06.03.2014 Views

IRSE News 140 Dec 08.pdf

IRSE News 140 Dec 08.pdf

IRSE News 140 Dec 08.pdf

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

TECHNICAL<br />

<strong>IRSE</strong><br />

TESTS<br />

As soon as components were ready, they<br />

could be tested. The tests were divided up<br />

as shown in Figure 7: Overview of tests.<br />

A: Level 1 system tests in the<br />

laboratory, conducted by ProRail<br />

The aim of these tests was to verify that<br />

the system described in the<br />

implementation guideline functioned in<br />

accordance with ProRail’s expectations.<br />

The tests were carried out on the ERTMS<br />

train simulator at Rail Infra Opleidingen<br />

(railway infrastructure training, RIO) in<br />

Amersfoort. This simulator consists of an<br />

ALSTOM EVC (European Vital Computer) with<br />

the data corresponding to a BR189<br />

locomotive. The Level 1 balise messages<br />

were fed to the EVC by an adapter<br />

computer.<br />

B: Level 1 system tests in the<br />

laboratory, conducted by ALSTOM<br />

These tests verified that the train behaved<br />

in accordance with the implementation<br />

guideline.<br />

C: FAT for programmed LEUs and<br />

balises<br />

Each LEU underwent a complete test,<br />

covering every possible input combination.<br />

The tests verified that all undefined input<br />

combinations resulted in the default<br />

message being sent. All switchable balises<br />

were tested to verify that they were<br />

sending the correct default message, i.e.<br />

the message sent if no valid message is<br />

received from the LEU.<br />

Following successful testing, the LEUs and<br />

balises were handed over to the<br />

construction team. During installation, the<br />

construction team simply had to verify that<br />

the components were functioning correctly<br />

and were installed in the correct locations.<br />

D: Interlocking software laboratory<br />

test.<br />

The controlled sections of the<br />

Havenspoorlijn use the ALSTOM Vital<br />

Processor Interlocking (VPI) system, and all<br />

VPIs had to be modified for Level 1. Once<br />

the software was ready, it was tested using<br />

the Movares VPI simulator. The simulator<br />

obviated the need to assemble a full set of<br />

Figure 7: Overview of tests<br />

VPI hardware just for testing. Following<br />

successful testing, the software was<br />

prepared for installation on site.<br />

E: Pre-installation hardware checks<br />

The changes affected the hardware, as<br />

well as the software. The contractor<br />

prepared all changes to components and<br />

wiring, and these preparations were<br />

verified a few weeks before<br />

commissioning. Following verification, the<br />

system was ready for installation during a<br />

possession.<br />

F: SAT on IXL interfaces and B-relay<br />

logic<br />

These tests required night possessions –<br />

20 weekend nights in all. During the<br />

possessions, the installation was modified<br />

in accordance with the preparations. After<br />

final installation checks were complete,<br />

the changes could undergo static testing.<br />

Functional testing was carried out by<br />

simulating track occupation. Once testing<br />

was complete, it was possible to guarantee<br />

that the existing functionality had not been<br />

impaired and that the new ERTMS Level 1<br />

LEUs were working correctly.<br />

G: LEU and balise commissioning test<br />

Only after the SAT had demonstrated that<br />

the LEUs were working correctly was it<br />

possible to connect the balises in situ and<br />

test them. After connecting the balise to<br />

the LEU, it was necessary to verify that the<br />

LEU was still functioning correctly. This<br />

was indicated by LED indicators on the<br />

LEU. The next step was to verify that the<br />

balise was sending the correct messages.<br />

The purpose of this check was to verify<br />

that the balise was not sending default<br />

messages. This could readily be verified<br />

using the message number (M_COUNT).<br />

H: Functional train tests, conducted by<br />

ProRail<br />

The aim of these tests was to demonstrate<br />

that the Level 1 system would create an<br />

operationally viable situation in practice.<br />

Some of the train tests were conducted<br />

during the day, with the test train running<br />

between revenue-earning services. The<br />

only test runs that had to be carried out<br />

during night possessions were those<br />

involving special scenarios, which could<br />

not be carried out without disrupting other<br />

train movements. For most tests, the train<br />

started from a siding in the Level 1 area.<br />

The test runs were conducted using a<br />

BR203 locomotive with an ALSTOM EVC.<br />

When other on-board equipment is<br />

approved for use in the Netherlands, test<br />

runs will also be carried out with this<br />

equipment.<br />

SAFETY CASE<br />

In order to be able to start using Level 1<br />

after a year’s hard work, a ‘Safety Case<br />

Delivery Strategy’ was required. This plan<br />

listed the documents needed in order to<br />

obtain authorization for use during the<br />

project. An independent team from<br />

ProRail supervised this process and<br />

conducted audits throughout design,<br />

installation and testing.<br />

The first important step in putting<br />

together the safety case was authorisation<br />

to use the principles of design. The<br />

documents required for Level 1 were<br />

compiled by the joint team. For the<br />

existing installation, it was possible to use<br />

the ProRail principles of design for that<br />

installation.<br />

Once this authorization had been<br />

obtained, the engineers could start<br />

designing, installing and testing. During<br />

the design process, audits were carried out<br />

that enabled authorization to be granted<br />

for use of the installation and for tests.<br />

Installation and testing were conducted in<br />

accordance with procedures that have<br />

been applied to ProRail installations for<br />

several years. Following completion of<br />

tests, the engineers submitted all<br />

verification and validation reports to the<br />

independent safety case team.<br />

ProRail also carried out the functional<br />

train tests. Once all tests are completed<br />

successfully, authorization for commercial<br />

service can be granted.<br />

COMPLETION<br />

The combined efforts of all concerned<br />

meant that it was possible to hand over<br />

the Level 1 track equipment, fully tested,<br />

in September 2008. Only a small number<br />

of issues were discovered during testing,<br />

and these were easy to resolve. ProRail<br />

will carry out final testing using a train at<br />

the end of 2008. As things look now, the<br />

track equipment is ready for commercial<br />

service.<br />

<strong>IRSE</strong><br />

NEWS Issue <strong>140</strong> <strong>Dec</strong>ember 2008 11

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!