[322/03] Francke - Ingenia
[322/03] Francke - Ingenia
[322/03] Francke - Ingenia
You also want an ePaper? Increase the reach of your titles
YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.
INFRASTRUCTURE<br />
approach bridges were produced by<br />
Dragados in Cadiz in Southern Spain<br />
and subsequently towed to Sweden in<br />
pairs, complete with concrete<br />
motorway deck.<br />
The high bridge is carried by a total<br />
of 80 pairs of cables, ten in each<br />
direction from each pylon leg. Each<br />
cable consists of between 68 and 73<br />
strands. A strand consists of seven 5<br />
mm wires. The wires are galvanised,<br />
waxed and encased in plastic casing.<br />
Each cable has a tensile strength of<br />
2,000 tonnes and the combined length<br />
of all cables is about 25 km. The total<br />
weight is about 2,300 tonnes.<br />
Following the inauguration of the<br />
Øresund Fixed Link on 1 July 2000<br />
approximately 500,000 vehicles<br />
crossed the Øresund Bridge during the<br />
first month. Information about traffic<br />
and toll prices etc. can be seen at<br />
www.oeresundsbron.com. The photo<br />
files of the Øresund Bridge are available<br />
at www.bridgephoto.dk. ■<br />
ingenia<br />
28<br />
Figure 7: Side view of bridge to show cable pattern<br />
With a height of 204 metres above<br />
sea level the pylons of the Øresund<br />
Bridge are the tallest concrete<br />
structures in Sweden. The construction<br />
of the pylons began with the placing of<br />
the pylon caissons which had been<br />
cast in a dry dock in Malmö Harbour<br />
and towed to the bridge line. On top of<br />
the caissons the casting of the pylons<br />
was carried out by means of selfclimbing<br />
formwork. The entire casting<br />
process took seven to ten days for<br />
each 4 metre lift.<br />
About 4,335 m 3 of concrete went<br />
into each pylon leg – 220 m 3 per lift in<br />
the first stage and about 34 m 3 per lift<br />
near the top. The concrete was<br />
provided from a batching plant on a<br />
barge moored next to the pylon<br />
cofferdam. Each pylon leg required 800<br />
tonnes of reinforcement which was<br />
prepared in prefabricated cages, and<br />
then lifted into position. The pentagon<br />
shaped pylon legs are solid for the first<br />
17 metres and hollow above that level.<br />
The reinforcement cages for the<br />
cross beams, which connect the pylon<br />
legs approximately 45 metres above<br />
sea level, were built ashore, then lifted<br />
into position for casting. Steel anchor<br />
boxes were also cast into the pylon<br />
legs, to which the cables are attached.<br />
The eight bridge girders for the high<br />
bridge were produced at Karlskrona<br />
shipyard on the East coast of Sweden<br />
and then towed to Malmö, where the<br />
concrete motorway deck was added.<br />
The forty-nine girders for the two<br />
Main contractors on the<br />
Øresund Bridge<br />
Dredging and Reclamation<br />
Öresund Marine Joint Venture:<br />
● Per Aarselff (DK)<br />
● Ballast Nedam Dredging (NL)<br />
● Great Lakes Dredge and Dock<br />
Co. (USA)<br />
The Tunnel<br />
Øresund Tunnel Contractors:<br />
● NCC International (SE)<br />
● Dumez-GTM International (F)<br />
● John Laing (UK)<br />
● E. Pihl & Søn (DK)<br />
● Boskalis Westminster Dredging<br />
(NL)<br />
The Bridge<br />
Sundlink Contractors:<br />
● Skanska (SE)<br />
● Højgaard & Schultz (DK)<br />
● Monberg & Thorsen (DK)<br />
● Hochtief (D)<br />
The Railway<br />
Banverket Industridivisionen (SE)