02.03.2014 Views

[322/03] Francke - Ingenia

[322/03] Francke - Ingenia

[322/03] Francke - Ingenia

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

INFRASTRUCTURE<br />

approach bridges were produced by<br />

Dragados in Cadiz in Southern Spain<br />

and subsequently towed to Sweden in<br />

pairs, complete with concrete<br />

motorway deck.<br />

The high bridge is carried by a total<br />

of 80 pairs of cables, ten in each<br />

direction from each pylon leg. Each<br />

cable consists of between 68 and 73<br />

strands. A strand consists of seven 5<br />

mm wires. The wires are galvanised,<br />

waxed and encased in plastic casing.<br />

Each cable has a tensile strength of<br />

2,000 tonnes and the combined length<br />

of all cables is about 25 km. The total<br />

weight is about 2,300 tonnes.<br />

Following the inauguration of the<br />

Øresund Fixed Link on 1 July 2000<br />

approximately 500,000 vehicles<br />

crossed the Øresund Bridge during the<br />

first month. Information about traffic<br />

and toll prices etc. can be seen at<br />

www.oeresundsbron.com. The photo<br />

files of the Øresund Bridge are available<br />

at www.bridgephoto.dk. ■<br />

ingenia<br />

28<br />

Figure 7: Side view of bridge to show cable pattern<br />

With a height of 204 metres above<br />

sea level the pylons of the Øresund<br />

Bridge are the tallest concrete<br />

structures in Sweden. The construction<br />

of the pylons began with the placing of<br />

the pylon caissons which had been<br />

cast in a dry dock in Malmö Harbour<br />

and towed to the bridge line. On top of<br />

the caissons the casting of the pylons<br />

was carried out by means of selfclimbing<br />

formwork. The entire casting<br />

process took seven to ten days for<br />

each 4 metre lift.<br />

About 4,335 m 3 of concrete went<br />

into each pylon leg – 220 m 3 per lift in<br />

the first stage and about 34 m 3 per lift<br />

near the top. The concrete was<br />

provided from a batching plant on a<br />

barge moored next to the pylon<br />

cofferdam. Each pylon leg required 800<br />

tonnes of reinforcement which was<br />

prepared in prefabricated cages, and<br />

then lifted into position. The pentagon<br />

shaped pylon legs are solid for the first<br />

17 metres and hollow above that level.<br />

The reinforcement cages for the<br />

cross beams, which connect the pylon<br />

legs approximately 45 metres above<br />

sea level, were built ashore, then lifted<br />

into position for casting. Steel anchor<br />

boxes were also cast into the pylon<br />

legs, to which the cables are attached.<br />

The eight bridge girders for the high<br />

bridge were produced at Karlskrona<br />

shipyard on the East coast of Sweden<br />

and then towed to Malmö, where the<br />

concrete motorway deck was added.<br />

The forty-nine girders for the two<br />

Main contractors on the<br />

Øresund Bridge<br />

Dredging and Reclamation<br />

Öresund Marine Joint Venture:<br />

● Per Aarselff (DK)<br />

● Ballast Nedam Dredging (NL)<br />

● Great Lakes Dredge and Dock<br />

Co. (USA)<br />

The Tunnel<br />

Øresund Tunnel Contractors:<br />

● NCC International (SE)<br />

● Dumez-GTM International (F)<br />

● John Laing (UK)<br />

● E. Pihl & Søn (DK)<br />

● Boskalis Westminster Dredging<br />

(NL)<br />

The Bridge<br />

Sundlink Contractors:<br />

● Skanska (SE)<br />

● Højgaard & Schultz (DK)<br />

● Monberg & Thorsen (DK)<br />

● Hochtief (D)<br />

The Railway<br />

Banverket Industridivisionen (SE)

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!