsbury</strong> <strong>Park</strong> Community Hub Development<br />

Category: Community facilities<br />

Sub-category: Community support funding<br />

Priority: 2 - Medium<br />

Approx cost: £49,000<br />

Funds secured: £0<br />

To employ an additional member of staff to work<br />

alongside the CEO; to develop the board of directors<br />

and staff to better fulfil the Hub’s objectives.<br />

FPCH is <strong>Finsbury</strong> <strong>Park</strong>'s main Community Hub and<br />

is a model for other hubs in the borough. It is<br />

essential to the success of its partners, including<br />

the FPWP, that FPCH has the tools, resources and<br />

skills to drive for<strong>ward</strong> <strong>Islington</strong>’s Core Strategy, the<br />

Fairness Commission's recommendations and to<br />

expand the provision of services<br />

agreed with LBI. This is a one off request for<br />

funding and will allow the CEO to concentrate on<br />

fundraising and the board and staff to support her<br />

in this activity<br />

24 June 2013 Page 83


<strong>Finsbury</strong> <strong>Park</strong> <strong>ward</strong> - Connecting <strong>Finsbury</strong><br />

<strong>Park</strong><br />

Category:<br />

Sub-category:<br />

Priority:<br />

Approx cost:<br />

Funds secured: £0<br />

Community facilities<br />

Community support funding<br />

2 - Medium<br />

£10,000<br />

A hyper local website would be developed with an<br />

attached volunteering and business development<br />

project. The website would would give news and<br />

information about the <strong>Finsbury</strong> <strong>Park</strong> area - it would<br />

concentrate on positive news but also give a space for<br />

people to suggest <strong>improvement</strong>s. It would allow all<br />

local groups, organisation and businesses to promote<br />

themselves and thier activiites . It would use the<br />

tempate developed for Holloway<br />

www.hollowayonline.net which will be live in Feb 2012.<br />

We need to pay for a staff member to under take<br />

the training up of volunteers who will collect<br />

information and take photos for one year. We<br />

need to pay a modest fee to the designer for the<br />

template.<br />

<strong>Finsbury</strong> <strong>Park</strong> <strong>ward</strong> tree <strong>plan</strong>ting<br />

Category: Transport and streetscape<br />

Sub-category: Trees<br />

Priority: 2 - Medium<br />

Approx cost: £85,000<br />

Funds secured: £0<br />

Street tree <strong>plan</strong>ting in this <strong>ward</strong> in line with the tree<br />

