PART IV – Special Conditions<br />
36. The Bidder is required to give confirmation of their acceptance of Special Conditions of the<br />
RFP mentioned below which will automatically be considered as part of the Contract concluded<br />
with the successful Bidder (i.e. Seller <strong>in</strong> the Contract) as selected by the Buyer. Failure to do so<br />
may result <strong>in</strong> rejection of Bid submitted by the Bidder.<br />
37. Performance Bond/ Bank Guarantee/ Security Deposit. The firm shall submit a<br />
Performance Bank Guarantee (PBG) for 10 % of the total estimated value of the contract <strong>in</strong> favour<br />
of The Pr<strong>in</strong>cipal Controller of Defence Accounts, (Navy), Mumbai issued by a public sector bank or<br />
a private sector bank authorized to conduct government bus<strong>in</strong>ess <strong>in</strong> the prescribed format with<strong>in</strong><br />
10 days from the date of contract/issue of work order. The PBG should rema<strong>in</strong> valid for a period of<br />
sixty days beyond the date of completion of contractual obligations/warranty. The BG will be<br />
returned to the firm on successful completion of all his obligations under the contract/work order.<br />
In case the execution of the contract/work order is delayed beyond the contracted period and the<br />
Client grants extension of delivery period, with or without LD, the supplier must get the BG<br />
revalidated, if not already valid.<br />
38. Option Clause. This contract has an Option Clause, where<strong>in</strong> the Client can exercise an<br />
option to procure an additional 50% of the orig<strong>in</strong>al contracted quantity of items <strong>in</strong> accordance with<br />
the same terms & conditions of the present contract. This will be applicable with<strong>in</strong> the currency of<br />
contract. It will be entirely the discretion of the Client to exercise this option or not.<br />
39. Repeat Order Clause. This contract has a Repeat Order Clause, where<strong>in</strong> the Client can<br />
order upto 50% quantity of the items / services under the present contract with<strong>in</strong> six months from<br />
the date of successful completion of this contract, cost, terms & conditions rema<strong>in</strong><strong>in</strong>g the same. It<br />
will be entirely the discretion of Client to place the Repeat order or not.<br />
40. Tolerance Clause – To take care of any change <strong>in</strong> the requirement dur<strong>in</strong>g the period<br />
start<strong>in</strong>g from issue of RFP till placement of the contract, Buyer reserves the right to ___%<br />
plus/m<strong>in</strong>us <strong>in</strong>crease or decrease the quantity of the required goods up to that limit without any<br />
change <strong>in</strong> the terms & conditions and prices quoted by the Seller. While award<strong>in</strong>g the contract, the<br />
quantity ordered can be <strong>in</strong>creased or decreased by the Buyer with<strong>in</strong> this tolerance limit.<br />
Payment Terms<br />
41. No advance payment will be made. The payment will be made through PCDA (Navy) on<br />
supply<strong>in</strong>g and <strong>in</strong>stallation of completion of the contract as desired by the firm. Bank details<br />
<strong>in</strong>clud<strong>in</strong>g bank A/c No., MICR Code may please be <strong>in</strong>dicated to enable e-payment by PCDA(N)<br />
Mumbai.<br />
42. Pay<strong>in</strong>g Authority. Payment will be made by PCDA (Navy) with<strong>in</strong> 30 days of submission of<br />
the follow<strong>in</strong>g documents by the Firm to the Pay<strong>in</strong>g Authority.<br />
(a)<br />
(b)<br />
unit.<br />
(c)<br />
02 Ink-signed copy of Commercial <strong>in</strong>voice / Firm’s bill.<br />
User Trial Certificate / work completion certificate / User Satisfaction certificate from the<br />
Performance Bank guarantee.<br />
(d) Details for electro<strong>nic</strong> payment viz Account holder’s name, Bank name, Branch name<br />
and address, Account type, Account number, IFSC code, MICR code (if these details are not<br />
<strong>in</strong>corporated <strong>in</strong> contract).<br />
12