strategy - 169 street trees<br />

To increase the number of street trees in the area,<br />

improving the feel of the area, providing shade for<br />

pedestrians, and absorbing carbon emissions.<br />

Because there is no longer a dedicated annual<br />

budget for tree <strong>plan</strong>ting, funding such as s106 is<br />

required in order for new trees to be <strong>plan</strong>ted or<br />

replaced.<br />

<strong>Islington</strong> LinkUp, 48 Seven Sisters Road<br />

Category: Community facilities<br />

Sub-category: Community space<br />

Priority: 2 - Medium<br />

Approx cost: £14,000<br />

Funds secured: £0<br />

Flooring on the ground floor needs to be replaced due<br />

to wear and tear. First floor maintance and decorating<br />

to make rooms useable. Phone and electrical system<br />

needs to be updated. Kitchen equipment sort for<br />

users needs.<br />

Investment is needed so that <strong>Islington</strong> Link Up can<br />

deliver activities and services to users in a safe,<br />

friendly and professional environment.<br />

24 June 2013 Page 84


Rowan Arts Shop<br />

Category: Community facilities<br />

Sub-category: Arts<br />

Priority: 2 - Medium<br />

Approx cost: £35,000<br />

Funds secured: £10,000<br />

Rowan Arts are applying for funding to develop a<br />

dynamic shop space that engages local people who<br />

are in need of training and development through<br />

volunteering opportunities, skills workshops, and<br />

offering space for artists and crafts persons to sell<br />

their work. It will invite other local people to donate<br />

items and skills. £10,000 has been as match funding<br />

for a Big Lottery Reaching Communities bid.<br />

To provide volunteering and training and the<br />

development of new skills and work experience<br />

opportunities. Once the model is deemed to be<br />

successful, Rowan Arts will approach other funders<br />

to support it on an ongoing basis. Other local<br />

organisations will also be supported to promote<br />

their work and the hyperlocal websites.<br />

Sue Davies pitch relocation/replacement<br />

Category: Estate <strong>improvement</strong>s<br />

Sub-category: Leisure / play space<br />

Priority: 2 - Medium<br />

Approx cost: £995,000<br />

Funds secured: £70,000<br />

To relocate/replace the Sue Davies pitch from the rear<br />

of Old Andover to Corker Walk / Seven Sisters Road<br />

with a modern, fit for purpose, sound proofed, semisunken<br />

Astroturf/G3 pitch as well as building an<br />

ancillary administrative light-weight prefabricated<br />

building with classroom, cafe and other facilities. The<br />

scheme also includes landscaping and provisioning of<br />

play-space and an outdoor gym.<br />

Alternatively option, if less funding was available,<br />

would be just to refurbish the football pitches and kick<br />

about areas on the estates (approx. cost: £150k).<br />

The scheme will benefit all residents in <strong>Finsbury</strong><br />

<strong>Park</strong> Ward.<br />

- Residents on the Andover Estate and Birnam<br />

Road, the Andover Futures Forum, <strong>Finsbury</strong> <strong>Park</strong>'s<br />

Safer Neighbourhoods Team, council officers and<br />

<strong>ward</strong> councillors agree that the ASB and criminal<br />

activities going on at the football pitch need to be<br />

resolved.<br />

- Relocating the Sue Davies pitch to Corker<br />

Walk/Seven Sisters Rd is the "linchpin" to unlock<br />

land that will enable the development of 150-170<br />

new homes on the Andover within the context of<br />

the Andover Estate Development Plan.<br />

- Arsenal wish to use this for community football<br />

training ('Arsenal Positive Futures' community<br />

coaching scheme) which will involve not only the<br />

estate children but children from all over the local<br />

area could be met while avoiding the ASB and<br />

neighbour complaints occasioned by the Sue<br />

Davies Playground.<br />

24 June 2013 Page 85


Andover Estate - tree management project<br />

Category: Estate <strong>improvement</strong>s<br />

Sub-category: Open space / green space<br />

Priority: 3 - Low<br />

Approx cost: £10,000<br />

Funds secured: £0<br />

To prune remaining trees in an effort to support the<br />

other security projects for the installation of addition<br />

CCTV on the estate.<br />

As part of our programme of security initiatives for<br />

the Andover Estate, LBI Housing in conjunction<br />

with the Tree Services at LBI have recently<br />

completed a scheme which saw the pruning of<br />

some 50 trees on the estate. This was part of the<br />

wider security works programme. There is still a<br />

requirement for additional funding to lower more of<br />

the tree stock on the estate. It was identified that<br />

there was a requirement to have these works<br />

carried out in order to support the installation of<br />

new lighting and the CCTV system. This figure<br />

equates to some 25% of the overall quantity of<br />

trees on the estate. We are now seeking an<br />

additional £10k to complete the tree pruning<br />

programme as all local budgets have been<br />

exhausted in the process.<br />

Coleridge Road streetscape <strong>improvement</strong>s<br />

Category: Transport and streetscape<br />

Sub-category: Streetscape<br />

Priority: 3 - Low<br />

Approx cost: £200,000<br />

Funds secured: £0<br />

Streetscape <strong>improvement</strong>s, including DDA works,<br />

footway renewal, de-cluttering of street furniture,<br />

possible tree <strong>plan</strong>ting, replacement of road humps with<br />

sinusoidal profile for cyclists (road is main cycle route),<br />

carriageway resurfacing for ease of movement for both<br />

cyclists and vehicles.<br />

Improve the environment for pedestrians.<br />

CPZ IS-J Area parking review<br />

Category: Transport and streetscape<br />

Sub-category: <strong>Park</strong>ing<br />

Priority: 3 - Low<br />

Approx cost: £78,500<br />

Funds secured: £0<br />

Review of CPZ IS-J. All the signs (at bay and zone<br />

entry) will need to changed to reflect any changes.<br />

Cover stickers cannot be used as these will bleach in<br />

time and will effect enforcement capabiities. The<br />

zones in the matchday area have similar enforcement<br />

times apart from CPZ IS-J having full Saturday<br />

enforcement as opposed to ending at 1.30pm. Careful<br />

consideration needs to given to reviews of zones in<br />

isolation to ensure they cause no adverse parking<br />

impacts on adjacent zones.<br />

To review the zone to ensure it provides benefits to<br />

residents with particular focus on hours of<br />

operation (possibly to match surrounding zones).<br />

24 June 2013 Page 86


Eburne Road disabled parking<br />

Category: Transport and streetscape<br />

Sub-category: Highway maintenance<br />

Move one disabled parking space and replace with<br />

double yellow lines. Remove kerb build out to create<br />

turning head.<br />

Resident cars being damaged due to poor road<br />

layout. No turning head for emergency services.<br />

Priority:<br />

Approx cost:<br />

3 - Low<br />

£6,500<br />

Funds secured: £0<br />

<strong>Finsbury</strong> <strong>Park</strong> principle routes streetscape<br />

<strong>improvement</strong>s<br />

Category:<br />

Sub-category:<br />

Priority:<br />

Approx cost:<br />

Funds secured: £0<br />

Transport and streetscape<br />

Streetscape<br />

3 - Low<br />

£1,000,000<br />

Streetscape <strong>improvement</strong>s to main thoroughfares<br />

incuding Seven Sisters Road, Stroud Green Road and<br />

Holloway Road; possible works to include DDA works,<br />

footway renewal, decluttering of street furniture,<br />

possible lighting enhancement, tree <strong>plan</strong>ting, and<br />

public art, designed to improve community safety and<br />

public confidence in using public space. £1m is a<br />

conservative estimate of how much it would cost to<br />

make any significant <strong>improvement</strong> to these streets.<br />

Improvements would also need the co-operation of<br />

Transport for London, and would need to be<br />

implemented by TfL.<br />

Community safety is the Partnership's top priority.<br />

<strong>Finsbury</strong> <strong>Park</strong> station access<br />

Category: Transport and streetscape<br />

Sub-category: Public transport<br />

Measures to improve pedestrian access between<br />

stations, bus stops and walking routes on borough<br />

roads.<br />

To ensure easy pedestrian access between<br />

various modes of transport at interchanges.<br />

Priority:<br />

Approx cost:<br />

3 - Low<br />

£150,000<br />

Funds secured: £0<br />

24 June 2013 Page 87


<strong>Finsbury</strong> <strong>Park</strong> <strong>ward</strong> bus facilities<br />

Category: Transport and streetscape<br />

Sub-category: Public transport<br />

Review of bus provision on a <strong>ward</strong> by <strong>ward</strong> basis to<br />

establish current bus services and <strong>improvement</strong>s<br />

required to serve local residents.<br />

Many local residents rely on buses as their main<br />

form of transport. By providing evidence and a<br />

suitable strategy we will be in a stronger position to<br />

petition TfL for <strong>improvement</strong>s to bus services.<br />

Priority:<br />

Approx cost:<br />

3 - Low<br />

£10,000<br />

Funds secured: £0<br />

<strong>Finsbury</strong> <strong>Park</strong> <strong>ward</strong> cycling <strong>improvement</strong>s<br />

Category: Transport and streetscape<br />

Sub-category: Walking / cycling<br />

Priority: 3 - Low<br />

Approx cost: £320,000<br />

Funds secured: £0<br />

To provide an improved, safer cycling environment in<br />

the borough. This includes removal of barriers to<br />

cycling, such as one-way streets and "No Entry" points<br />

to allow cycling on less trafficked roads (approx 8<br />

sites, £100,000). This also includes improving<br />

infrastructure by providing enhancements such as<br />

Advanced Stop Lines (ASLs), cycle lanes/tracks, cycle<br />

logo on-street markings and signage where<br />

appropriate (approx 11 sites, £220,000).<br />

The <strong>Council</strong> aims to increase cycling, and to do so,<br />

must address the range of barriers faced by<br />

cyclists and those who wish to cycle. Costeffective<br />

investment will target funding at specific<br />

barriers and will ensure that there is a reduction in<br />

casualties despite any increase in cycling.<br />

<strong>Finsbury</strong> <strong>Park</strong> <strong>ward</strong> speed management<br />

Category: Transport and streetscape<br />

Sub-category: Road safety<br />

Priority: 3 - Low<br />

Approx cost: £20,000<br />

Funds secured: £0<br />

To implement measures to address any speeding<br />

issues that may be occuring following the<br />

implementation of the borough wide 20mph speed limit<br />

scheme. Possible measures include new vehicle<br />

activated signs, visual road narrowings, additional<br />

20mph road markings and resident community<br />

enforcement programmes.<br />

A figure of £20K is proposed for each <strong>ward</strong> to be<br />

allocated to roads as highlighted in the surveys being<br />

undertaken to identify the most at risk locations.<br />

The recently introduced 20mph limit will be most<br />

effective if any areas of non-compliance are<br />

highlighted and remedial measures undertaken. As<br />

part of the review of the borough 20mph limit<br />

scheme speed surveys are being undertaken postimplementation<br />

to establish which roads have<br />

speed limits which are not complying with the new<br />

limit and identify measures to improve this.<br />

24 June 2013 Page 88


Isledon Road Gardens play area<br />

Category: Open space / green space<br />

Sub-category: Leisure / play space<br />

Priority: 3 - Low<br />

Approx cost: £60,000<br />

Funds secured: £0<br />

Increase play value of existing play area by replacing<br />

some of the existing play equipment and/or adding<br />

more natural play opportunities.<br />

The existing play area is in reasonable condition<br />

but the play value needs to be improved. The<br />

project is identified as a medium priority in the<br />

Greenspace Play Areas Audit and Action Plan,<br />

indicating that its physical condition and<br />

developmental and engagement value could be<br />

enhanced.<br />

Manor Gardens streetscape <strong>improvement</strong>s<br />

Category: Transport and streetscape<br />

Sub-category: Streetscape<br />

Priority: 3 - Low<br />

Approx cost: £280,000<br />

Funds secured: £0<br />

Footway reconstruction, for de-cluterring and design in<br />

line with <strong>Islington</strong> Streetbook.<br />

Manor Gardens has been highlighted as a route<br />

which requires renewal as identified by condition<br />

surveys. Footways and carriageway require further<br />

works to improve access to local businesses and<br />

transport links.<br />

Stroud Green Road road safety measures<br />

Category: Transport and streetscape<br />

Sub-category: Road safety<br />

Priority: 3 - Low<br />

Approx cost: £300,000<br />

Funds secured: £0<br />

Accident reduction, road safety and environmental<br />

<strong>improvement</strong>s for vulnerable road users (incl.<br />

pedestrians and cyclists)<br />

The borough now has a 20mph limit on all borough<br />

roads except Principal Roads (still 30mph). In view<br />

of the volume of pedestrian and vehicular traffic on<br />

these Principal Roads, and recent casualty data, it<br />

is expected that the majority of accidents will occur<br />

there; therefore, further investment is required to<br />

maintain a continuing reduction in the number of<br />

casualties.<br />

24 June 2013 Page 89


Andover Community Centre - internal<br />

decorations<br />

Internal decorations and replacement of doors<br />

throughout centre<br />

Andover CC is a well used centre with hub status in<br />

the borough and requires redecoration throughout.<br />

Category:<br />

Sub-category:<br />

Priority:<br />

Approx cost:<br />

Community facilities<br />

Community space<br />

4 - To be prioritised<br />

£30,000<br />

s106 allocated from 89-219 Isledon Rd (£25k + any<br />

remaining funds from the community cafe allocation,<br />

07/2012) have been allocated to<strong>ward</strong>s <strong>improvement</strong>s<br />

to the Andover Community Centre<br />

All doors within the community centre are of a poor<br />

quality and and an age where replacement could<br />

be deemed as needed.<br />

Funds secured: £25,000<br />

Annette Road - Contraflow cycling<br />

Category: Transport and streetscape<br />

Sub-category: Walking / Cycling<br />

Priority: 4 - To be prioritised<br />

Approx cost: £15,000<br />

Funds secured: £0<br />

Provide contraflow cycle facilities in Annette Road<br />

between Arthur Road and Tollington Road.<br />

Note: Cost of £15000 is subject to consultation / could<br />

change.<br />

Contraflow cycling on this section of Annette Road<br />

would provide a useful link to the communities<br />

either side of Tollington Road<br />

Note: Request for scheme came from ICAG<br />

(<strong>Islington</strong> Cyclists' Action Group)<br />

Bennett Court playground<br />

New play equiment<br />

Request by TRA<br />

Category:<br />

Sub-category:<br />

Priority:<br />

Approx cost:<br />

Estate <strong>improvement</strong>s<br />

Leisure / play space<br />

4 - To be prioritised<br />

£40,000<br />

Funds secured: £0<br />

24 June 2013 Page 90


<strong>Finsbury</strong> <strong>Park</strong> Community Arts<br />

Category: Community facilities<br />

Sub-category: Arts<br />

Priority: 4 - To be prioritised<br />

Approx cost: £175,000<br />

Funds secured: £90,000<br />

Support for community arts in <strong>Finsbury</strong> <strong>Park</strong>, including:<br />

- Public art/heritage project to utilise hoardings,<br />

streetscape, station tunnels etc to create temporary<br />

exhibition (~£35k)<br />

- Public Arts Programme / bursary to commission<br />

artwork from new/emerging artist or arts organisations<br />

(~£50k)<br />

- Development of community facilities/ contemporary<br />

public gallery space (~£90k)<br />

(Projects could be connected with John Jones site)<br />

* To engage local residents in contemporary art /<br />

heritage of local art<br />

* To develop residents' core skills in reading and<br />

writing and visual literacy linked to the Word<br />

Festival, reading strategy and Platform Youth Hub<br />

* Public art / gallery space under-represented in<br />

area<br />

£90k for development of community facilities /<br />

contemporary public gallery space has been<br />

secured in principle through an agreement with the<br />

developers of the John Jones site.<br />

Friends of The Royal Northern Gardens -<br />

Weekly Craft Club<br />

Category:<br />

Sub-category:<br />

Priority:<br />

Approx cost:<br />

Funds secured: £0<br />

Community facilities<br />

Community support funding<br />

4 - To be prioritised<br />

£4,880<br />

This club would be coordinated by a craft club leader<br />

who would run and organise themed sessions for<br />

parents and their children (from April 2012). We<br />

specifically would like to continue to target isolated and<br />

vunerable parents who have children under the age of<br />

5. Our target group would include recent migrants,<br />

socially isolated and single parents. The funding would<br />

be used for an event room hire, fees for the club<br />

leader, advertising and materials.<br />

The North Library used to run a craft club, this ran<br />

in 2009/2010. Unfortunately, the funding for it<br />

ceased. The members were from a variety of<br />

social backgrounds, a number of them migrants,<br />

single parents and socially isolated parents who<br />

had found a safe, educative, inclusive environment<br />

to meet other parents. We would like to continue<br />

this environment in order to build on capacity<br />

building in the community for knowledge exchange<br />

among new parents and providing an alternative<br />

environment to the home in order to prevent<br />

isolation.<br />

Hercules Street - contraflow cycle route<br />

Category: Transport and streetscape<br />

Sub-category: Walking / cycling<br />

Priority: 4 - To be prioritised<br />

Approx cost: £12,500<br />

Funds secured: £0<br />

Provide contraflow cycle route in Hercules Street.<br />

Hercules Street N7 is currently one way from<br />

Holloway Road.<br />

Note: Request for scheme came from ICAG<br />

(<strong>Islington</strong> Cyclists' Action Group)<br />

24 June 2013 Page 91


Funded and Completed<br />

<strong>Finsbury</strong> <strong>Park</strong><br />

Scheme location and details Description of scheme Why Investment is needed<br />

Bennett Court Community Centre - internal<br />

decoration<br />

Category:<br />

Sub-category:<br />

Priority:<br />

Approx cost:<br />

Funds secured: £0<br />

Estate <strong>improvement</strong>s<br />

Community space<br />

£15,000<br />

Internal decoration to community centre.<br />

Bennett Court CC is currently well utilised,<br />

particularly for asuccessful children’s nursery. The<br />

internal decoration to the centre has not been<br />

completed for several years. Users of the centre<br />

complain that walls are in disprepair, ceilings<br />

cracking and the general feel of the centre is<br />

unwelcoming. An internal decoration programme<br />

would improve users' enjoyment of the centre and<br />

increase usage.<br />

Andover Community Centre - feasibility study<br />

Category: Community facilities<br />

Sub-category: Community space<br />

Priority: 1 - High<br />

Approx cost: £35,000<br />

Funds secured: £35,000<br />

Feasibility study for creation of social enterprise 'café<br />

on the square'.<br />

S106 funds allocated from from 189-219 Isledon Rd<br />

(up to £35k, 07/2012) for development of a 'community<br />

café' social enterprise / employment training facility<br />

(subject to a feasibility study)<br />

To provide training and job opportunities for local<br />

people.<br />

24 June 2013 Page 217


<strong>Finsbury</strong> <strong>Park</strong> Community Hub<br />

Category: Community facilities<br />

Sub-category: Community support funding<br />

Priority: 1 - High<br />

Approx cost: £165,000<br />

Funds secured: £165,000<br />

To increase the breadth and width of services provided<br />

to the community directly and in partnership with other<br />

statutory and voluntary organisations. To develop,<br />

expand and support the range of services already<br />

provided and include new services proposed by LBI,<br />

the board of directors and requested by the community<br />

at large. (Core funding provided by LBI for the basic<br />

operation of the Hub.)<br />

S106 allocated to<strong>ward</strong>s <strong>Finsbury</strong> <strong>Park</strong> Community Hub<br />

employment and training and regeneration<br />

programmes from 189-219 Isledon Rd (£105k,<br />

01/2013)<br />

Core funding covers remainder (£60k)<br />

The services offered to the community are based<br />

on established needs, feedback from the<br />

community and are an expression of the <strong>Council</strong>’s<br />

Core Objectives and the Priorities and<br />

Recommendations of LBI’s Fairness Commission<br />

Report.<br />

<strong>Finsbury</strong> <strong>Park</strong> <strong>ward</strong> project support funding<br />

Category: Community facilities<br />

Sub-category: Community support funding<br />

Priority: 1 - High<br />

Approx cost: £45,000<br />

Funds secured: £45,000<br />

Running cost of <strong>ward</strong> project, incorporating some<br />

project money. This would likely be £22,500 per year<br />

over a two year period (including on costs).<br />

To be funded by LBI Housing.<br />

To support local physical regeneration and<br />

community engagement.<br />

24 June 2013 Page 218


<strong>Finsbury</strong> <strong>Park</strong> <strong>ward</strong> estate <strong>improvement</strong>s<br />

Category: Estate <strong>improvement</strong>s<br />

Sub-category: Open space / green space<br />

Priority: 2 - Medium<br />

Approx cost: £200,000<br />

Funds secured: £0<br />

To resolve issues of anti-social behaviour created by<br />

poorly designed and/or redundant public spaces, this<br />

proposal would enhance the amenity of local housing<br />

estates by improving public spaces. Schemes could<br />

range from small scale projects (play areas,<br />

community gardens, lighting, seating, landscaping etc)<br />

to more ambitious schemes to upgrade green spaces,<br />

provide new leisure facilities or re-allocate space from<br />

other redundant uses such as excess parking.<br />

Selection of locations would take into account potential<br />

future housing expansion.<br />

The cost per scheme will vary greatly depending on<br />

what is required. If prioritised, further investigation<br />

would be required to identify the specific measures to<br />

be implemented on each estate. This would involve<br />

working closely with residents and other stakeholders<br />

at the estates to identify these details.<br />

Suggested estates for consideration in this <strong>ward</strong><br />

include the Andover Estate.<br />

To resolve issues of anti-social behaviour created<br />

by poorly designeed and/or redundant public<br />

spaces. To create improved public space on<br />

estates and to increase the use of these spaces,<br />

particularly by the wider community.<br />

Kinloch Street open space<br />

Category: Open space / green space<br />

Sub-category: Leisure / play space<br />

Priority: 2 - Medium<br />

Approx cost: £213,562<br />

Funds secured: £213,562<br />

Replace existing play equipment and introduce more<br />

natural play opportunities. Recently, site lines have<br />

been improved and some small scale landscape<br />

works, but the play equipment has not been replaced.<br />

S106 allocated<br />

- from 189-219 Isledon Rd (£180k, 07/2012) to<strong>ward</strong>s<br />

<strong>improvement</strong>s to Kinloch Street Gardens and the open<br />

space around the Sobell Leisure Centre<br />

- from The Globe public house, 107 Tollington Rd<br />

(£33,562.96, 03/2013)<br />

The existing play area is not in good condition and<br />

needs to be replaced. It is identified as a high<br />

priority in the Greenspace Play Areas Audit and<br />

Action Plan, indicating that it is in poor physical<br />

condition, lacks developmental and engagement<br />

value, and/or is in an area of high deprivation.<br />

24 June 2013 Page 219


<strong>Park</strong> Theatre, Clifton Terrace<br />

Category: Community facilities<br />

Sub-category: Arts<br />

Priority: 2 - Medium<br />

Approx cost: £400,000<br />

Funds secured: £400,000<br />

This major new development in <strong>Finsbury</strong> <strong>Park</strong> will see<br />

the development of a new theatre space. We are<br />

currently raising £400,000 in order to fund a dedicated<br />

education floor on site. This would be a facility in which<br />

to engage with both young people and older members<br />

of the community through a range of educational<br />

programmes. These will include community plays, over<br />

60s playreading sessions, workshops for schools, a<br />

regular saturday school and summer school and a<br />

young writers' programme. The theatre may work in<br />

partnership with <strong>Islington</strong> Community Theatre.<br />

To extend its <strong>plan</strong>s for its education programme, the<br />

organisation has raised the required £400,000 through<br />

donations and £10,000 of s106 from LB <strong>Islington</strong>.<br />

<strong>Finsbury</strong> <strong>Park</strong> is one of the most deprived areas of<br />

<strong>Islington</strong> and has been crying out for better<br />

facilities for a long time. The focus is on nurturing<br />

people within a professional theatre context and<br />

making them feel part of the building.<br />

<strong>Islington</strong> <strong>Council</strong> helped support the theatre's<br />

fundraising activities with an early contribution of<br />

£10,000 of s106 funding from 3-5 Thane Villas<br />

(10k, 07/2012)<br />

Seven Sisters Road / Sussex Way<br />

Category: Transport and streetscape<br />

Sub-category: Streetscape<br />

Priority: 2 - Medium<br />

Approx cost: £100,000<br />

Funds secured: £100,000<br />

Improvements to the 'square' outside the Poundland<br />

shop on Seven Sisters Rd, with inclusion of public art<br />

(possibly neon, £10k). There is scope for involving<br />

local young people through Spring Board (locally<br />

based) and other youth organisations - linking into<br />

existing projects.<br />

s106 allocated from 67-83 Seven Sisters Rd (£100k,<br />

07/2012) to<strong>ward</strong>s streetscape <strong>improvement</strong>s, lighting<br />

and public art near the junction of Sussex Way and<br />

Seven Sisters Road<br />

The area looks run down and delapidated. It is<br />

extremely busy both with pedestrians and cars. It<br />

has become a gathering place for street drinkers.<br />

24 June 2013 Page 220


Six Acres Estate<br />

Category: Estate <strong>improvement</strong>s<br />

Sub-category: Open space / green space<br />

Priority: 2 - Medium<br />

Approx cost: £147,015<br />

Funds secured: £147,015<br />

Landscaping the new plaza which their new buildings<br />

will overlook. The £150k was therefore meant to allow<br />

us to deliver a high-quality scheme similar to the new<br />

Central Square on the Andover Estate, suitable for a<br />

variety of recreational and conmmunity-based uses for<br />

the combined Six Acres, Haden and Clifton estates as<br />

well as the newbuild properties.<br />

S106 allocated from Six Acres Estate (£147,015,<br />

07/2012)<br />

The lighting and concierge-controlled CCTV will<br />

allow us to make the square not just safe, but<br />

welcoming at all times. The external water and<br />

power points will provide the flexibility for<br />

community events and markets, and the highquality<br />

feature <strong>plan</strong>ting will form a suitable<br />

framework for the square. We wish to ensure that<br />

these elements form an integral part of the plaza,<br />

and are not tacked on piecemeal at a later date.,<br />

The existing funding has been allocated for the<br />

estate-wide environmental <strong>improvement</strong>s<br />

associated with security works, and the new layout<br />

formed by the OHG newbuild project, including the<br />

central plaza.<br />

However, the budget was allocated on the belief<br />

that a portion of funding for the main plaza would<br />

come from OHG via the S106 funding allocation.<br />

Bennett Court Community Centre - rewiring<br />

Category: Estate <strong>improvement</strong>s<br />

Sub-category: Community space<br />

Priority: 3 - Low<br />

Approx cost: £20,000<br />

Funds secured: £0<br />

Complete electrical rewire<br />

Bennett Court CC is currently well utilised,<br />

particularly for asuccessful children’s nursery. The<br />

building's electrics are the original electrics. A<br />

rewiring of the system will modernise the centre<br />

and increase security for users if an intercom<br />

system was also introduced to the main entrance<br />

door.<br />

24 June 2013 Page 221


Bennett Court Community Centre - windows<br />

Category: Estate <strong>improvement</strong>s<br />

Sub-category: Community space<br />

Priority: 3 - Low<br />

Approx cost: £33,000<br />

Funds secured: £33,000<br />

Replacement of existing window to double glazed and<br />

renewal of flooring throughout.<br />

S106 allocated from 14-20 Sussex Way (£33,396,<br />

07/2012)<br />

Bennett Court CC is currently well utilised,<br />

particularly for asuccessful children’s nursery.<br />

Windows are original windows and as such offer<br />

no heating retainment nor address climate change<br />

issues surrounding these types of windows. A<br />

replacement to double glazed would enhance the<br />

use of the centre and prove to be more effective.<br />

The current timber flooring is in a poor condition.<br />

Renewing the flooring would increase safe usage<br />

and enhance the centre for users with mobility<br />

issues.<br />

24 June 2013 Page 222

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!